Pinellas County v. Interpace

41 Fla. Supp. 2d 65
Circuit Court for the Judicial Circuits of Florida·Decided June 6, 1990·No. Case No. 83-13313-08·Published

Opinion

OPINION OF THE COURT

FRED BRYSON, Circuit Judge.

FINDINGS OF FACT, CONCLUSIONS OF LAW, AND FINAL JUDGMENT FOR PLAINTIFF, PINELLAS COUNTY

THIS CAUSE is before the Court for determination upon Plaintiff, PINELLAS COUNTY’S, First Amended Complaint claiming that a thirteen and one-half mile segment of its major water transmission main made of 54-inch and 60-inch diameter prestressed concrete pipe is defective and should be replaced. The prestressed concrete pipe was manufactured during 1977 and 1978 by a nationally known pipe manufacturer known as Interpace Corporation. On May 3, 1985 Interpace Corporation changed its name to Madison Management Group, Inc. In July of 1987, Clevepak Corporation merged with Madison Management Group, Inc. Therefore, the Defendant, MADISON MANAGEMENT GROUP, INC., is properly before the Court [67] as a successor to INTERPACE CORPORATION and throughout the remainder of these Findings will be referred to as “INTERFACE”.

In March of 1975 Pinellas County executed an agreement with a consulting engineering firm known as Black, Crow and Eidsness, Inc. to design the pipeline, select the pipeline’s route, draw all contracts necessary to the letting of bids including contracts with the pipe manufacturer, test the materials which were to be used in the manufacturing of the prestressed pipe, and to sufficiently inspect the pipe as it was being manufactured and after installation. The engineer’s main charge was to protect Pinellas County against improper manufacturing and installation of the pipeline. After the pipeline’s construction, Black, Crow & Eidsness, Inc. (BC&E) changed its name to CH2M Hill Southeast, Inc. Throughout the remainder of these Findings the Defendant engineer will be referred to as “CH2M Hill”.

In sum, the individual pieces of prestressed concrete pipe, both 54-inch and 60-inch in diameter, were to be manufactured by Interpace at its Lacooochee plant located in Lacoochee, Pasco County, Florida, who would in turn deliver the pipe to Suwanee Transfer and Storage, Inc. for hauling to the laying site to be installed by another contractor known as Bumby & Stimpson, Inc. CH2M Hill’s contractual obligation was to design the pipeline, review and approve the plans and specifications submitted by Interpace for the construction of the pipe, review certain component part tests which were to be submitted by the manufacturer, Interpace, draw the contract between Pinellas County and Interpace, and to certify to Pinellas County that the pipeline had been constructed according to the plans and specifications. There are other contractual duties assumed by CH2M Hill which will be referred to in these Findings which bear upon the question of breach of contract and negligence of CH2M Hill.

The Court started hearing testimony in the case on January 17, 1989, with testimony having been concluded on January 24, 1990. There have been 131 days of trial during the time. The case is purported to be one of the longest if not the longest case ever heard in Florida. There have been 1,567 exhibits admitted into evidence.

As trier of the facts, the Court has been required to learn and apply a substantial number of engineering and water production disciplines including metallurgy, wire making and drawing, the manufacture of large diameter prestress pipe, pipeline design, pipeline testing, the mathematical formulas associated with pipeline manufacture and design, hydraulics, structures, petrographies (the study of concrete and mortar), chemistry (as applied to groundwater, metallurgy and petro[68] graphics), corrosion, principles of water supply to a large populated county, statistics and population forecasting, computer programs depicting a water supply system, and interpretation and application of the national standard for manufacturing prestressed pipe known as AWWA C301-72 and various American standards testing metallurgical standards applicable in the case such as ASTM A227-71 and ASTM A648-73.

The County has sued the manufacturer Interpace upon several legal theories for providing to Pinellas County a prestressed concrete pipeline which does not have the specified operating pressure of 150 psi and surge pressure of 210 psi, and which is otherwise claimed defective in not complying with the specifications for manufacture of the pipe. Punitive damages are also sought from Interpace based upon the theories of fraud, strict liability in tort, and willful and wanton misconduct. Pinellas County has also sued its engineer whose duty was to protect the County has also sued its engineer whose duty was to protect the County from the manufacturer providing pipe which failed to meet the specified and the required pressure rating and defective pipe. Damages for the cost of the replacement of the pipeline are sought from both Defendants. Pinellas County also sues CH2M Hill for the cost of coal tar epoxy coating the pipeline which the County asserts should have been included by the engineers in the specifications because of the aggressive soil and groundwater attack to which the present pipeline is being subjected. In addition, Pinellas County has sued CH2M Hill for improperly designing certain vacuum relief valves at below ground level in vaults along the pipeline, claiming it was necessary to raise the valves above ground level to present the contamination of the pipeline with groundwater which had accumulated in the vaults. The County claims that the valves would not operate properly to prevent surges in the line when filled with water. Pinellas County claims further damages for replacement of burst pipe, failed tapped pipe and leaking pipe. After serious consideration and deliberation, the Court finds fo the Plaintiff, Pinellas County, and against the Defendant on all counts.

A. CONSTRUCTION STEPS OF PRESTRESSED CONCRETE STEEL CYLINDER PIPE

Free access — add to your briefcase to read the full text and ask questions with AI

Pinellas County v. Interpace, 41 Fla. Supp. 2d 65 (Fla. Super. Ct. 1990).

41 Fla. Supp. 2d 65 (Pinellas County v. Interpace) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Edward F. Krull v. The Celotex Corporation
827 F.2d 80 (Seventh Circuit, 1987)
US Home Corp. v. Suncoast Utilities
454 So. 2d 601 (District Court of Appeal of Florida, 1984)
Linehan v. Everett
338 So. 2d 1294 (District Court of Appeal of Florida, 1976)
Vokes v. Arthur Murray, Inc.
212 So. 2d 906 (District Court of Appeal of Florida, 1968)
Scarfone v. Marin
442 So. 2d 282 (District Court of Appeal of Florida, 1983)
Bell v. Harrington Manufacturing Co.
219 S.E.2d 906 (Supreme Court of South Carolina, 1975)
Northern Power & Engineering Corp. v. Caterpillar Tractor Co.
623 P.2d 324 (Alaska Supreme Court, 1981)
Valley Iron & Steel Co. v. Thorin
562 P.2d 1212 (Oregon Supreme Court, 1977)
Anchorage Asphalt Paving Co. v. Lewis
629 P.2d 65 (Alaska Supreme Court, 1981)
Rhode Island Turnpike & Bridge Authority v. Bethlehem Steel Corp.
379 A.2d 344 (Supreme Court of Rhode Island, 1977)
Oldham's Farm Sausage Co. v. Salco, Inc.
633 S.W.2d 177 (Missouri Court of Appeals, 1982)
Allegheny Mutual Casualty Company v. State
176 So. 2d 362 (District Court of Appeal of Florida, 1965)
Parks v. Zitnik
453 So. 2d 434 (District Court of Appeal of Florida, 1984)
Temple Beth Sholom v. Thyne Const. Corp.
399 So. 2d 525 (District Court of Appeal of Florida, 1981)
Bay Management, Inc. v. Beau Monde, Inc.
366 So. 2d 788 (District Court of Appeal of Florida, 1978)
Malver v. Sheffield Industries, Inc.
502 So. 2d 75 (District Court of Appeal of Florida, 1987)