Herb Holden Trucking v. Vinco Inc., No. Cv 94 0542455s (Feb. 2, 2000)

2000 Conn. Super. Ct. 1586
CourtConnecticut Superior Court
DecidedFebruary 2, 2000
DocketNo. CV 94 0542455S
StatusUnpublished

This text of 2000 Conn. Super. Ct. 1586 (Herb Holden Trucking v. Vinco Inc., No. Cv 94 0542455s (Feb. 2, 2000)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Herb Holden Trucking v. Vinco Inc., No. Cv 94 0542455s (Feb. 2, 2000), 2000 Conn. Super. Ct. 1586 (Colo. Ct. App. 2000).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.]

MEMORANDUM OF DECISION
The plaintiff, Herb Holden Trucking Inc., a subcontractor, sues its general contractor, defendant Vinco Incorporated, in ten counts alleging breaches of contract and negligence and violation of Connecticut Unfair Trade Practices Act. However, since the latter count was not briefed by plaintiff, it will not be considered by the court. Jennings v. Reale Construction Co.,175 Conn. 16, fn. 1 at 17 (1978); Johnson v. Flammia, 169 Conn. 491,498 (1975). The defendant, Vinco Incorporated, interposes a general denial and special defenses to the effect that the plaintiff executed waivers and releases of all of its claims, plaintiff's claims are barred due to its failure to give timely notice as set forth in the contract, and no payments are due the plaintiff because of its failure to provide contractually required documentation. The defendant also interposed a counterclaim to the effect that plaintiff breached the subcontracts in numerous ways. However, defendant has not briefed the issue of its counterclaim and the court deems it abandoned.Jennings v. Reale Construction Co., supra; Johnson v. Flammin, supra. CT Page 1587

The essence of plaintiff's claim is what in the building trade is known as loss of productivity, namely that by the defendant delaying and failing to coordinate the work on the projects which are the subject of this action, the defendant caused the plaintiff to lose a substantial amount of money. The court has bifurcated the case, agreeing first to hear and determine the issue of liability before turning to the issue of damages.

The facts are as follows: On March 30, 1990, the State of Connecticut, Department of Public Works invited sealed bids from general contractors for the construction of a project known as Renovation of North Block and 300 Cell Addition-Cheshire Correctional Facility, Project BI-EE-85 ("Project 85"). This project involved construction of a gymnasium and cafeteria as well as a 300 cell facility. Prior to Vinco, Incorporated (hereinafter Vinco), submitting its bid to the state on Project 85, Herb Holden Trucking, Inc. (hereinafter Holden) submitted a bid to Vinco on June 18, 1990 in the amount of $661,669 for the sitework portion of Project 85. Holden also submitted a similar bid to other contractors who were submitting bids to the state for Project 85. On August 10, 1990, the state awarded the contract for Project 85 to Vinco for the lump sum of $15,672,000.

On April 20, 1990, the state invited bids from general contractors for a project known as 312 Cell Addition, Cheshire Correctional Facility, Project BI-EE-100B ("Project 100B"). Prior to Vinco subcontracting its bid to the state, Holden submitted a bid to Vinco on June 19, 1990 in the amount of $554,850 for the sitework portion of Project 100B. On August 10, 1990, the state awarded the contract for Project 100B to Vinco for the lump sum of $13,130,000.

The state issued an "Order to Commence Work" to Vinco for both projects on August 20, 1990. Under the terms of the general contract between the state and Vinco, Project 85 was to be completed within 460 days or by November 23, 1991 and Project 100B within 510 days or by January 10, 1992. Liquidated damages were to accrue at $1,000 a day if the jobs were not completed by those dates.

On August 17, 1990, Holden offered to do the sitework on both projects, 85 and 100B, for the total sum of $1,238,725. The parties eventually agreed to $1,200,000, a reduction of $38,725 from the price offered by Holden. CT Page 1588

On August 27, 1990, Vinco and Holden entered into subcontracts for Projects 85 and 100B. As to Project 85, the contract price for the site work was $646,546 and for Project 100B it was $553,454. The subcontracts provided as follows.

6. Time of Performance

a. Subcontractor will proceed with the work in a prompt and diligent manner in accordance with Contractor's schedule as reasonably amended from time to time. TIME IS OF THE ESSENCE. Subcontractor shall be entitled to additional compensation for compliance with schedule amendments only to the extent, if any, that the Contract Documents entitle Contractor to reimbursement. Contractor shall not be liable to Subcontractor for any damages resulting from delays caused by an entity not a part to this Subcontract unless Contractor has first recovered same on behalf of Subcontractor from said entity. Subcontractor expressly agrees that apart from recovery from said entity, Subcontractor's exclusive remedy for delay shall be an extension of the time for performance of the Subcontractor's work.

7. Changes and Claims

b. Subcontractor shall submit in writing to Contractor all claims for adjustment in the Subcontract price or schedule for which the Owner is liable in the manner provided in the Contract Documents for like claims by Contractor against Owner. Such claims must be submitted by Subcontractor to Contractor at least three days prior to the time Contractor is required by the Contract Documents to submit claims to Owner otherwise such claims shall be waived. Contractor shall process such claims according to the provisions of the Contract Documents and Contractor's liability to Subcontractor for such claims is limited to any adjustment which shall be made by Owner to Contractor's contract on account of Subcontractor's claim.

c. Subcontractor shall submit in writing to Contractor all claims not included in paragraph 7b within five days of the beginning of the event for which claim is made, otherwise such claim will be waived. All unresolved claims shall be resolved in court of competent jurisdiction.

26. Complete Agreement CT Page 1589

This subcontract contains the entire agreement between the parties hereto with respect to the matter covered herein. No other agreements, representations, warranties, or other matters, oral or written, shall be deemed to bind the parties.

The contracts between the state and Vinco contained a portion entitled "General Conditions of the Contract". Article 2, "Conditions of Work", subsection 1 provides:

1. In carrying out his work, the contractor must employ such methods or means as will not cause any interruption of or interference with the work of any other contractor, nor with the normal routine of the institution or agency operating at the site.

Article 6, "Separate Contracts", subsection 4 provides:

4. Insofar as possible, the contractor shall arrange his work and shall place and dispose of the materials being used so as not to interfere with the operation of other contractors adjacent to or within the limits of the same project. He shall join his work with that of others in an acceptable manner, and perform it in a proper accordance with that of the others."

Article 7, "Cooperation of Trades", provides:

"The contractor is responsible for and shall control all activities of his subcontractors, and the subcontractors shall consult and cooperate with one another and the other contractors working on the site in the installation of the work of each."

Article 13.7 provides:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wayne J. Griffin Elec. v. Dunn Const.
622 So. 2d 314 (Supreme Court of Alabama, 1993)
Collins v. Sears, Roebuck & Co.
321 A.2d 444 (Supreme Court of Connecticut, 1973)
Jennings v. Reale Construction Co.
392 A.2d 962 (Supreme Court of Connecticut, 1978)
Harris v. Clinton
112 A.2d 885 (Supreme Court of Connecticut, 1955)
Wexler Construction Co. v. Housing Authority
183 A.2d 262 (Supreme Court of Connecticut, 1962)
Johnson v. Flammia
363 A.2d 1048 (Supreme Court of Connecticut, 1975)
Associated Catalog Merchandisers, Inc. v. Chagnon
557 A.2d 525 (Supreme Court of Connecticut, 1989)
TIE Communications, Inc. v. Kopp
589 A.2d 329 (Supreme Court of Connecticut, 1991)
Pero Building Co. v. Smith
504 A.2d 524 (Connecticut Appellate Court, 1986)
Snydergeneral Corp. v. Lee Parcel 6 Associates Ltd. Partnership
681 A.2d 1008 (Connecticut Appellate Court, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
2000 Conn. Super. Ct. 1586, Counsel Stack Legal Research, https://law.counselstack.com/opinion/herb-holden-trucking-v-vinco-inc-no-cv-94-0542455s-feb-2-2000-connsuperct-2000.