United States v. Peavey Barge Line

748 F.2d 395, 1984 U.S. App. LEXIS 16873
CourtCourt of Appeals for the Seventh Circuit
DecidedNovember 8, 1984
DocketNo. 84-1251
StatusPublished
Cited by23 cases

This text of 748 F.2d 395 (United States v. Peavey Barge Line) is published on Counsel Stack Legal Research, covering Court of Appeals for the Seventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Peavey Barge Line, 748 F.2d 395, 1984 U.S. App. LEXIS 16873 (7th Cir. 1984).

Opinion

FLAUM, Circuit Judge.

This is an appeal of an admiralty case by the defendants following a bench trial which was limited to the issue of damages. The district court awarded the United States $425,373.24 for damages to a lock, dam, and bridge on the Mississippi River plus prejudgment interest at a rate of 11% from the date of the accident. For the reasons stated below, we affirm the decision of the district court.

I.

On July 15, 1978, the defendant Motor Vessel Gremco, operated by the Peavey Barge Line, was towing nine loaded barges near Rock Island, Illinois when one of the barges struck the guide wall of Lock and Dam No. 15, which are owned by the United States. This collision caused the remaining barges to become detached and collide with the lock’s miter gates, the Rock Island Arsenal Bridge, and the roller gates of the dam. The Rock Island District of the United States Corps of Engineers began temporary repairs to the miter gates on July 31, 1978, and completed these repairs on April 27, 1979. The United States employed a private contractor for the guide wall repairs, which were completed on June 6, 1980. Repairs to the Rock Island Arsenal Bridge were completed in mid to late 1979 by a private contractor as part of a previously planned major bridge rehabilitation and renovation. At the trial in September 1983, the dam’s roller gates had not yet been repaired, but the Corps of Engineers submitted an estimate of repair costs which went unchallenged by the defendant.

The United States filed suit against the defendant on June 30,1981, claiming that it should recover for the damages it sustained to the lock and dam based on a theory of absolute liability under 33 U.S.C. § 408 (1982)1 and to the bridge based on a negligence theory. Following a confession of liability by the defendant, the district court entered summary judgment for the United States on the issue of liability on December 28, 1982, and ordered a $1,000 pecuniary penalty against each of the defendant’s barges pursuant to 33 U.S.C. §§ 411 and 412. After a two-day trial at which the sole issue was the reasonableness of the damages claimed by the United States, the district court awarded the United States $425,373.242 plus prejudgment interest at a rate of 11% per annum from [398]*398the date of the collision to the date of the judgment.

[397]*397It shall not be lawful for any person or persons to take possession of or make use of for any purpose, or build upon, alter, deface, destroy, move, injure, obstruct by fastening vessels thereto or otherwise, or in any manner whatever impair the usefulness of any sea wall, bulkhead, jetty, dike, levee, wharf, pier, or other work built by the United States, or any piece of plant, floating or otherwise, used in the construction of such work under the control of the United States, in whole or in part, for the preservation and improvement of any of its navigable waters or to prevent floods, or as boundary marks, tide gauges, surveying stations, buoys, or other established marks, nor remove for ballast or other purposes any stone or other material composing such works____

[398]*398On appeal, the defendant claims that the district court’s award of damages for such items as use of plant and equipment, use of shop and yards, motor vehicle usage, and labor on the guide wall was erroneous because these items lacked any evidentiary support. The defendant also challenges the award of overhead as being unrelated to the repair work caused by the collision and as being computed on items that constitute overhead themselves. Finally, the defendant disputes the grant of prejudgment interest from the date of the collision, if interest is granted at all, rather than from the date that the United States expended money to make the repairs. These issues will be addressed in turn below.

II.

A. Disputed Elements of Damages

In an admiralty case, as in a civil action under Rule 52(a) of the Federal Rules of Civil Procedure, the findings of fact of the district court may not be set aside unless clearly erroneous. McAllister v. United States, 348 U.S. 19, 20, 75 S.Ct. 6, 7-8, 99 L.Ed. 20 (1954); Feeder Line Towing Service, Inc. v. Toledo, Peoria & W. R.R. Co., 539 F.2d 1107, 1110 (7th Cir. 1976). According to the Supreme Court, a finding is “clearly erroneous” when although there is evidence to support it, the appellate court on the entire evidence is left with the definite and firm conviction that a mistake has been committed. United States v. United States Gypsum Co., 333 U.S. 364, 395, 68 S.Ct. 525, 541, 92 L.Ed. 746 (1948). When reviewing for clear error in the district court’s findings, the appellate court must be especially circumspect if there has been conflicting evidence on controverted issues of fact. Indiana State Employees Ass’n v. Negley, 501 F.2d 1239, 1241 (7th Cir.1974).

In this case, the defendant disputes the district court’s award of $52,327.00 for use of plant and equipment on the miter gate repair project, $2,262.39 for use of shop and yards, $1,644.00 for motor vehicle usage, and $4,825.59 for the Army Corps of Engineers’ labor on the guide wall repairs.3 The defendant claims that the Corps merely offered testimony identifying each item rather than proving that the charge was necessary and reasonable.4 The district court found that the charges for use of plant and equipment, use of shop and yards, and motor vehicle usage were items [399]*399which bore a “reasonable relationship to the Corps’ experience in equipment breakage and obsolescence.” United States v. Peavey Barge Line, 590 F.Supp. 319 at 323-324 (C.D.Ill.1984) (“Memorandum Opinion”). The district court noted that certain amounts for items claimed by the United States could be determined by applying a fixed percentage to specific costs. Id. However, the court noted that the plaintiff has to prove that there exists a reasonable basis to apply that item to a particular repair claim. Id. Applying this test, the court disallowed the United States’ claim of $38.41 for handling charges, $1,101.62 for per diem and transportation, $24.90 for reproduction services, and $922.56 for tool, furniture, and equipment replacement.5 Id.

The district court also found that the $4,825.59 for Corps labor related to the guide wall repairs was an appropriate charge. Id. at 324-325. The court held that this charge was supported by testimony that the figure was derived from time cards for the period that Corps laborers worked on the repairs. Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re the Complaint of Ingram Barge Co.
102 F. Supp. 3d 1008 (N.D. Illinois, 2015)
Teknowledge Corp. v. United States
85 Fed. Cl. 235 (Federal Claims, 2009)
United States v. Capital Sand Co., Inc.
466 F.3d 655 (Eighth Circuit, 2006)
Arkansas River Corp. v. United States
947 F. Supp. 941 (N.D. Mississippi, 1996)
United States v. Schooner Windspirit
32 V.I. 285 (Virgin Islands, 1995)
O'TOOL v. Hathaway
461 N.W.2d 161 (Supreme Court of Iowa, 1990)
Certified Midwest, Inc. v. Local Union No. 738
686 F. Supp. 189 (N.D. Illinois, 1988)
Havens Steel Company v. Randolph Engineering Company
813 F.2d 186 (Eighth Circuit, 1987)
Dow Chemical Pacific Ltd. v. Rascator Maritime S.A.
640 F. Supp. 882 (S.D. New York, 1986)
United States v. Republic Marine, Inc.
627 F. Supp. 1425 (C.D. Illinois, 1986)
Shappert Engineering v. Steel City Marine Transport
620 F. Supp. 1377 (E.D. Missouri, 1985)
Larsen v. A.C. Carpenter, Inc.
620 F. Supp. 1084 (E.D. New York, 1985)
Central Rivers Towing, Inc. v. City of Beardstown
750 F.2d 565 (Seventh Circuit, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
748 F.2d 395, 1984 U.S. App. LEXIS 16873, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-peavey-barge-line-ca7-1984.