Wexler Construction Co. v. Housing Authority

183 A.2d 262, 149 Conn. 602, 1962 Conn. LEXIS 221
Supreme Court of Connecticut·Decided July 5, 1962·Published·Cited by 21 cases

Opinion

King, J.

This is an action in which, under the first count, the plaintiff, a general contractor, seeks to recover on behalf of its subcontractor the reasonable value of work performed by the latter, outside the scope of the original construction contract, at the request of the defendant, the owner. 1 The other claims of the plaintiff will be discussed later. Although the trial was lengthy and the details involved, the facts necessary for an understanding of our decision will be given in an abbreviated and simplified form.

The plaintiff, as the general contractor, entered into a contract with the defendant on May 13, 1950, for the construction of a housing project in Norwich for a price of $466,809. The plaintiff subcontracted the site development portion of the work to the Candor Construction Company, Inc., of Norwich, hereinafter referred to as Candor, for a price of $44,000. Candor commenced its work on or about May 18, 1950. Shortly thereafter, drainage and resulting grading problems were encountered, and they eventually made it necessary for Candor substantially to deviate from the site development plans called for in the contract between the plaintiff and the defendant. Some of these deviations were made pursuant to written change orders and were, therefore, in accordance with the terms of the con *604 tract. However, even on the claims of proof most favorable to the plaintiff, many of the deviations were not covered by change orders but were made outside the contract in accordance with oral directives given by representatives of the defendant. Some of these directives apparently were given to the plaintiff to pass along to Candor, and others were given directly to Candor. In consequence of these orally authorized deviations, the time and the cost involved in developing the project site were greatly increased.

Finally, on November 6, 1951, some thirteen and a half months after the time when the project was to have been completed, the defendant ordered the site development work stopped in order to afford it an opportunity to work out solutions to the drainage and grading problems. A large amount of corrective and additional drainage and site development work still remained to be performed. All the work required to be performed under the plaintiff’s contract with the defendant, apart from the site development work, was fully performed in accordance with the contract. The site development work was finally completed by another contractor following new competitive bids on new plans, which were submitted by a new architect.

Under the first count, the plaintiff sought recovery, on behalf of Candor, of $178,672.27, with interest, in quantum meruit. This is claimed to be the reasonable value of the work done outside the contract by Candor at the request of the defendant, either directly or through the plaintiff. In the earlier stages of this protracted litigation, the defendant demurred to this count on the ground that it did not allege that the plaintiff was in any way liable to Candor so as to entitle the plaintiff to *605 maintain the action on Candor’s behalf. We held, on appeal from the action of the trial court in sustaining the demurrer, that the allegations of the complaint were sufficiently broad to allege that the plaintiff was liable to Candor. We did not decide whether evidence of such liability was required. The judgment was ordered set aside, and the case was remanded with direction to overrule the demurrer. Wexler Construction Co. v. Housing Authority, 144 Conn. 187, 194, 128 A.2d 540.

A basic claim of the defendant on this appeal is that the liability of the plaintiff to Candor is a prerequisite to recovery and has not been proven. The plaintiff claims that such liability is not a prerequisite to its right of recovery. “It is a fundamental concept of judicial administration that no person is entitled to set the machinery of the courts into operation unless for the purpose of obtaining redress for an injury he has suffered or to prevent an injury he may suffer, either in an individual or representative capacity.” Waterbury Trust Co. v. Porter, 130 Conn. 494, 498, 35 A.2d 837; Bassett v. Desmond, 140 Conn. 426, 430, 101 A.2d 294. A plaintiff can recover only by proving that he himself is entitled to prevail on the cause of action alleged. It is not enough that he prove that some other person, not a party to the case, would be entitled to recover on that cause of action. The only way in which the plaintiff here could be injured, under the allegations of the first count, is if it is liable to Candor in connection with the extra work. A contractor is not necessarily, nor even generally, liable to its subcontractor for the extra work done by the subcontractor by reason of fault on the part of the owner or his agents. See Lichter v. Mellon-Stuart Co., 196 F. Sup. 149, 151 (W.D.Pa.); McGrath v. Electrical *606 Construction Co., 230 Ore. 295, 304, 364 P.2d 604, rehearing denied, 230 Ore. 295, 309, 370 P.2d 231.

Free access — add to your briefcase to read the full text and ask questions with AI

Wexler Construction Co. v. Housing Authority, 183 A.2d 262, 149 Conn. 602, 1962 Conn. LEXIS 221 (Colo. 1962).

183 A.2d 262 (Wexler Construction Co. v. Housing Authority) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

CAS Construction Co. v. Town of East Hartford
845 A.2d 466 (Connecticut Appellate Court, 2004)
Interstate Contracting Corp. v. City of Dallas
135 S.W.3d 605 (Texas Supreme Court, 2004)
Inter Contr Corp v. City of Dallas Texas
407 F.3d 708 (Fifth Circuit, 2003)
Interstate Contracting Corp. v. City of Dallas
320 F.3d 539 (Fifth Circuit, 2003)
Construction Coord. v. Naek Const. Co., No. Cv 99 0594686s (Apr. 30, 2001)
2001 Conn. Super. Ct. 5741-gx (Connecticut Superior Court, 2001)
Herb Holden Trucking v. Vinco Inc., No. Cv 94 0542455s (Feb. 2, 2000)
2000 Conn. Super. Ct. 1586 (Connecticut Superior Court, 2000)
M.J. Daly Sons v. City of West Haven, No. Cv96-0053211s (Sep. 24, 1999)
1999 Conn. Super. Ct. 12917 (Connecticut Superior Court, 1999)
Atlas Const. Co. v. Amity Regional Sch., No. Cv97 0405442 (Mar. 25, 1999)
1999 Conn. Super. Ct. 3403 (Connecticut Superior Court, 1999)
F.D.I.C. v. Peabody N.E. Inc., No. Cv 93-525754-S (Jan. 25, 1996)
1996 Conn. Super. Ct. 570 (Connecticut Superior Court, 1996)
Newberry Square Dev. Corp. v. Southern Landmark, Inc.
578 So. 2d 750 (District Court of Appeal of Florida, 1991)
Silverman v. Polidori, No. Cv 89-0435529s (Jan. 4, 1991)
1991 Conn. Super. Ct. 719 (Connecticut Superior Court, 1991)
Bolton Corp. v. T. A. Loving Co.
380 S.E.2d 796 (Court of Appeals of North Carolina, 1989)
Farrell Construction Co. v. Jefferson Parish
693 F. Supp. 490 (E.D. Louisiana, 1988)
Walter Kidde Constructors, Inc. v. State
434 A.2d 962 (Connecticut Superior Court, 1981)
Gannon v. Sanders
244 A.2d 397 (Supreme Court of Connecticut, 1968)
Cecio Bros. v. Town of Greenwich
244 A.2d 404 (Supreme Court of Connecticut, 1968)
Frager v. Pennsylvania General Insurance
231 A.2d 531 (Supreme Court of Connecticut, 1967)
Zaist v. Olson
227 A.2d 552 (Supreme Court of Connecticut, 1967)
Lerner Shops of Connecticut, Inc. v. Town of Waterbury
193 A.2d 472 (Supreme Court of Connecticut, 1963)
Knapp v. New Haven Road Construction Co.
189 A.2d 386 (Supreme Court of Connecticut, 1963)