M.J. Daly Sons v. City of West Haven, No. Cv96-0053211s (Sep. 24, 1999)

1999 Conn. Super. Ct. 12917
CourtConnecticut Superior Court
DecidedSeptember 24, 1999
DocketNo. CV69-0053211S
StatusUnpublished

This text of 1999 Conn. Super. Ct. 12917 (M.J. Daly Sons v. City of West Haven, No. Cv96-0053211s (Sep. 24, 1999)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
M.J. Daly Sons v. City of West Haven, No. Cv96-0053211s (Sep. 24, 1999), 1999 Conn. Super. Ct. 12917 (Colo. Ct. App. 1999).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.]

MEMORANDUM OF DECISION
The plaintiff in this matter is a Waterbury-based construction company M.J. Daly Sons, Inc. which has been in business for a number of years engaging in municipal work including pumping stations as well as specialized industrial work. In March 1992 the defendant City of West Haven advertised for bids to construct a main pumping station in connection with the City's sewage disposal system. The necessity for this came about apparently as a result of a lawsuit by the State of Connecticut against the City which ended with a stipulated judgment requiring the City to upgrade its system. There were originally 3 areas of work encompassed within the City's plans and specifications consisting of:

(1) above grade activity including replacement of electrical switching equipment; CT Page 12918

(2) removal and replacement of existing pumps and piping and;

(3) some structural modifications.

The bid submitted by Daly in the amount of $998,452 was accepted by the City with the executed contract calling for completion within 365 days with the period of construction running from March 30, 1992 to March 31, 1993. (P. Ex. 3A) The engineering firm of Cascio-Bechir had been previously selected by the City to be its engineers supervising the project. Problems interfering with Daly's performance of the contract arose almost immediately on the project and substantial delays were experienced resulting in considerable extra costs through the project and dissension between the parties. This dissension continued throughout the plaintiff's attempted performance of the contract until June 3, 1996 (D. Ex. 49) when the City elected to terminate the contract short of completion, which termination became effective 10 days thereafter; i.e. June 13, 1996.

Among the major problems experienced were the immediate discovery of an underground structure not shown on the plans which prevented Daly from doing any initial excavating to get the project under way. Later it was discovered that the force main running from the pumping station to the Water Pollution Control Plant (WPCP) was made of asbestos cement which prohibited its continued use and a parallel force main was required to be installed. This brought about a cessation of work while the City's engineers prepared plans and specifications to cover that construction. Another major problem arose when the City and its engineers Cascio-Bechir parted company around December 1994 requiring the introduction of a new engineering firm, namely Black Veatch. The problems created by these events and others and the inability of the parties to reach an amicable financial resolution resulted in the termination of the contract by the defendant. As a result, Daly filed this action on January 31, 1996 consisting of six counts seeking money damages, interest, attorney's fees and punitive damages.

The First Count of the complaint sets out in some 44 paragraphs the terms of the contract as relating to the problems which arose, the factual allegations of the plaintiff giving rise to the claims of damages resulting from delays allegedly caused by the City and extra costs brought about by change orders and the unanticipated failure of existing pumps requiring bypass CT Page 12919 pumping on an emergency basis.

The Second Count claims damages allegedly incurred by Daly for home office expense and overhead incurred as a result of the delays caused by events set out in the First Count.

The Third Count claims a lack of good faith and fair dealing by the defendant in its handling and resolution of Daly's claims under the contract.

The Fourth Count grounded in negligence claims damages based upon the City's failure to provide accurate plans for the project and its failure to seasonably act on problems encountered during the course of the construction.

The Fifth Count claims negligent misrepresentations and omissions on the part of the City as to the City's obligation to compensate the Plaintiff for extra work performed to complete the project.

The Sixth and final count concerns additional expenses incurred by the plaintiff in construction with the bypass pumping which the defendant agreed to assume initially but according to the plaintiff apparently never intended to pay constituting intentional misrepresentations upon which the plaintiff relied to its loss and damages.

The defendant under date of March 1, 1999 responded to the plaintiff's complaint with its answer and several special defenses.

The First Special defense claims an accord and satisfaction by way of change orders for various agreed amounts and costs of delays through May 25, 1995.

The Second Special Defense claims an accord and satisfaction by an agreed change order for all claims arising out of work performed at the WPCP as well as bypass pumping connected therewith.

The Third Special Defense claims that any work performed by the plaintiff in connection with the emergency bypass pumping is not compensable under the terms of the contract because of Daly's failure to proceed under the contract terms as regards work to be performed on an emergency basis. CT Page 12920

The Fourth Special Defense again alleges lack of compliance with terms of the contract and as a result such claims are barred.

The Fifth Special Defense alleges that under the terms of the contract the parties agreed that the engineer selected by the City was to resolve any disputes arising under the contract and that determination by the engineer was a prerequisite to any civil action. Under the contract terms relating to termination, the City determined what was due and owing under the contract and since Daly refused to participate in determining the final amount due under the contract, Daly is deemed to have accepted such amount and is accordingly barred from pursing this action.

The City, by way of counterclaim setting forth Daly's failure to abide by the contract terms regarding the engineer as the arbiter, requests this court to adopt the amount due the plaintiff as determined by the defendant and enforce the award as final and binding on the parties.

The court heard the evidence as presented by the parties over a period of 6 weeks and consisting of several hundred exhibits and approximately 2000 pages of transcript.

The court will first take up the defendant's several special defenses as they relate to the barring of any of the plaintiff's claims under the terms of the contract.

The defendant's five special defenses can be divided into two subject areas: accord and satisfaction (the first and second special defenses), and arguments based on the contract (the third, fourth and fifth special defenses). In its accord and satisfaction special defenses, the defendant maintains change orders (CO) one through seven redress all of the plaintiff's claims and thus the claims are barred by the doctrine of accord and satisfaction from being reconsidered. In its contract special defenses, the defendant argues that the plaintiff's claims are barred by the contract as the plaintiff has failed to submit his claims to the engineer as required pursuant to the contract and, moreover, that the engineer's final decision addressing any outstanding disputes is final and binding on all parties involved.

As to the defendant's first two special defenses, the court CT Page 12921 finds that the plaintiff's present claims are not barred through a previous discharge of the debt by way of accord and satisfaction.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

E & F CONSTRUCTION CO. v. Rissil Construction Associates, Inc.
435 A.2d 343 (Supreme Court of Connecticut, 1980)
Southern New England Contracting Co. v. State
345 A.2d 550 (Supreme Court of Connecticut, 1974)
Wexler Construction Co. v. Housing Authority
183 A.2d 262 (Supreme Court of Connecticut, 1962)
Peerless Soda Fountain Service Co. v. Savin
166 A. 386 (Supreme Court of Connecticut, 1933)
Bieluch v. Bieluch
509 A.2d 8 (Supreme Court of Connecticut, 1986)
Chmielewski v. Aetna Casualty & Surety Co.
591 A.2d 101 (Supreme Court of Connecticut, 1991)
Northrop v. Allstate Insurance
720 A.2d 879 (Supreme Court of Connecticut, 1998)
Foley v. Huntington Co.
682 A.2d 1026 (Connecticut Appellate Court, 1996)
Munroe v. Emhart Corp.
699 A.2d 213 (Connecticut Appellate Court, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
1999 Conn. Super. Ct. 12917, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mj-daly-sons-v-city-of-west-haven-no-cv96-0053211s-sep-24-1999-connsuperct-1999.