Havens Steel Company v. Randolph Engineering Company

813 F.2d 186, 22 Fed. R. Serv. 1206, 1987 U.S. App. LEXIS 3077
CourtCourt of Appeals for the Eighth Circuit
DecidedMarch 9, 1987
Docket85-1800
StatusPublished
Cited by16 cases

This text of 813 F.2d 186 (Havens Steel Company v. Randolph Engineering Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Havens Steel Company v. Randolph Engineering Company, 813 F.2d 186, 22 Fed. R. Serv. 1206, 1987 U.S. App. LEXIS 3077 (8th Cir. 1987).

Opinion

JOHN R. GIBSON, Circuit Judge.

Havens Steel Company appeals from the district court’s 1 judgment awarding Randolph Engineering Company $105,599.11 for the cost of capital used to pay additional expenses caused by Havens’ breach of contract. Havens Steel Co. v. Randolph Eng’g Co., 613 F.Supp. 514, 541-42 (W.D.Mo.1985). Havens argues that Randolph failed to prove to a reasonable certainty the *187 amount and the cost of capital used to finance the additional work. We affirm.

Havens entered a contract to fabricate and erect certain steel components to be used in the expansion of a cement plant owned and operated by Medusa Cement Company. Havens subcontracted with Randolph to perform the erection portion of Havens’ contract. After the cement plant was completed, Havens and Randolph disputed their respective contractual obligations. Havens filed a complaint in the district court, alleging breach of contract and seeking declaratory relief and damages. Randolph filed a counterclaim alleging that Havens interfered with its work, causing delays and extra work, thus causing Randolph to incur additional expenses.

After a bench trial, the district court found for Randolph on all liability claims and on the majority of Randolph’s counterclaims for damages. Our only concern in this appeal is with the district court’s finding in favor of Randolph on its damage claim for cost of capital. 2 In this counterclaim, Randolph sought to recover the interest on the capital Randolph used to finance the additional expenses associated with the delays and extra work caused by Havens. Havens does not dispute the district court’s finding that Havens’ breach of contract forced Randolph to pay over $188,-000 in additional costs. 3 Havens contends, however, that Randolph failed to introduce sufficient evidence to prove either the amount of money it borrowed or the interest it paid for the money used to pay these expenses.

Havens first argues that the evidence was insufficient to support the district court’s conclusion that Randolph’s cost of capital is recoverable under Missouri law 4 either as ordinary contract damages or under the theory that the contract contained an “equitable adjustment” provision. 5 The district court reasoned that Randolph could recover ordinary contract damages for the cost of its capital by proving either the cost of borrowing additional funds or the cost of using its own capital. Havens Steel Co., 613 F.Supp. at 541-42 (citing Maryland Port Admin. v. C.J. Langenfelder & Son, Inc., 50 Md.App. 525, 438 A.2d 1374 (1982)). Gene Vogan, one of Randolph’s project managers, testified that Randolph borrowed under a continuing line of credit to finance its work on the Medusa project. He testified that while other projects were also financed out of Randolph’s single line of credit, the amount *188 borrowed for any particular project could be ascertained from Randolph’s records. Tr. at 460-66, 654-55. Based on this testimony and its finding that Randolph incurred over $188,000 in expenses resulting from Havens’ breach, the district court concluded that the evidence was sufficient to prove that Randolph either borrowed money or used its own money to pay over $188,000 in expenses necessitated by Havens’ breach of contract.

Under Missouri law, the existence and amount of damages must be proved with reasonable certainty. The evidence must not leave the matter to speculation, and in the event of uncertainty, the amount of estimated loss must at least be supported by the best evidence available. E.g., Hargis v. Sample, 306 S.W.2d 564, 569 (Mo.1957); Sides Constr. Co. v. Arcadia Valley R-II School Dist., 565 S.W.2d 761, 768 (Mo.Ct.App.1978).

In this diversity case, we must apply the law as we think the highest court of Missouri would, e.g., Tucker v. Paxson Mach. Co., 645 F.2d 620, 624 (8th Cir.1981), and while we are not bound by the district court’s interpretations, we give great weight to the decisions of the experienced district court judge on state law questions. E.g., Northern States Power Co. v. ITT Meyer Indus., 777 F.2d 405, 413 (8th Cir.1985); Shidler v. All Am. Life & Fin. Corp., 775 F.2d 917 (8th Cir.1985). We agree with the district court’s conclusion that a Missouri court would apply to the present situation the reasoning articulated in C.J. Langenfelder, supra, and conclude that Randolph could recover damages for its cost of capital by proving that it incurred a cost by either borrowing additional money or using its own money. In Missouri, a claim for the cost of money used to pay expenses necessitated by a breach of contract is a claim for damages, not prejudgment interest. E.g., Killian Constr. Co. v. Tri-City Constr. Co., 693 S.W.2d 819, 828-29 (Mo.Ct.App.1985); Groppel Co. v. United States Gypsum Co., 616 S.W.2d 49, 63-64 (Mo.Ct.App.1981). We see nothing in these cases or any others brought to our attention indicating that in awarding damages a Missouri court would ignore economic reality and distinguish the cost of borrowed funds from the cost of using one’s own interest-bearing capital.

Havens does not dispute the district court’s finding that Randolph spent over $188,000 as a result of Havens’ breach. This finding alone establishes with reasonable certainty that Randolph either borrowed additional money or used its own money to pay these expenses. Havens misses the mark with its argument that Vogan’s testimony, by itself, fails to establish with reasonable certainty that Randolph borrowed additional funds to pay the costs caused by Havens’ breach. While Vogan’s testimony substantiates the uncontested finding that Randolph spent over $188,000 as a result of Havens’ breach, it matters little to the extent it does or does not prove that Randolph borrowed funds, instead of using its own, to finance these added costs.

Havens’ second argument is that there is insufficient evidence to support the district court’s use of certain interest rates to calculate Randolph’s cost of capital. Vogan testified that during the time Randolph worked on the Havens project, Randolph paid “1 percent over prime to borrow money,” and 15% represented a fair and accurate figure of Randolph’s borrowing cost. Tr. at 462. The district court found that “[t]he record contains no proof to the contrary.” 613 F.Supp. at 541.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Evans, Mechwart, Hambleton & Tilton, Inc. v. Triad Architects, Ltd.
965 N.E.2d 1007 (Ohio Court of Appeals, 2011)
Siemens Westinghouse Power Corp. v. Dick Corp.
320 F. Supp. 2d 120 (S.D. New York, 2004)
Energy Capital Corp. v. United States
47 Fed. Cl. 382 (Federal Claims, 2000)
Business Men's Assurance Co. of America v. Graham
891 S.W.2d 438 (Missouri Court of Appeals, 1994)
AROK Construction Co. v. Indian Construction Services
848 P.2d 870 (Court of Appeals of Arizona, 1993)
City of Charlotte v. Skidmore, Owings & Merrill
407 S.E.2d 571 (Court of Appeals of North Carolina, 1991)
Chestnut Hill Development Corp. v. Otis Elevator Co.
739 F. Supp. 692 (D. Massachusetts, 1990)
Rosebud Sioux Tribe v. A & P Steel, Inc.
874 F.2d 550 (Eighth Circuit, 1989)
Farrell Construction Co. v. Jefferson Parish
693 F. Supp. 490 (E.D. Louisiana, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
813 F.2d 186, 22 Fed. R. Serv. 1206, 1987 U.S. App. LEXIS 3077, Counsel Stack Legal Research, https://law.counselstack.com/opinion/havens-steel-company-v-randolph-engineering-company-ca8-1987.