C & H Electric, Inc. v. Bethel

CourtSupreme Court of Connecticut
DecidedAugust 12, 2014
DocketSC19162
StatusPublished

This text of C & H Electric, Inc. v. Bethel (C & H Electric, Inc. v. Bethel) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
C & H Electric, Inc. v. Bethel, (Colo. 2014).

Opinion

****************************************************** The ‘‘officially released’’ date that appears near the beginning of each opinion is the date the opinion will be published in the Connecticut Law Journal or the date it was released as a slip opinion. The operative date for the beginning of all time periods for filing postopinion motions and petitions for certification is the ‘‘officially released’’ date appearing in the opinion. In no event will any such motions be accepted before the ‘‘officially released’’ date. All opinions are subject to modification and technical correction prior to official publication in the Connecti- cut Reports and Connecticut Appellate Reports. In the event of discrepancies between the electronic version of an opinion and the print version appearing in the Connecticut Law Journal and subsequently in the Con- necticut Reports or Connecticut Appellate Reports, the latest print version is to be considered authoritative. The syllabus and procedural history accompanying the opinion as it appears on the Commission on Official Legal Publications Electronic Bulletin Board Service and in the Connecticut Law Journal and bound volumes of official reports are copyrighted by the Secretary of the State, State of Connecticut, and may not be repro- duced and distributed without the express written per- mission of the Commission on Official Legal Publications, Judicial Branch, State of Connecticut. ****************************************************** C AND H ELECTRIC, INC. v. TOWN OF BETHEL (SC 19162) Palmer, Zarella, Eveleigh, Espinosa and Robinson, Js. Argued March 19—officially released August 5, 2014

Jeffrey J. White, with whom, on the brief, were Greg- ory R. Faulkner and Elizabeth K. Wright, for the appel- lant (plaintiff). Benjamin B. Manchak, with whom were Joshua A. Hawks-Ladds and, on the brief, Richard C. Robinson, for the appellee (defendant). Opinion

ROBINSON, J. This appeal requires us to consider whether a property owner’s conduct constituted ‘‘active interference’’ for purposes of an exception to a ‘‘no damages for delay’’ clause in a construction contract, which otherwise would preclude a contractor from recovering additional costs for delays caused by the owner, instead giving a contractor additional time to complete the job. The plaintiff, C & H Electric, Inc., appeals1 from the judgment of the trial court in part for the defendant, the town of Bethel (town), on the plaintiff’s claims of breach of contract and unjust enrichment arising from the plaintiff’s role in the town’s renovation of its high school.2 The trial court rejected the plaintiff’s claim that the town must reimburse it for additional costs incurred during its electrical work due to interference from the town’s ongoing asbestos abate- ment work at the school. On appeal, the plaintiff insists that the trial court: (1) applied an improper standard for determining ‘‘active interference,’’ arguing that it needed to show only an affirmative, wilful act by the town that unreasonably interfered with the plaintiff’s work, rather than bad faith or gross negligence as the trial court required; and (2) incorrectly concluded that the town’s conduct did not fall within either of two judicially created exceptions to the enforcement of ‘‘no damages for delay’’ clauses adopted by this court in White Oak Corp. v. Dept. of Transportation, 217 Conn. 281, 289, 585 A.2d 1199 (1991) (White Oak). We agree with the plaintiff that it need not show bad faith or gross negligence to establish active interfer- ence, but conclude that the town’s conduct in this case did not rise to the level of active interference or fall within either of the claimed White Oak exceptions. We therefore agree with the trial court’s decision that the plaintiff is not entitled to compensation under any of the ‘‘no damages for delay’’ exceptions at issue here. Accordingly, we affirm the trial court’s judgment. The record reveals the following facts, as stipulated by the parties or found by the trial court, and relevant procedural history. The town originally built the school in the 1960s and later expanded it in the 1970s. Consis- tent with typical construction practices of that era, the town installed significant quantities of materials that contained asbestos during those projects. The town abated some of these materials during renovations in the 1980s, but left some in place because its contractors had difficulty reaching them at that time. According to an environmental consultant later hired by the town, this was ‘‘not an uncommon condition.’’ Several years later, in 2004, the town decided to reno- vate and expand the school by updating the existing structure and building a large addition. Before begin- ning construction, the town hired an environmental consultant to look for hazardous materials within the school, including asbestos. The consultant discovered some of the asbestos left behind in the existing building during the earlier renovations and recommended that the town remove it before beginning the renovation project. The town hired an abatement contractor to perform the removal work. The town expected the abatement contractor to complete its work during the summer of 2006, before the start of classes in the fall of 2006, and before any new construction, which was slated to begin in early 2007. In a July, 2006 letter to the town’s Board of Selectmen, the town’s school building committee chairperson explained: ‘‘[W]e are addressing [the asbestos abatement] now and not during the actual construction phase, which would have complicated our project and more than likely would have added signifi- cant costs.’’ For reasons not clear from the record, the abatement contractor completed just 70 percent of the abatement work during that summer before students returned for the 2006–2007 school year. The town suspended the abatement work before the start of classes, choosing instead to complete the remaining 30 percent of the work later in the year and over the following summer. In an August, 2006 letter to the town’s first selectman, the town’s environmental consultant explained: ‘‘The work that did not get completed this year was the removal of the locker banks and cleaning of the corridor ceilings on the first and second floors. Leaving these areas will not immediately affect the new construction work . . . .’’ Although the town had yet to complete the abate- ment, it chose to move forward with the construction. Through its construction manager, the town initially opened the project for bidding at the end of the summer of 2006, but later asked contractors to hold their bids open for two additional months so that the town could seek additional financing for the project. The plaintiff held its bid open and, after lengthy negotiations, con- tracted with the town to perform the project’s electrical work for a price of more than three million dollars. The parties’ contract contained a ‘‘no damages for delay’’ clause limiting the town’s liability for any delays caused by the town. An addendum to the contract pro- vided in relevant part: ‘‘Notwithstanding anything to the contrary in the [contract], an extension in the [time to complete the work] shall be the sole remedy of [the plaintiff] for any (1) delay in the commencement, prose- cution or completion of the work, (2) hindrance or obstruction in the performance of the work, (3) loss of productivity, or (4) other similar claims whether or not such delays are foreseeable, contemplated, or uncon- templated . . . .’’ The parties included a single exception to this ‘‘no damages for delay’’ clause, expressly excluding from its scope any claims for ‘‘a [d]elay . . . caused by acts of the [town] constituting active interference with [the plaintiff’s] performance of the [w]ork . . .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

U.S. F/U/B/A Williams Electric Co. v. Metric Constructors, Inc.
480 S.E.2d 447 (Supreme Court of South Carolina, 1997)
Gherardi v. Trenton Board of Education
147 A.2d 535 (New Jersey Superior Court App Division, 1958)
Hydro-Hercules Corporation v. Gary Excavating, Inc.
353 A.2d 714 (Supreme Court of Connecticut, 1974)
418 Meadow St. Assoc. v. Clean Air Partners
43 A.3d 607 (Supreme Court of Connecticut, 2012)
Murtha v. City of Hartford
35 A.3d 177 (Supreme Court of Connecticut, 2011)
Cecio Bros. v. Town of Greenwich
244 A.2d 404 (Supreme Court of Connecticut, 1968)
Pellerin Construction, Inc. v. Witco Corp.
169 F. Supp. 2d 568 (E.D. Louisiana, 2001)
FCM Group, Inc. v. Miller
17 A.3d 40 (Supreme Court of Connecticut, 2011)
Tricon Kent Co. v. Lafarge North America, Inc.
186 P.3d 155 (Colorado Court of Appeals, 2008)
American Bridge Co. v. State
245 A.D. 535 (Appellate Division of the Supreme Court of New York, 1935)
Taylor-Fichter Steel Construction Co. v. Niagara Frontier Bridge Commission
261 A.D. 288 (Appellate Division of the Supreme Court of New York, 1941)
Kalisch-Jarcho, Inc. v. City of New York
448 N.E.2d 413 (New York Court of Appeals, 1983)
Corinno Civetta Construction Corp. v. City of New York
493 N.E.2d 905 (New York Court of Appeals, 1986)
Gasparini Excavating Co. v. Pennsylvania Turnpike Commission
187 A.2d 157 (Supreme Court of Pennsylvania, 1963)
P.T. & L. Construction Co. v. State, Department of Transportation
531 A.2d 1330 (Supreme Court of New Jersey, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
C & H Electric, Inc. v. Bethel, Counsel Stack Legal Research, https://law.counselstack.com/opinion/c-h-electric-inc-v-bethel-conn-2014.