CAS Construction Co. v. Town of East Hartford

845 A.2d 466, 82 Conn. App. 543, 2004 Conn. App. LEXIS 169
CourtConnecticut Appellate Court
DecidedApril 20, 2004
DocketAC 23143
StatusPublished
Cited by9 cases

This text of 845 A.2d 466 (CAS Construction Co. v. Town of East Hartford) is published on Counsel Stack Legal Research, covering Connecticut Appellate Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
CAS Construction Co. v. Town of East Hartford, 845 A.2d 466, 82 Conn. App. 543, 2004 Conn. App. LEXIS 169 (Colo. Ct. App. 2004).

Opinion

Opinion

BISHOP, J.

This appeal arises from the trial of a dispute involving a road reconstruction project in East [545]*545Hartford. On May 21, 1997, the plaintiff, CAS Construction Company, Inc., entered into a written contract with the defendant town of East Hartford for the reconstruction of Forest Street. The project was funded by the department of transportation.1 Pursuant to the contract, the plaintiff agreed to remove and to replace the storm drainage systems under Forest Street, and the defendant agreed, in return, to pay for the plaintiffs services on the basis of the unit prices contained in the defendant’s solicitation of bids.2

Work on the project began in June, 1997, and was completed by June, 1998. A dispute arose after the defendant rejected several requisitions submitted by the plaintiff for payment for various units of work. Thereafter, the plaintiff commenced this action. In count one of its complaint, the plaintiff alleged breach of contract for failure to make payments in excess of $71,729.90 for work contained in the contract specifications. In count two, the plaintiff claimed nonpayment in an amount exceeding $105,204.17 for extra work not contained in the contract specifications. In count three, the plaintiff alleged delays to contract performance caused by the defendant that resulted in additional unspecified costs to the plaintiff. In response, the defendant denied that the amounts claimed were due and filed five special defenses.3

[546]*546After a trial to the court, judgment was rendered for the plaintiff on counts one and two of the complaint in the amounts of $28,722 and $5008.28, respectively. Judgment was rendered for the defendant on count three.

On appeal, the plaintiff claims that the court improperly (1) interpreted the parties’ contract by concluding that the plaintiff was not entitled to additional compensation for (A) remobilization costs associated with the defendant’s suspension of work, (B) costs associated with the reconnection of pipes to the newly installed catch basins and (C) services provided by the plaintiff beyond the contractual horns of operation; (2) found that the plaintiff failed to prove its damages with reasonable certainty; and (3) concluded that the defendant was not hable for compensation claimed by the plaintiff for the extra costs incurred by a subcontractor. We affirm the judgment of the trial court. Additional facts will be set forth as necessary.

I

The plaintiffs first claim is that the court improperly interpreted the contract by concluding that the plaintiff was not entitled to additional compensation because (A) the contract provisions governing the suspension of work encompassed a provision for making a claim for remobilization costs, (B) the contract unit price for each catch basin included the costs incurred by the plaintiff in reconnecting the pipes to the catch basins and (C) the contract limited the paid hours of operation.

A

The plaintiff challenges the court’s conclusion that the contract barred its claim for additional compensa[547]*547tion for the costs associated with the defendant’s suspension of work.

The following additional facts are relevant to our disposition of the plaintiffs claim. On November 24, 1997, the defendant notified the plaintiff that it was suspending work on the project for the winter months and that the project was to resume no later than April 1, 1998. In its complaint, the plaintiff alleged that it suffered monetary damages as a result of the suspension. Specifically, the plaintiff alleged that as a result of the defendant’s suspension of work, all of its equipment from the site was “demobilized” and in April, when the project resumed, it had to “remobilize” the equipment again. At trial, the plaintiff claimed that this “remobilization” cost it an additional $20,000.

The court denied the plaintiffs claim for remobilization costs and, in its memorandum of decision, stated: “[T]he defendant acted reasonably, lawfully and in accordance with the rules and procedures authorizing a winter closure. The plaintiff failed to conform to CT DOT Form 814A, § 1.08.06, and did not submit ‘. . . to [the defendant], in writing, a request for a contract adjustment within seven calendar days of receipt of a notice to resume work.’ ”

On appeal, the plaintiff contends that the court improperly applied the contractual requirements of the suspension of work provisions to its claim for remobili-zation costs. We are not persuaded.

We begin by articulating the appropriate standard of review. In the present case, the parties do not dispute that the interpretation of the language of § 1.08.06 of the contract’s Standard Specifications for Roads, Bridges and Incidental Construction, Form 814A (1995) (Standard Specifications), as promulgated by the department of transportation, presents a question of law over which we exercise plenary review. “[W]here [548]*548there is definitive contract language, the determination of what the parties intended by their contractual commitments is a question of law. . . . [B]ecause the trial court relied solely upon the written [agreement] in ascertaining the intent of the parties, the legal inferences properly to be drawn from the [document is a] question of law, rather than fact.” (Internal quotation marks omitted.) Schoonmaker v. Lawrence Brunoli, Inc., 265 Conn. 210, 227, 828 A.2d 64 (2003).

The plaintiff contends that the court misconstrued the contract in concluding that the defendant was entitled to order a winter shutdown. On appeal, however, the plaintiff acknowledges that the defendant was, in fact, entitled to order a suspension of work. In that regard, the plaintiffs brief states in relevant part: “The contract terms were clear, [the plaintiff] was to proceed with work with no winter shutdown. [The defendant] decided to suspend the Project. [The defendant] has a contractual right to suspend the work (CTDOT 814A, Section 1.08.06 . . .) but it must pay [the plaintiff] for the costs of such a suspension, such as idle equipment, utility and rental costs.”

The plaintiffs acknowledgment that the defendant was entitled to order a shutdown of the work is correct. The contract language at issue unambiguously provides that the parties intended to give the defendant the authority to suspend work under certain circumstances.4 Accordingly, we conclude that the court’s con-[549]*549elusion that the defendant was entitled to suspend work on the project during the winter months was legally correct.5

The plaintiff also challenges the court’s conclusion that it was not entitled to recover the extra remobilization costs it incurred because it did not submit to the defendant a written request for a contract adjustment within seven calendar days of the plaintiffs receipt of the defendant’s notice to resume work. The plaintiff contends that even if the defendant had the contractual right to order the suspension of work, the plaintiff was entitled to recover the additional costs it incurred in remobilizing its equipment regardless of whether it submitted a timely written request for additional compensation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Li v. Yaggi
198 A.3d 123 (Connecticut Appellate Court, 2018)
System Pros, Inc. v. Kasica
145 A.3d 241 (Connecticut Appellate Court, 2016)
Old Colony Construction, LLC v. Southington
Supreme Court of Connecticut, 2015
AMERICAN DIAMOND EXCHANGE, INC. v. Alpert
28 A.3d 976 (Supreme Court of Connecticut, 2011)
Sparveri v. Town of Rocky Hill
656 F. Supp. 2d 297 (D. Connecticut, 2009)
Viejas Band of Kumeyaay Indians v. Lorinsky
976 A.2d 723 (Connecticut Appellate Court, 2009)
Socha v. BORDEAU
961 A.2d 495 (Connecticut Superior Court, 2007)
Valentin v. COMMUNITY REMODELING CO., INC.
876 A.2d 1252 (Connecticut Appellate Court, 2005)
Nationwide Mutual Insurance v. Allen
850 A.2d 1047 (Connecticut Appellate Court, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
845 A.2d 466, 82 Conn. App. 543, 2004 Conn. App. LEXIS 169, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cas-construction-co-v-town-of-east-hartford-connappct-2004.