Kay-R Electric Corporation v. Stone & Webster Construction Co., Inc., and the Federal Insurance Company

23 F.3d 55, 39 Cont. Cas. Fed. 76,685, 1994 U.S. App. LEXIS 9450, 1994 WL 161063
CourtCourt of Appeals for the Second Circuit
DecidedMay 2, 1994
Docket1031, Docket 93-6225
StatusPublished
Cited by39 cases

This text of 23 F.3d 55 (Kay-R Electric Corporation v. Stone & Webster Construction Co., Inc., and the Federal Insurance Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kay-R Electric Corporation v. Stone & Webster Construction Co., Inc., and the Federal Insurance Company, 23 F.3d 55, 39 Cont. Cas. Fed. 76,685, 1994 U.S. App. LEXIS 9450, 1994 WL 161063 (2d Cir. 1994).

Opinion

OAKES, Senior Circuit Judge:

Kay-R Electric Corporation (“Kay-R”), an electrical subcontractor, brought this suit under the Miller Act, 40 U.S.C. §§ 270a-270d (1988), against Stone & Webster Construction Co. (“Stone & Webster”), a general contractor that had contracted with the United States to furnish the materials and perform the labor for the construction of three buddings at Stewart Air Force Base in Orange County, New York. 1 The value of Kay-R’s subcontract was $1,218,200. It called for the work to commence on August 3, 1987, and to be completed by July 4, 1988. The suit alleges that as a result of Stone & Webster’s failures to excavate, pour footings, construct foundations and slabs for or erect structural steel for the buddings, enclose the buddings, and complete the interior of the buddings in a timely manner, the buildings were not finally enclosed until approximately 11 months after the date on which they were scheduled to be enclosed. The suit further alleges that these delays caused Kay-R to perform work in a piecemeal fashion, on an accelerated work schedule, through the inefficient use of its work force, and in exposed winter conditions. Kay-R claims to have experienced substantial additional costs for labor, materials, and the storage of materials to the reasonable value of $855,442. The United States District Court for the Northern District of New York, Howard Munson, Judge, granted summary judgment to Stone & Webster and the Federal Insurance Company on the following basis: As part of each requisition for payment, Kay-R released Stone & Webster, its agents, heirs, successors or assigns, “from any claim or claims of whatever nature for materials furnished, labor performed, or expense incurred to date which is not included in the above amounts or noted in the space above as provided therefor....” Moreover, on none of the requisitions was any claim made as a result of or on account of delays. Rather, each requisition showed the material furnished and labor performed in accordance with the contract, deducted the previous payments, and showed the amount due.

We now affirm.

It is elemental that we consider motions for summary judgment de novo. Owens v. New York City Hous. Auth., 934 F.2d 405, 408 (2d Cir.), cert. denied, — U.S.-, 112 S.Ct. 431, 116 L.Ed.2d 451 (1991). “As a general rule, all ambiguities and inferences to be drawn from the underlying facts should be resolved in favor of the party opposing the motion, and all doubts as to the existence of a genuine issue for trial should be resolved against the moving party.” Brady v. Town of Colchester, 863 F.2d 205, 210 (2d Cir.1988) (citing Celotex Corp. v. Catrett, 477 U.S. 317, 330 n. 2, 106 S.Ct. 2548, 2556 n. 2, 91 L.Ed.2d 265 (1986)).

Correctly, Kay-R states that the requisition forms that were used were not called for by the contract itself. Indeed, Kay-R first used its own form which contained no language pertaining to the release. On July 29, 1987, on Stone & Webster’s letterhead, an assistant project accountant wrote Kay-R, requesting Kay-R to “submit the attached requisition for payment along with your invoice when billing against the above contract,” attaching the Stone & Webster requisition forms which did contain the release language.

Apparently, Kay-R did not consult counsel and dutifully submitted the requisitions on the Stone & Webster forms. This is true even though by letter of February 10, 1988, *57 Kay-R had informed the Stone & Webster project manager that Kay-R was presently behind four months in supply and two months in maintenance, and that if it were the project manager’s intention to maintain the completion schedule, radical work had to be done immediately, pointing out also that “we do not have enough nor have we had sufficient work for the men we have on site,” and that “today we are performing work in the Supply Building which is contrary to normal practice, but we have nowhere to go.” The letter mentioned nothing about additional expense being incurred. The affidavit of Kay-R’s president, Robert L. Serafini, states that he and Stone & Webster’s vice president, Ronald Wagner, during the course of the project had a number of meetings in which Wagner always acknowledged the responsibility of Stone & Webster to provide for additional costs, specifically, additional labor that was required to be furnished.

On March 11, 1989, after all of the work was performed, Serafini met with Stone & Webster representatives and lawyers in Boston. At that point, there had been no payments on the February 7, 1989, payment requisition form for $13,147, or on the March 23, 1989, requisition for $1,999.71. Nor were these requisitions subsequently paid, no doubt because Serafini made clear that he was making a claim on behalf of Kay-R.

On appeal, Kay-R makes five claims: (1) the district court misapplied the applicable summary judgment rules because respondent’s moving papers were deficient as a matter of law; (2) there was no release of Kay-R’s claims; (3) there was ambiguity in the scope of the release, or, alternatively, Stone & Webster failed to make a sufficient showing of a lack of ambiguity; (4) the exception dispensing with consideration as a prerequisite to an enforceable release as set forth in New York General Obligations Law § 15-303, was inapplicable because “the written instrument” in question purported to be a “requisition for payment on contract and because payment was a condition subsequent that was never fulfilled”; and that (5) under the doctrine of collateral estoppel the trial court should have followed the decision of another district judge in a similar case brought by another subcontractor against Stone & Webster. We discuss each of these points in turn.

The first point, that the moving papers were deficient as a matter of law, is based on the proposition that the only fact alleged in Stone & Webster’s moving papers is that documents entitled “requisition for payment on contract” were received by Stone & Webster. Beyond that, according to Kay-R, there was nothing other than an after the fact understanding of the Stone & Webster affiant at the time he signed the summary judgment affidavit which reads: “Based upon the above, it is my understanding, and I am so informed by counsel, that Kay-R has released Stone & Webster_” (emphasis added). Thus, Kay-R argues, (1) there was no evidence whatsoever that any official of Stone & Webster believed or had an understanding that Kay-R had released Stone & Webster from the type of delay damage claims that Kay-R was pursuing in the litigation and (2) there was also no evidence whatsoever as to the reason for the blank lines on the form.

The short answer to Kay-R’s first point is that we are not concerned with what was going through the heads of the parties at the time these requisitions were signed by Kay-R’s president and paid by Stone & Webster. Rather, we are talking about objective principles of contract law.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pabon v. H&R Block, Inc.
E.D. New York, 2025
Woods v. City of Utica
N.D. New York, 2025
Genao v. Ruiz
S.D. New York, 2025
Matter of Timperio v. Bronx-Lebanon Hosp.
163 N.Y.S.3d 302 (Appellate Division of the Supreme Court of New York, 2022)
Suarez-Torres v. Panaderia y Reposteria Espana
988 F.3d 542 (First Circuit, 2021)
Ferring B.V. v. Serenity Pharm., LLC
391 F. Supp. 3d 265 (S.D. Illinois, 2019)
Wexler v. AT & T Corp.
211 F. Supp. 3d 500 (E.D. New York, 2016)
Prospect 34, LLC v. Gunnison County Board of County Commissioners
2015 COA 160 (Colorado Court of Appeals, 2015)
Vornado Realty Trust v. Marubeni Sustainable Energy, Inc.
987 F. Supp. 2d 267 (E.D. New York, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
23 F.3d 55, 39 Cont. Cas. Fed. 76,685, 1994 U.S. App. LEXIS 9450, 1994 WL 161063, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kay-r-electric-corporation-v-stone-webster-construction-co-inc-and-ca2-1994.