Cecio Bros. v. Town of Greenwich

244 A.2d 404, 156 Conn. 561, 1968 Conn. LEXIS 637
CourtSupreme Court of Connecticut
DecidedJune 25, 1968
StatusPublished
Cited by74 cases

This text of 244 A.2d 404 (Cecio Bros. v. Town of Greenwich) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cecio Bros. v. Town of Greenwich, 244 A.2d 404, 156 Conn. 561, 1968 Conn. LEXIS 637 (Colo. 1968).

Opinion

House, J.

This case arose out of a school construction project in Greenwich. The town of Greenwich entered into a contract with the V. B. Construction Company, Inc., to construct a school at a cost of $1,707,423. The plaintiff entered into a subcontract with the V. B. Construction Company, Inc., hereinafter called the contractor, whereby it agreed, for the sum of $249,000, to furnish labor, equipment and materials in connection with the construction of the school, including the establishment of finished grades in accordance with the plans and specifications of the prime contract. The plans and specifications, including a topographical survey, were prepared by architects hired by the town and by an engineer employed by the architects. On the basis *563 of the survey and an estimate of borrow fill requirements submitted to it by an independent estimator whom it hired for that purpose (and who was an employee of the engineer who was employed by the architects for the project), the plaintiff estimated that 39,000 cubic yards of borrow fill would be necessary to grade the project in accordance with the plans and specifications. In performing its subcontract, the plaintiff furnished more than 49,000 cubic yards of borrow fill. The plaintiff’s action to obtain compensation for the 10,000 additional cubic yards of borrow fill was brought against the town, the contractor and the American Surety Company of New York, which had given a performance bond to the town in the amount of the prime contract. As originally instituted, the action was one for quantum meruit. After the town successfully demurred to this complaint, the plaintiff amended it to include an allegation that the town “has been unjustly enriched in that it has received fill from the plaintiff which cannot, in equity and good conscience, be retained without paying for it.”

After the pleadings were closed, the case was referred to a referee who, after a hearing, concluded that the town was unjustly enriched by the additional borrow fill furnished by the plaintiff and that the plaintiff was entitled to damages of $14,000 from the town, that being the reasonable cost of furnishing this additional borrow fill in place and compacted. The town’s objections and exceptions to the report were overruled, and judgment against the town was rendered in the amount of $14,000. Although the judgment did not expressly find the issues in favor of the other two defendants, it did award costs to the defendant contractor and to the defendant surety company. The defendant town *564 appealed from the judgment on several grounds, and the plaintiff also appealed, claiming that the court erred in failing to include an award of interest on the $14,000 damages.

In the view which we take of these appeals, it is unnecessary to consider most of the town’s many assignments of error. The determinative question presented to us is whether the facts support the conclusion that the town will be unjustly enriched unless it is required to pay the plaintiff for furnishing 10,000 cubic yards of borrow fill in excess of the amount which it estimated was necessary to establish finished grades in accordance with the plans and specifications of the prime contract and on the basis of which the plaintiff contracted with the contractor.

The doctrine of unjust enrichment has been described as a doctrine “which is so broad as to include almost any case in which unfair dealing appears and so vague as to give no help in solving cases as they arise.” 3 Page, Contracts (2d Ed.) § 1503, p. 2567; see Fischer v. Kennedy, 106 Conn. 484, 498 (dis.), 138 A. 503. It applies “wherever justice requires compensation to be given for property or services rendered under a contract, and no remedy is available by an action on the contract.” 5 Williston, Contracts (Rev. Ed.) § 1479. “A right of recovery under the doctrine of unjust enrichment is essentially equitable, its basis being that in a given situation it is contrary to equity and good conscience for one to retain a benefit which has come to him at the expense of another. Franks v. Lockwood, 146 Conn. 273, 278, 150 A.2d 215; Schleicher v. Schleicher, 120 Conn. 528, 534, 182 A. 162.” Connecticut National Bank v. Chapman, 153 Conn. 393, 399, 216 A.2d 814. With no other test than what, *565 under a given set of circumstances, is just or unjust, equitable or inequitable, conscionable or unconscionable, it becomes necessary in any case where the benefit of the doctrine is claimed to examine the circumstances and the conduct of the parties and apply this standard.

Although the matter was strongly contested, the referee found that there was an undefined discrepancy between the topographical survey and the actual elevation of the existing grades on the site and that the survey indicated that 39,000 cubic yards of borrow fill would be necessary to establish proper finished elevations of the site in accordance with the plans and specifications of the prime contract. The plaintiff commenced the delivery of fill to the job on August 29, 1957. Its records disclose that by February 11, 1958, it had delivered 39,177.6 cubic yards. It nevertheless, with no notice to the contractor or the town, continued to deliver additional fill until September 24, 1958, by which time it had delivered in excess of 50,000 cubic yards. Although the plaintiff kept a record of its fill deliveries to the job, it did not discover the discrepancy until August or September, 1958, and did not make a written claim until February 12, 1959, when it demanded from the contractor $14,000 for 10,000 cubic yards, at $1.40 per cubic yard, of additional borrow fill in place and compacted. Although the referee made no finding as to when any claim was filed with the town, the plaintiff alleges that it filed its claim with the town and the contractor on February 12, 1959, “for payment for the said 10,000 additional cubic yards of borrow fill.” There is nothing in the record to indicate that either the town or the contractor received notice of, knew or had any reason to suspect the existence of any such claim on the *566 part of the plaintiff until the plaintiff rendered a bill for additional fill on February 12, 1959 — a full year after the date on which the plaintiff had completed delivery of the originally estimated 39,000 cubic yards of fill.

In view of this lack of notice and the long delay in presenting a claim for extra compensation, certain provisions of the subcontract between the plain- . tiff and the contractor are particularly relevant.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Connecticut Light & Power Co. v. Proctor
152 A.3d 470 (Supreme Court of Connecticut, 2016)
C & H Electric, Inc. v. Bethel
Supreme Court of Connecticut, 2014
Location Realty, Inc. v. Colaccino
949 A.2d 1189 (Supreme Court of Connecticut, 2008)
McGovern v. Proprietors of Cemetery
21 Mass. L. Rptr. 667 (Massachusetts Superior Court, 2006)
Ramondetta v. Amenta
903 A.2d 232 (Connecticut Appellate Court, 2006)
Vertex, Inc. v. City of Waterbury
898 A.2d 178 (Supreme Court of Connecticut, 2006)
Santagate v. Tower
833 N.E.2d 171 (Massachusetts Appeals Court, 2005)
Yale Diagnostic Radiology v. Estate of Fountain
838 A.2d 179 (Supreme Court of Connecticut, 2004)
Cd 36 Ct Limited v. Dart Building, No. Cv-00-0072838 S (May 31, 2002)
2002 Conn. Super. Ct. 6930 (Connecticut Superior Court, 2002)
Town of Columbia v. J.S. Nasin Company, No. Cv-01-0074739-S (Mar. 26, 2002)
2002 Conn. Super. Ct. 3758 (Connecticut Superior Court, 2002)
Rosier v. Reilly, No. Cv-01-0449340-S (Dec. 17, 2001)
2001 Conn. Super. Ct. 16647 (Connecticut Superior Court, 2001)
Riccio v. Riccio, No. Hsdp-107359 (May 1, 2001)
2001 Conn. Super. Ct. 6269 (Connecticut Superior Court, 2001)
Zaks v. Zaks, No. 546038 (Mar. 15, 2001)
2001 Conn. Super. Ct. 3652 (Connecticut Superior Court, 2001)
Gagne v. Vaccaro
766 A.2d 416 (Supreme Court of Connecticut, 2001)
City of New Haven v. Town of E. Haven, No. X01 98 0160402s (Dec. 12, 2000)
2000 Conn. Super. Ct. 15414 (Connecticut Superior Court, 2000)
C M Crocco Air v. Whiting Prods., No. Cv98 0261455 (Dec. 4, 2000)
2000 Conn. Super. Ct. 15221 (Connecticut Superior Court, 2000)
Lowe v. Durso, No. Cv99 06 67 99 (Apr. 6, 2000)
2000 Conn. Super. Ct. 4144 (Connecticut Superior Court, 2000)
Moschini v. Bristol Crane Service, No. Cv 98 0579527s (Nov. 18, 1999)
1999 Conn. Super. Ct. 15370 (Connecticut Superior Court, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
244 A.2d 404, 156 Conn. 561, 1968 Conn. LEXIS 637, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cecio-bros-v-town-of-greenwich-conn-1968.