Farrell Construction Co. v. Jefferson Parish

693 F. Supp. 490, 1988 U.S. Dist. LEXIS 9617, 1988 WL 90980
CourtDistrict Court, E.D. Louisiana
DecidedAugust 25, 1988
DocketCiv. A. 86-4242
StatusPublished
Cited by11 cases

This text of 693 F. Supp. 490 (Farrell Construction Co. v. Jefferson Parish) is published on Counsel Stack Legal Research, covering District Court, E.D. Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Farrell Construction Co. v. Jefferson Parish, 693 F. Supp. 490, 1988 U.S. Dist. LEXIS 9617, 1988 WL 90980 (E.D. La. 1988).

Opinion

ARCENEAUX, District Judge.

Currently before the Court is the motion of the defendant, Burk & Associates, Inc. (Burk) for summary judgment. In addition, Burk has filed a “motion in limine” which seeks to exclude consideration of certain of the plaintiff’s claims. Below the Court summarizes the undisputed facts relevant to disposition of the motions.

INTRODUCTION

On January 20, 1983, the plaintiff, Farrell Construction Co. (Farrell) entered into two construction contracts with the defendant, Jefferson Parish, in which Farrell agreed to become the general contractor on two drainage and pump station projects. Jefferson Parish entered into a separate contract with Burk, in which Burk agreed to serve as the engineer or architect for the projects. Farrell entered into a subcontract with Emile M. Babst Company (Babst), in which Babst agreed to provide mechanical services on the projects.

On September 29, 1986, Farrell filed this lawsuit against Jefferson Parish and Burk, its jurisdictional basis being diversity of citizenship. Farrell claimed that the defendants prepared defective and inadequate drawings, plans, and specifications upon which Farrell relied in performing its obligations under the construction contract. These defective submissions allegedly “substantially impeded the progress” of the project and “caused Farrell to substantially change its planned sequence of construction of both projects.” (Complaint i[ 13). The defendants also allegedly required Farrell to perform work beyond that called for in its contracts and unreasonably delayed approval of shop drawings and other documents submitted by Farrell. Jefferson Parish allegedly further breached its contract by failing to timely provide to Farrell equipment called for by the contracts and by failing to pay Farrell for its services upon completion of the contract. In addition to the injuries allegedly suffered directly by Farrell, Farrell claims that Babst, the mechanical subcontractor, was required by the defendants’ acts to perform substantial additional work for which it has claimed additional compensation from Farrell. Therefore, Farrell seeks “to recover additional compensation for the account of Babst.” (Complaint ¶ 38).

It is undisputed that Farrell is not pursuing claims ex contractu against Burk, as there is no privity between Farrell and Burk. Instead, “Farrell asserts only tort claims against Burk.” (Farrell’s Memo in Opposition, p. 3). Burk now contends that *492 (1) Burk owed no duty of care to Farrell under ordinary principles of Louisiana law, (2) any duty Burk might have otherwise owed to Farrell was negated by an exculpatory provision contained in the contract between Farrell and Jefferson Parish, (3) Farrell’s claims have prescribed, and (4) Farrell may not recover for the additional expenses and work of Babst.

DUTY OF ENGINEER/ARCHITECT TO PERSONS NOT IN PRIVITY

Burk argues that C.H. Leavell & Co. v. Glantz Contracting Corp. of La., Inc., 322 F.Supp. 779 (E.D.La.1971), entirely disposes of Farrell’s claims. In Leavell, id. at 781, a general contractor on a construction project sued the architects who prepared the plans for the project, alleging that the architects’ actions produced unreasonable delays in the completion of the project. The Court framed the issues as follows: “whether a contract between a building owner and its architect constitutes a stipulation pour autrui in favor of the contractor engaged to construct the building, and whether the architect is impliedly a party to the owner’s agreement with the construction contractor.” Id.

The Court found no privity between the contractor and the architects and determined that there was no stipulation pour autrui (or third party beneficiary contract) in favor of the contractor. The Court granted a partial summary judgment in favor of the architects, but stated that “Leavell has asserted other claims in tort. For reasons orally assigned, the motion is denied as to such claims.” Id. at 784.

This Court does not read Leavell to prohibit claims ex delicto such as those of Farrell in the present case. Rather, Lea-vell addresses only contractual claims and, as noted above, expressly excludes from its consideration any tort-based claims. Moreover, caselaw from Louisiana and many other jurisdictions recognizes the existence of a duty of care owed by an architect to persons with whom the architect does not have privity.

In Gurtler, Hebert & Co. v. Weyland Machine Shop, Inc., 405 So.2d 660, 662 (La.App. 4th Cir.1981), the issue was

whether a subcontractor made defendant in a suit by the contractor for breach of contract can assert in a third party de-mahnd a cause of action in tort against the architect where no privity of contract exists between the architect and his subcontractor.

The Court concluded that privity was not essential to the tort claim and found the existence of an independent duty owed by the architect to the subcontractor. Gurtler, Hebert & Co., 405 So.2d at 662.

In Milton J. Womack, Inc. v. State House of Representatives, 509 So.2d 62 (La.App. 1st Cir.), writ denied, 513 So.2d 1211 (La. 1987), the Court held that the contractor on a project to renovate the state capítol building could recover in tort for economic injuries from the architectural firm which negligently prepared defective plans. In discussing the standard of care to be applied to the defendant, the Court stated that

The duty of an architect is to exercise the degree of skill ordinarily employed, under similar circumstances, by members of his profession in good standing and to use reasonable care and diligence, along with his best judgment, in the application of his skill.... The architect’s duty is not to provide perfect plans but to exercise the degree of professional care and skill customarily employed by other architects in the same general area.

Id. at 64.

Because there is ample authority to support Farrell’s claim under Louisiana principles of tort law, Burk’s first argument be rejected. See also American Fidelity Fire Insurance Co. v. Pavia-Byrne Engineering, 393 So.2d 830, 837 (La.App. 2d Cir.1981) (liability of architect to surety); see generally Annot., 63 A.L.R.3d 249 (compilation of cases from various jurisdictions).

EXCULPATORY PROVISIONS IN JEFFERSON PARISH/FARRELL CONTRACT

Burk’s second argument is based upon Article 9.11 of the contract between Jeffer *493 son Parish and Farrell, which provides as follows:

Neither ENGINEER’S authority to act under this Article 9 or elsewhere in the Contract Documents nor any decision made by ENGINEER in good faith either to exercise or not exercise such authority shall give rise to any duty or responsibility of ENGINEER to CONTRACTOR or any Subcontractor, any manufacturer, fabricator, supplier or distributor, or any of their agents or employees or any other person performing any of the work.

Article 1 of the contract defines “Contract Documents” as follows:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

MR Pittman Group, LLC v. Plaquemines Parish Government
182 So. 3d 291 (Louisiana Court of Appeal, 2015)
Harbor v. Davie Shoring, Inc.
176 So. 3d 619 (Louisiana Court of Appeal, 2015)
Caro Properties (A), LLC v. City of Gretna
3 So. 3d 29 (Louisiana Court of Appeal, 2008)
Inter Contr Corp v. City of Dallas Texas
407 F.3d 708 (Fifth Circuit, 2003)
Interstate Contracting Corp. v. City of Dallas
320 F.3d 539 (Fifth Circuit, 2003)
Colbert v. BF Carvin Const. Co.
600 So. 2d 719 (Louisiana Court of Appeal, 1992)
Newberry Square Dev. Corp. v. Southern Landmark, Inc.
578 So. 2d 750 (District Court of Appeal of Florida, 1991)
SK Whitty & Co. v. LL LAMBERT
576 So. 2d 599 (Louisiana Court of Appeal, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
693 F. Supp. 490, 1988 U.S. Dist. LEXIS 9617, 1988 WL 90980, Counsel Stack Legal Research, https://law.counselstack.com/opinion/farrell-construction-co-v-jefferson-parish-laed-1988.