Anchorage Asphalt Paving Co. v. Lewis

629 P.2d 65, 1981 Alas. LEXIS 503
CourtAlaska Supreme Court
DecidedJune 5, 1981
Docket5055
StatusPublished
Cited by19 cases

This text of 629 P.2d 65 (Anchorage Asphalt Paving Co. v. Lewis) is published on Counsel Stack Legal Research, covering Alaska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Anchorage Asphalt Paving Co. v. Lewis, 629 P.2d 65, 1981 Alas. LEXIS 503 (Ala. 1981).

Opinion

OPINION

Before RABINOWITZ, C. J., CONNOR, BURKE and MATTHEWS, JJ., and BLAIR, Superior Court Judge.

MATTHEWS, Justice.

This is the third time the parties in this case have appeared before this court. 1 The present issues on appeal concern the damages awarded J. R. Lewis. Specifically, appellant, Anchorage Asphalt, contends that the trial court erred in valuing Lewis’ damages as of the time of the third trial rather than the date of breach, that the award unjustly enriches Lewis because he failed properly to maintain the roads in question, and that the award of prejudgment interest computed on the 1979 valuation of damages constitutes a double recovery. 2 We reject the first two claims of error and accept the third.

In 1969, appellee, Lewis, contracted with Anchorage Asphalt to pave seven roads in his mobile home park, the Four Seasons Mobiland. The roads began to deteriorate soon after the paving was completed and after April 1970, Lewis discontinued payments on the paving contract, having paid a total of $80,000.00. The contract price was $57,052.50.

Anchorage Asphalt sued on the contract and Lewis counterclaimed for breach of contract. On the second appeal, this court ruled that Anchorage Asphalt was liable for the pavement failure due to its failure to warn Lewis of the inadequacy of the pavement subsurface and remanded the case for a determination of damages. Lewis v. Anchorage Asphalt Paving Company, 579 P.2d 532, 535 (Alaska 1978). Damages were to be determined according to the formula established by this court on the first appeal:

If the court below reaches the issue of damages, they should be limited to those necessary to put Lewis in as good a position as that in which he would have been had such warning been given. Restatement of the Law, Contracts, § 329, Comment a, page 504. Since we have affirmed the trial court’s finding that “preparation of the subgrade” involved only its “grading, shaping and compacting,” damages should not include the costs of excavation and filling, but only the costs of removing the portions of paving that have failed, shaping and compacting the subgrade and replacing that pavement. The amount due and unpaid on the contract will be an offset against those damages, and if the amount due and unpaid exceeds the amount of the damages, Anchorage Asphalt will be entitled to an award for the difference.

Lewis v. Anchorage Asphalt Paving Company, 535 P.2d 1188, 1200 n. 31 (Alaska 1975).

At the third trial, Lewis introduced expert testimony that of the total pavement area of 205,464 square feet, 105,474 square feet had failed and needed reconstruction or patching. Total reconstruction would, naturally, give the best result. Bids were introduced from four paving companies on the cost of total reconstruction during the summer of 1979. Using the lowest of these bids, Lewis’ expert stated it would cost $114,987.00 to reconstruct and patch the road, to achieve a “good result.” The trial court accepted this testimony and awarded damages of $114,987.00. From that amount, the court deducted $28,757.29 which Lewis still owed Anchorage Asphalt on the contract, 3 netting a damage recovery by Lewis of $86,229.71. The court also *68 awarded prejudgment interest on the full amount of the damages from April 9, 1970, plus costs and attorney’s fees.

I. THE DATE OF THE DAMAGE VALUATION.

Anchorage Asphalt contends that the proper time to value damages is at the time of breach or a reasonable time thereafter, and the 1979 valuation used by the trial court was thus error. First, it should be noted that in accordance with the measure of damages mandated by this court, “damages should be the reasonable cost of completion in accordance with the contract specifications.” Lewis v. Anchorage Asphalt Paving Company, 535 P.2d at 1200 n. 81; Davis v. McCall, 568 P.2d 956, 959 (Alaska 1977). The purpose of this rule is to grant the plaintiff what he bargained for under the contract.

As a general rule in contract actions, the date‘ of breach affords the most appropriate time for valuing damages. 4 However, this is not a rule to be applied inflexibly when it undermines the remedial goals of a damage award. 5

A case such as the one at bar, where litigation has been protracted over the length of a decade and the appropriate remedy is the cost of repair, presents a situation where limiting the plaintiff to the time of breach cost or repair has the potential of subverting the remedial purposes of the damage award. Simply put, where inflation has eroded the time of breach monetary valuation of an injury to a fraction of what is required to remedy the plaintiff’s injury, then the time of breach rule may be regarded as inappropriate. Because the circumstances of individual cases differ drastically, it is impractical to adopt a definite point in time to value damages. It has been found preferable to leave the question to the trial court’s discretion. 6 Fairway Builders, Inc. v. Malouf, 124 Ariz. 242, 603 P.2d 513, 526 (Ariz.App.1979); see Restatement of Contracts § 329, Comment a (1932).

In this case, in view of the substantial inflation which took place between 1972, when the full extent of the breakdown of the streets became apparent, and the time of the trial in 1979, 7 we cannot say that the court abused its discretion using 1979 as the date of damage valuation.

In reaching this conclusion we necessarily reject a suggestion not directly made by Anchorage Asphalt, but contained in some of the cases it has cited, that one may be guilty of an unreasonable failure to minimize costs which have increased due solely to inflation. 8 This question has not been frequently addressed by American courts, and those authorities that exist are divided *69 . 9 We believe that the better view is that there is no duty to take action simply to avoid an increase in costs due solely to inflation because such an increase is not a real increase in cost to the defendant, who will be paying the award with money which has also decreased in value. Including a rise in costs due solely to inflation within the duty to minimize damages simply means that the claimant rather than the wrongdoer must bear the risk of inflation. Since this allows the wrongdoer to gain by delaying payment, where allowable prejudgment interest is exceeded by inflation, we see nothing to recommend it.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kilpatrick v. Wiley, Rein & Fielding
2001 UT 107 (Utah Supreme Court, 2001)
Camacho v. L & T International Corp.
4 N. Mar. I. 323 (Sup. Ct. of the Comm. of the N. Mariana Islands, 1996)
Tookalook Sales and Service v. McGahan
846 P.2d 127 (Alaska Supreme Court, 1993)
Vineyard Brands, Inc. v. Oak Knoll Cellar
587 A.2d 77 (Supreme Court of Vermont, 1990)
Pinellas County v. Interpace
41 Fla. Supp. 2d 65 (Florida Circuit Courts, 1990)
Merdes v. Underwood
742 P.2d 245 (Alaska Supreme Court, 1987)
Morris v. Morris
724 P.2d 527 (Alaska Supreme Court, 1986)
Alaska Statebank v. Fairco
674 P.2d 288 (Alaska Supreme Court, 1983)
Bevins v. Peoples Bank & Trust Co.
671 P.2d 875 (Alaska Supreme Court, 1983)
Gilman v. Martin
662 P.2d 120 (Alaska Supreme Court, 1983)
Sebring v. Colver
649 P.2d 932 (Alaska Supreme Court, 1982)
Farnsworth v. Steiner
638 P.2d 181 (Alaska Supreme Court, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
629 P.2d 65, 1981 Alas. LEXIS 503, Counsel Stack Legal Research, https://law.counselstack.com/opinion/anchorage-asphalt-paving-co-v-lewis-alaska-1981.