Maskel Construction Co. v. Town of Glastonbury

264 A.2d 557, 158 Conn. 592, 1969 Conn. LEXIS 636
CourtSupreme Court of Connecticut
DecidedDecember 22, 1969
StatusPublished
Cited by10 cases

This text of 264 A.2d 557 (Maskel Construction Co. v. Town of Glastonbury) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Maskel Construction Co. v. Town of Glastonbury, 264 A.2d 557, 158 Conn. 592, 1969 Conn. LEXIS 636 (Colo. 1969).

Opinion

House, J.

This action was brought by the plaintiff against the town of Glastonbury for compensation for services and materials claimed to be due under the provisions of a sewer construction contract. The contract, known as a unit price contract, was one in which a bidder did not submit a bid on the project at a total price but rather submitted a bid for each unit item to be installed, the total cost being subsequently determined by the number of such units *594 ordered by the defendant’s sewer authority and installed by the contractor. The defendant supplied the bidders with maps or plans and specifications of the proposed sanitary sewer system and invited bids for a unit price contract. The plaintiff was the successful bidder and was awarded the contract.

Two provisions of the contract are of special significance in this case. One related to a term known in sewer construction as “conflict.” A “conflict” is defined as a situation where the designed sewer comes into conflict or is obstructed by what is actually found to exist in the ground and which was not shown on the plan or map. The contract anticipated the discovery of conflicts in the course of the work, and the defendant expressly disclaimed the completeness and accuracy of the underground structures indicated in the drawings on the basis of which bids were solicited. 1 Another section of the contract provided that the work should be constructed under the supervision of an engineering firm to whom all questions arising as to performance of the contract should be referred for decision and whose judgment exercised in reasonable discretion should be final and *595 accepted by tbe contractor and the tow in all cases. 2

When tbe construction was completed tbe plaintiff made claims for additional compensation, asserting that extra work was required because the plans, maps and specifications provided by the defendant, which were part of the contract, described physical conditions which differed from those encountered in tbe field when construction commenced. Pursuant to the provisions of the contract, the supervising engineer made decisions on all of tbe claims made by the plaintiff. Some of these claims were paid by the town in accordance with such decisions and are not involved in this action. Six claims decided adversely to the contentions of the plaintiff and one claim decided in favor of the plaintiff hut only partially paid by the defendant were pressed by the plaintiff in this action. The court found for the plaintiff on all seven claims and rendered judgment for $12,066.16 damages. It is from this judgment that the defendant has appealed.

Five of the plaintiff’s seven claims pressed in this case arose from the existence of conflicts. The court concluded that where a conflict is unexpectedly discovered it is the custom of the trade in sewer con *596 strnction for the owner or municipality to be charged with the extra cost of solving the conflict problem, that as a matter of interpretation the contract contemplated that the defendant town should pay any extra cost arising from the existence of a conflict and that the engineer was arbitrary and unreasonable in his decisions on these claims of the plaintiff. We find no factual basis whatsoever in the court’s finding to support its conclusion as to any custom in the trade. Even if the existence of such a custom in the sewer construction trade had been proved, it nevertheless could not vary the specific terms of the contract, which, as we have noted (footnote 1), expressly stated that the possible conflicts indicated on the drawings were neither accurate nor complete and that it should be the responsibility of the contractor to move and relocate any conflicts in accordance with the direction of the engineers or the official responsible for the service. “After this, to permit oral testimony, or prior or contemporaneous conversation, or circumstances, or usages &c., in order to learn what was intended, or to contradict what is written, would be dangerous and unjust in the extreme.” Glendale Woolen Co. v. Protection Ins. Co., 21 Conn. 19, 37.

Not only did the defendant expressly disclaim any warranty as to the existence or nonexistence of any conflicting underground structures, but it affirmatively represented that the information indicated in the drawings, while containing all obtainable information, was “neither complete nor accurate.” “The defendant was entitled to limit its commitment to bidders, and it clearly brought home to them that it was making no representation as to the . . . conditions which might be found in the actual performance of the work.” Construction Aggregates Corpo *597 ration v. State, 148 Conn. 315, 325, 170 A.2d 274. In the face of this warning and disclaimer the plaintiff in submitting its bid took its chances on the number and extent of conflicts which might be discovered in the course of the work.

Finally, and conclusively so far as this aspect of the appeal is concerned, the record discloses that the engineer in accordance with the terms of the contract considered each of the plaintiff’s claims based on the conflicts discovered and in writing rendered his decisions. We find no basis for the court’s conclusion that his decisions were arbitrary and unreasonable nor any justification for the substitution by the court of its own judgment for that of the engineer, whose opinions and judgments, exercised in reasonable discretion, the parties agreed “shall be accepted by the Contractor and Town in all cases.” Here the parties to the contract made a third party, the engineer, the final judge to decide, acting in good faith and in the exercise of his best judgment, when one of the contracting parties had fulfilled the requirements of the contract. “If, in the honest performance of this duty, the engineer has in good faith and in the exercise of his best judgment decided that the . . . [plaintiff was] required to perform the work and furnish the materials in question, in the proper performance of . . . [its] written contract, . . . [it] cannot recover in this suit. Such a decision so rendered by the engineer, that they were a part of the written contract, would be a conclusive decision that they were not extras.” Beattie v. McMullen, 82 Conn. 484, 491, 74 A. 767; see also Friend v. Green, 146 Conn. 360, 364, 151 A.2d 343; Dahl v. Edwin Moss & Son, Inc., 136 Conn. 147, 154, 69 A.2d 562; George S. Chatfield Co. v. O’Neill, 89 Conn. 172, 174, 93 A. 133.

*598 We conclude that the court was in error in reversing the decision reached by the engineer with respect to the several conflicts items of the plaintiff’s claim and that damages should not have been awarded contrary to his decision.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

CAS Construction Co. v. Town of East Hartford
845 A.2d 466 (Connecticut Appellate Court, 2004)
FOUNDATION INTERN. v. ET Ige Const.
78 P.3d 23 (Hawaii Supreme Court, 2003)
Cas Construction Co. v. East Hartford, No. Cv-98-0087320-S (May 1, 2002)
2002 Conn. Super. Ct. 5614 (Connecticut Superior Court, 2002)
Empire Paving, Inc. v. City of Milford
747 A.2d 1063 (Connecticut Appellate Court, 2000)
Empire Paving, Inc. v. City of Milford, No. Cv-94-0362457s (Mar. 3, 1998)
1998 Conn. Super. Ct. 2687 (Connecticut Superior Court, 1998)
Daly Sons v. City of West Haven, No. Cv96 0053211s (Feb. 13, 1997)
1997 Conn. Super. Ct. 832 (Connecticut Superior Court, 1997)
M & L Building Corp. v. Housing Authority
646 A.2d 244 (Connecticut Appellate Court, 1994)
John T. Brady & Co. v. City of Stamford
599 A.2d 370 (Supreme Court of Connecticut, 1991)
Grenier v. Compratt Construction Co.
454 A.2d 1289 (Supreme Court of Connecticut, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
264 A.2d 557, 158 Conn. 592, 1969 Conn. LEXIS 636, Counsel Stack Legal Research, https://law.counselstack.com/opinion/maskel-construction-co-v-town-of-glastonbury-conn-1969.