Farrell Construction Company v. Jefferson Parish, Louisiana and Burk & Associates, Inc.

896 F.2d 136, 16 Fed. R. Serv. 3d 545, 1990 U.S. App. LEXIS 3705, 1990 WL 17173
CourtCourt of Appeals for the Fifth Circuit
DecidedMarch 15, 1990
Docket88-3764, 89-3292
StatusPublished
Cited by60 cases

This text of 896 F.2d 136 (Farrell Construction Company v. Jefferson Parish, Louisiana and Burk & Associates, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Farrell Construction Company v. Jefferson Parish, Louisiana and Burk & Associates, Inc., 896 F.2d 136, 16 Fed. R. Serv. 3d 545, 1990 U.S. App. LEXIS 3705, 1990 WL 17173 (5th Cir. 1990).

Opinion

CLARK, Chief Judge:

Farrell Construction Company in this consolidated appeal challenges the dismissal of its action against Jefferson Parish, Louisiana, and Burk and Associates, Inc. (No. 88-3764) and the district court’s denial of its “Motion to Review and Amend Judgment or, in the Alternative, to Clarify its Judgment” (No. 89-3292). Farrell, hired by the Parish as general contractor for the construction of two drainage and pump stations, asserted claims on behalf of itself and its mechanical subcontractor, Emile Babst and Company, against the Parish and Burk, the projects’ design and inspection engineer. Babst was not joined as a party to the suit. On the eve of trial and after two years of pretrial litigation, the district court learned that Babst was a Louisiana corporation, nondiverse from the Parish or Burk. The court held Babst to be an indispensable party and dismissed the entire action for want of subject matter jurisdiction. We conclude that Babst is neither a real party in interest nor a party necessary for a just adjudication of the action. The record does not support the district court’s alternate conclusion that Babst and Farrell colluded to create jurisdiction. Accordingly, we reverse and remand.

I

In 1983 Farrell, a Tennessee corporation with its principal place of business in Texas, successfully bid on two pumping station projects in response to solicitations by the Parish. The Parish contracted separately with Burk, a Louisiana corporation, to act as engineer for the projects. Babst, another Louisiana corporation, became Farrell’s subcontractor for the projects’ mechanical work.

The projects were completed after significant delay which Farrell and Babst alleged was caused by the Parish and Burk and resulted in significant damages. Babst made a written demand on Farrell for its damages but did not file suit. Instead, Farrell and Babst entered into a “prelitigation agreement.” The contract’s preamble stated that the “complexity and interrelationship of the claims to be asserted by Farrell and Babst are such that the parties hereto believe and, therefore, agree that it will be mutually beneficial for Farrell to make one consolidated action against Jefferson Parish, Louisiana.... Farrell and Babst agree that it is in their best interests to fully cooperate with each other in the prosecution of claims against Jefferson Parish, Louisiana which would include damages sustained by Farrell as well as damages sustained by Babst.”

In consideration of those reasons, the parties agreed to the following in pertinent part:

(1) Phil B. Abernethy of Jackson, Mississippi would represent Farrell in the prosecution of its and Babst’s claims against the Parish and Burk; Babst would be represented by Laurence D. Rudman of New Orleans, Louisiana; however, Rudman would enter appearances in any litigation as an attorney for Farrell unless any con *139 flict of interest arose in which case Rud-man would represent only Babst;

(2) if a general award was made to Farrell that did not designate a portion for Babst, the award would be divided between the two according to the percentage amount each party’s claim bore to the total amount claimed; e.g., if Babst’s claim represented 35% of the total claim presented by Farrell, Babst would receive 35% of any award to Farrell;

(3) each party would pay its respective attorney fees and would share court and expert expenses based upon the percentage of each party’s claim to the total claim;

(4) Babst agreed to accept its percentage of the claim in full satisfaction of any claims it had against Farrell arising from the projects, and each party released the other from any liability arising from Babst’s performance of the construction subcontract excluding that resulting from latent defects; however, Babst reserved the right to approve any settlement agreement; and

(5) any recovery against either party by the Parish would reduce that party’s percentage share by the amount of the recovery.

In September 1986, two months after the prelitigation agreement was executed, Farrell filed suit against the Parish and Burk. Farrell alleged, among other things, that the defendants had submitted defective plans and specifications which Farrell relied upon in performing its obligations under the construction contracts. The defective submissions allegedly caused Farrell to change significantly the construction sequence of both projects, resulting in large delay damages. Farrell additionally claimed that Babst was compelled to perform unplanned extra work at considerable expense as a result of the allegedly defective plans and specifications. Farrell’s complaint claimed these damages “for the account of Babst.”

Burk moved for summary judgment against Farrell and against Farrell on behalf of Babst. The court granted the motion against Farrell on behalf of Babst, but denied it in large part with regard to Farrell’s own claims. Farrell Constr. Co. v. Jefferson Parish, 693 F.Supp. 490 (E.D.La.1988). Farrell does not appeal this decision.

While deliberating on Burk’s motion for summary judgment, the court discovered Babst’s Louisiana citizenship and ordered the parties to brief the issue whether Babst’s citizenship and presence as a party would destroy complete diversity. The court found that the “secret” prelitigation agreement constituted a joint venture between Farrell and Babst, thereby rendering Babst an indispensable party to the action. As such, the court ruled, Babst’s presence destroyed diversity. The court dismissed the action for lack of jurisdiction. In the alternative, the court held that the action should be dismissed as a sanction because Farrell and Babst had colluded to “ ‘pull the wool over the eyes of the court’ to fraudulently invoke diversity jurisdiction.”

II

Farrell contends in this court that Louisiana law permits a prime contractor, such as Farrell, to assert as part of its own claim the damages of a subcontractor not in privity with the owner and then “pass through” to the subcontractor its portion of the damages. Farrell argues that a subcontractor does not become a real party in interest or an indispensable party when a primary contractor asserts such pass-through damages. As a result, Farrell maintains that Babst need not and should not have been joined in this action. Farrell further argues that the prelitigation agreement does not elevate Babst to the status of an indispensable party or a real party in interest. According to Farrell, the district court erred by holding to the contrary and dismissing the action. Farrell also disputes the district court’s conclusion that it colluded with Babst to create diversity jurisdiction.

III

All plaintiffs must be diverse in citizenship from all defendants in an action brought under the jurisdiction conferred by *140 28 U.S.C. § 1332(a). Babst is a Louisiana corporation, nondiverse from both the Parish and Burk. Babst’s joinder as a plaintiff in this action would deprive the district court of jurisdiction. The issue therefore becomes whether Babst must be joined. Our analysis is guided principally by two Federal Rules of Civil Procedure.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
896 F.2d 136, 16 Fed. R. Serv. 3d 545, 1990 U.S. App. LEXIS 3705, 1990 WL 17173, Counsel Stack Legal Research, https://law.counselstack.com/opinion/farrell-construction-company-v-jefferson-parish-louisiana-and-burk-ca5-1990.