Cd 36 Ct Limited v. Dart Building, No. Cv-00-0072838 S (May 31, 2002)

2002 Conn. Super. Ct. 6930
CourtConnecticut Superior Court
DecidedMay 31, 2002
DocketNo. CV-00-0072838 S
StatusUnpublished

This text of 2002 Conn. Super. Ct. 6930 (Cd 36 Ct Limited v. Dart Building, No. Cv-00-0072838 S (May 31, 2002)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cd 36 Ct Limited v. Dart Building, No. Cv-00-0072838 S (May 31, 2002), 2002 Conn. Super. Ct. 6930 (Colo. Ct. App. 2002).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.]

MEMORANDUM OF DECISION APPLICATION FOR PREJUDGMENT REMEDY
The plaintiff has brought an application for a prejudgment remedy pursuant to General Statutes § 52-278d. A hearing on said application commenced before the court on July 9, 2001. Thereafter, evidence was also presented on July 20, 2001, December 19, 2001 and January 14, 2002. The parties submitted legal memorandums of law to the court in support of their respective positions on February 15, 2002.

The plaintiff argues that defendant entered into a written contract with the plaintiff for construction work for projects known as the Shelton Technology Center and the Cross County Sewer line. The defendant, hereinafter referred to as "Dart" was hired by the plaintiff hereinafter referred to as "CD 36" to do site work, such as, excavation, blasting, paving and landscaping at the construction site. The contract, which was for a price of $1,732,000 lists CD 36 as the "Owner" and "Dart" as the contractor.

The plaintiff claims that on August 18, 2000 it conducted an inspection of a building pad prepared by Dart. According to CD 36, the inspection revealed deficiencies in the building pad, which would not allow further construction of a structure on the building pad.

An argument regarding the alleged deficiencies and defects ensued between CD 36's representative Cuminotto and Dart's president Cochiola. As a result of this argument, Cochiola ordered his workers off of the property, ending the workday early. When CD 36 became aware that Dart was leaving the site, Cuminotto notified the Shelton Police Department and CT Page 6931 barred Dart or its employees from returning to, or re-entering, the construction site. CD 36 claims that Dart by leaving the site, abandoned the remaining work which it had contracted to complete.

Thereafter, the plaintiff CD 36 hired new companies to complete Dart's work and to remedy alleged defects and deficiencies in work already done by Dart. CD 36 claims that corrective work and additional costs that have been incurred due to Dart's actions amount to more than the $152,202, prejudgment remedy which is being sought by this application.

Dart in defending against CD 36's claim, denies that its work was defective and/or deficient. It also denies that it abandoned the construction site on August 18, 2000. Dart claims that it had every intention of honoring its contract obligations with the plaintiff, but was prevented by doing so by the plaintiff, who had enlisted the Shelton Police Department's assistance in barring Dart from re-entering the construction site.

Dart additionally claims that the plaintiff CD 36 has not satisfied certain conditions precedent listed in the contract, prior to instituting litigation, including this application for a prejudgment remedy.

II.
General Statutes § 52-278d regarding prejudgment remedies in pertinent part states:

"The defendant shall have the right to appear and be heard at the hearing. The hewing shall be limited to a determination of (1) whether or not there is probable cause that a judgment in the amount of the prejudgment remedy sought, or in an amount greater than the amount of the prejudgment remedy sought, taking into account any defenses, counterclaims or set-offs, will be rendered in the matter in favor of the plaintiff . . . If the court, upon consideration of the facts before it and taking into account any defenses, counterclaims or set-offs, claims of exemption and claims of adequate insurance, finds that the plaintiff has shown probable cause that such a judgment will be rendered in the matter in the plaintiffs favor in the amount of the prejudgment remedy sought and finds that a prejudgment remedy securing the judgment should be granted, the prejudgment remedy applied for shall be granted as requested or as modified by the court."

CT Page 6932 The defendant in opposing the application for a prejudgment remedy argues that the plaintiff, CD 36, has not satisfied a condition precedent to pursuit of the litigation, as set forth in Section 4.4.1 of the written contract between the parties. Dart claims that CD 36 did not provide written notice of its claims against Dart to the Engineer and Dart, in writing, within three months of the condition giving rise to the claims, as required by Sections 4.3.1 and 4.3.2 of the contract. The court agrees with the defendant Dart.

Since written notice within this time frame is established by the contract to be a condition precedent to the institution of litigation, and since the time for CD to comply with the notice provisions has passed, its prejudgment remedy application should be denied.

II.
Prejudgment remedy proceedings do not address the merits of the action; they concern only whether and to what extent the plaintiff is entitled to have property of the defendant held in custody of the law pending adjudication of the merits of the action. Tyler v. Schnabel,34 Conn. App. 216, 219-20, 641 A.2d 388 (1994). The plaintiff does not have to establish that it will prevail. It has to establish that there is probable cause to sustain the validity of the claim. Id.; East Lyme v.Wood, 54 Conn. App. 394, 397, 735 A.2d 843 (1999); Dufraineau v. CHRO,236 Conn. 250, 261, 673 A.2d 101 (1996). Probable cause must exist as to both the merits of the action and damages.

CD 36's prejudgment remedy application is denied because of CD 36's failure to give notice, as required by the contract, precludes a finding of a probability of success at trial. The standard for a finding of probable cause requires the court to conclude that judgment will be rendered in favor of the plaintiff, taking into account any defenses, counterclaims or setoffs, claims of exemption and claims of adequate insurance, as stated in General Statutes § 52-278d. In evaluating whether probable cause exists that a judgment will enter in favor of the plaintiff, the court must evaluate any defenses raised by the defendant.Haxhi v. Moss 25 Conn. App. 16, 591 A.2d 1275, 1277 (1991). "A good defense . . . will be enough to show that there is no `probable cause that judgment will be rendered in the matter in favor of the plaintiff'"Id. at 20, quoting Augeri v. Wooding Co., 173 Conn. 426, 429, 378 A.2d 538 (1977).

The court agrees with the defendant Dart that courts have routinely enforced contract provisions that require written notice within specified time periods.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Silver v. Indemnity Insurance
79 A.2d 355 (Supreme Court of Connecticut, 1951)
Cecio Bros. v. Town of Greenwich
244 A.2d 404 (Supreme Court of Connecticut, 1968)
Augeri v. C. F. Wooding Co.
378 A.2d 538 (Supreme Court of Connecticut, 1977)
Hartford Federal Savings & Loan Ass'n v. Aetna Casualty & Surety Co.
206 A.2d 650 (Connecticut Superior Court, 1964)
Milford Power Co. v. Alstom Power, No. X04-Cv-00-0121672s (Jun. 28, 2001)
2001 Conn. Super. Ct. 8562 (Connecticut Superior Court, 2001)
Dufraine v. Commission on Human Rights & Opportunities
673 A.2d 101 (Supreme Court of Connecticut, 1996)
Tallmadge Bros. v. Iroquois Gas Transmission System, L.P.
746 A.2d 1277 (Supreme Court of Connecticut, 2000)
Haxhi v. Moss
591 A.2d 1275 (Connecticut Appellate Court, 1991)
Tyler v. Schnabel
641 A.2d 388 (Connecticut Appellate Court, 1994)
Town of East Lyme v. Wood
735 A.2d 843 (Connecticut Appellate Court, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
2002 Conn. Super. Ct. 6930, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cd-36-ct-limited-v-dart-building-no-cv-00-0072838-s-may-31-2002-connsuperct-2002.