United States Ex Rel. Perosi Electrical Corp. v. Manshul Construction Corp.

940 F. Supp. 492, 1996 WL 590422
CourtDistrict Court, E.D. New York
DecidedAugust 2, 1996
Docket94 CV 1575 (RML)
StatusPublished
Cited by1 cases

This text of 940 F. Supp. 492 (United States Ex Rel. Perosi Electrical Corp. v. Manshul Construction Corp.) is published on Counsel Stack Legal Research, covering District Court, E.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Ex Rel. Perosi Electrical Corp. v. Manshul Construction Corp., 940 F. Supp. 492, 1996 WL 590422 (E.D.N.Y. 1996).

Opinion

MEMORANDUM AND ORDER

LEVY, United States Magistrate Judge:

This action arises out of a renovation and improvement project for the Community Facilities Budding at the United States Naval Station in Staten Island, New York, (the “Project”). Defendant Manshul Construction Corp. (“Manshul”) was the general contractor on the Project. Manshul hired plaintiff Perosi Electrical Corp. (“plaintiff’ or “Perosi”) as an electrical subcontractor. In this action, brought pursuant to the Miller Act, 40 U.S.C. §§ 270a and 270b, Perosi is seeking to recover from Manshul and its surety, defendant Aetna Casualty and Surety Company (“Aetna”), payments it claims it is owed for work performed and materials furnished in connection with the Project. Manshul is counterclaiming for damages it allegedly incurred in order to correct or complete work Perosi was under contract to perform.

By stipulation dated February 20, 1996, the parties consented to a trial before a Magistrate Judge. Accordingly, a bench trial was held before me on March 20 and 21, 1996, at which three witnesses testified: Richard Perosi, an officer of the plaintiff corporation; Alfred Haugland, Project Manager for the defendant corporation; and George Oprescu, Senior Project Manager for the Maximum Electric Company, an electrical subcontractor that also contracted to perform work for the Project. For the reasons stated below, I find in favor of plaintiff Perosi, in the total amount of $83,713.33, plus interest.

FINDINGS OF FACT AND CONCLUSIONS OF LAW

On or about September 26, 1991, the United States entered into a written contract with Manshul, whereby Manshul agreed to furnish the necessary labor and *494 materials for the renovation and improvement of the Headquarters/Administration, Community Facilities Building at the Naval Station in Staten Island. On the same date, in accordance with 40 U.S.C. § 270a, Manshul and Aetna, as surety, executed and delivered to the United States a payment bond in the penal sum of $2,500,000, wherein Manshul and Aetna bound themselves jointly and severally to all persons furnishing labor or materials in connection with the Project. Manshul then entered into an Electrical Subcontract Agreement with Perosi, dated January 6, 1992, wherein Perosi agreed to supply all labor, materials and equipment necessary to complete the electrical work for the Project. 1 In consideration therefor, Manshul agreed to pay Perosi the sum of $835,000.

On January 17, 1992, Perosi commenced performance of its obligations under the Electrical Subcontract Agreement. It is undisputed that, to date, Manshul has paid $720,245 to or on behalf of Perosi under that agreement. (See Amended Civil Pretrial Order at ¶ 5). 2

Perosi’s Claims

Perosi contends that it duly completed and performed all of its obligations under the Electrical Subcontract Agreement, except as prevented or frustrated by Manshul’s “material breaches”; it thus seeks to recover the remainder of the balance due under that agreement, in the sum of $114,755, together with interest from February 17, 1994. (See First Amended Complaint at ¶ 11). Perosi also seeks to recover for additional and extra work, not included in the Electrical Subcontract Agreement, that it claims Manshul directed it to perform and for which it claims it has not received payment. According to Perosi, such work includes: (a) furnishing control wiring for VAV boxes for the temperature control equipment; (b) remedying defective sheetrock cuts; (c) providing and maintaining temporary light and power to perform “miscellaneous site work” ordered by Manshul; (d) repairing ducts damaged by others; and (e) wiring a radio transmitter in the Administration Building. Perosi alleges that the fair and reasonable value of this extra work was $53,849.43; it thus seeks recovery of that amount, together with interest from February 17, 1994. Each of plaintiffs claims will be addressed in turn.

The Electrical Subcontract Agreement

The Electrical Subcontract Agreement, dated January 6, 1993, required Perosi to “supply all labor, materials and equipment necessary to complete all Electrical Work, as called for by the contract specifications and amendments and as shown on the contract drawings.” Such work was to include, but was not limited to: (a) demolition and removal work, (b) electrical general requirements, (c) the underfloor raceway system, (d) overhead electrical work, (e) interior wiring systems, (f) interior switchboard, low-voltage, (g) pad mounted transformer (750 KVA), (h) interior lighting, (i) exterior lighting; and (j) the fire alarm and fire detecting system, all as described in the contract specifications and amendments. In addition, the agreement required Perosi to, inter alia, (1) furnish to the jobsite all extension cords as required, (2) provide all ground fault detectors as required, (3) provide all temporary light and power systems “for all days that work of the General Contractors trades shall be at the jobsite,” (4) provide temporary site lighting as per the contract plans, specifications and amendments, (5) perform all site electrical work, including site lighting and all underground work, (6) furnish and install all new telephone ducts per the plans and specifications, (7) remove existing overhead electric lines, poles and transformers, as per the plans, specifications and amendments, (8) provide electrical lighting and power for the general contractor, (9) place all rubbish and debris into containers, for removal by others, *495 (10) coordinate with other trades and provide coordination drawings, (11) provide all shop drawings, certificates as required by the Navy, test reports, catalogs and cuts, (12) perform all testing and provide all reports required for the Project, (13) furnish and install all underground work as per the plans, specifications and amendments, (14) provide all access doors related to its work, (15) furnish and install all electrical cells as shown on electrical drawing S-l, (16) furnish and install header trenches and covers, (17) furnish and install concrete bases for light poles, (18) provide all safety features including safety nets, goggles, signs, etc., and (19) furnish and install all sleeves required to be installed in foundation walls.

Specifically excluded from the agreement were, inter alia, “control wiring,” unless “shown on the electrical drawings under requirements of the electrical specifications,” and “H.V.A.C. Control Wiring,” defined by Richard Perosi at trial as “[a]ny control wiring that has to do with the heating, ventilating and air-conditioning system....” (Trial Transcript (“Tr.”) at 14).

In addition, Paragraph 9 of the agreement, as amended, states in pertinent part:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lucente v. International Business MacHines Corp.
117 F. Supp. 2d 336 (S.D. New York, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
940 F. Supp. 492, 1996 WL 590422, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-perosi-electrical-corp-v-manshul-construction-corp-nyed-1996.