City of Charlotte v. Skidmore, Owings & Merrill

407 S.E.2d 571, 103 N.C. App. 667, 1991 N.C. App. LEXIS 928
CourtCourt of Appeals of North Carolina
DecidedAugust 20, 1991
Docket9026SC527
StatusPublished
Cited by10 cases

This text of 407 S.E.2d 571 (City of Charlotte v. Skidmore, Owings & Merrill) is published on Counsel Stack Legal Research, covering Court of Appeals of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Charlotte v. Skidmore, Owings & Merrill, 407 S.E.2d 571, 103 N.C. App. 667, 1991 N.C. App. LEXIS 928 (N.C. Ct. App. 1991).

Opinion

PARKER, Judge.

I.

This is a civil action for breach of contract and breach of implied warranty. Desiring to upgrade and beautify downtown Charlotte, North Carolina, plaintiff on 11 January 1982 contracted with defendant Skidmore, Owings and Merrill (“SOM”) to design an urban streetscape to be known as Tryon Street Transit Mall. The mall was to cover eleven city blocks, nine on Tryon Street and two on Trade Street. Defendant SOM’s design provided for a system of sidewalks, crosswalks, roadways, storm drainage, curbing, bus shelters, benches, light posts, and trash receptacles. The plan included reducing vehicular traffic on Tryon Street from six lanes to four and widening sidewalks to encourage pedestrian traffic. Plaintiff eventually paid $7,967,772.70 for construction of the mall.

On 22 November 1983, plaintiff contracted with defendant Weiss Brothers Construction Company, Inc., (“Weiss”) to do the actual work of constructing the mall. The work included removing the *670 old curbs and gutters and installing new granite curbing and taking up the old concrete sidewalks and laying new and bigger sidewalks. In addition, the streets were newly paved and new pedestrian crosswalks harmonious with the design of the sidewalks were installed. Defendant Weiss also installed a new electrical system.

Defendant SOM’s design called for the use of granite and concrete blocks (“pavers”), eighteen inches square, in the mall sidewalks and crosswalks. The pavers in the central area of the mall were pink; those in other areas were in two shades of grey. Underneath all the pavers were setting beds supported by eleven-inch concrete subslabbing. The sidewalks were designed to bear only pedestrian traffic and were constructed of pavers two inches thick, but. crosswalks and driveways were designed to withstand vehicular traffic and used three-inch pavers. In addition, some pavers laid over utility vaults were only one inch thick. The original contract specifications for setting beds included the following:

1. Pedestrian areas (General): Portland cement/sand bed with latex additive bond coat for setting pavers such as Laticrete 4237 or Tec-crete by Fuller Co.
2. Pedestrian areas (minimum depth): Thinset sand/cement mortar mix.
3. Vehicular areas (roadway and drives): Liquid latex additive as above, Portland cement/sand bed with cement/latex additive bond coat for setting pavers.

The sand-cement bed was to be two inches thick in vehicular areas and one inch thick in pedestrian areas. Setting bed materials were to be (i) spread evenly over the entire area to be paved and (ii) screeded to a minimum level that would provide the minimum thickness indicated when the pavers had been put in place. Other contract specifications as to granite paving listed materials in the setting beds but included only Portland cement, sand, and a latex additive bond coat. Instructions as to execution of granite paving included the following:

B. Granite paving:

1. Setting Bed: The sand/cement bedding course shall consist of sand and Portland Cement in the proportions of one (1) part cement and three (3) parts sand by volume, mixed dry until the mass is of uniform color. Mixing may *671 be done in an approved batch mixer or by hand on a clean type surface. The bedding course of moist mortar shall be placed and shaped upon the base so that finish depth shall not be less than as indicated. The bedding shall be shaped to a true surface, parallel with the surface of the finished paving by means of a template and the bed shall be struck off until proper alignment is secured. After final shaping, the bedding shall not be disturbed prior to applying the latex additive bond coat and laying the stone.
2. Latex Additive Bond Coat: apply in accordance with the manufacturer’s instructions and recommendations and as approved.

According to the contract between plaintiff and defendant SOM, all plaintiff’s instructions to the contractor were to be issued through SOM. SOM was to make monthly trips to the project site to observe construction activities, render decisions in the field, and interpret drawings during construction. SOM was to “endeavor to guard [plaintiff] against defects and deficiencies in the work of the Contractor” but was not required to make exhaustive or continuous on-site observations to check the quality or quantity of the work. Although under the proposed contract SOM was to provide a full time site representative, this provision did not appear in the final agreement. The contract provided that SOM’s observations did not render it responsible for construction means, methods, techniques, or procedures or for the contractor’s failure to carry out the work in accordance with the contract documents. Supplementary conditions to the specifications for the project generally reiterated that SOM would not have control or charge of such matters. SOM agreed to perform all services under the contract “in conformity with the standards of reasonable care and skill of [its] profession.”

A. Setting Bed Problems

Construction of the project began in January of 1984. Defendant Weiss prepared two crosswalk setting beds by mixing sand and cement in a ratio of three to one. No additional water or other wetting agent was added. When defendant WeiSs began to lay pavers in these crosswalk setting beds, the latex bond coat called for by the contract specifications would not adhere to the sand-cement mixture. Discussions of two issues ensued among representatives of plaintiff and defendants SOM and Weiss.

*672 First, as to latex, it became clear that defendant Weiss did not believe the contract specifications required latex as an additive in any of the setting beds. Plaintiff asked defendant SOM to determine whether latex was needed. Defendant SOM’s representative eventually told plaintiffs representative that all use of latex, as additive or bond coat, could be omitted.

The second issue involved how much water to use in preparing the setting beds. After a meeting on 10 May 1984, SOM wrote to plaintiff as follows:

In response to your requests of May 3, 1984[,] and May 10, 1984[,] to confirm the proper setting bed for the precast concrete and granite pavers, we have contacted the National Building Granite Quarries Association, National Concrete Masonry Association, paving manufacturers, granite fabricators, latex additive manufacturers, contractors, [and] our consultants, and have examined this item within SOM and have the following recommendation:
1. The setting bed for the pedestrian and vehicular areas should consist of a “dry sand-cement” setting bed at the specified 3/1 ratio with sufficient water added to the mix to permit the bed to be screeded and trowelled as necessary. Thoroughly mix the sand and cement to a visually uniform color consistency throughout. Guage [sic] the sand-cement setting bed with a sufficient quantity of water to bring the setting bed materials to the proper consistency for placing the pavers. The 1" setting beds for the pedestrian areas should remain as per the contract documents.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

PRESNELL v. SNAP-ON SECURECORP., INC.
M.D. North Carolina, 2022
Crescent Univ. City Venture, LLC v. Ap Atl., Inc.
2019 NCBC 46 (North Carolina Business Court, 2019)
Heron Bay Acquisition, LLC v. United Metal Finishing, Inc.
2014 NCBC 15 (North Carolina Business Court, 2014)
Prichard Enterprises, Inc. v. Adkins
858 F. Supp. 2d 576 (E.D. North Carolina, 2012)
St. Louis, LLC v. FINAL TOUCH
899 A.2d 1018 (New Jersey Superior Court App Division, 2006)
Design Plus Store Fixtures, Inc. v. Citro Corp.
508 S.E.2d 825 (Court of Appeals of North Carolina, 1998)
Madden v. Carolina Door Controls, Inc.
449 S.E.2d 769 (Court of Appeals of North Carolina, 1994)
Haas v. Warren
436 S.E.2d 259 (Court of Appeals of North Carolina, 1993)
Willie's Const. Co., Inc. v. Baker
596 N.E.2d 958 (Indiana Court of Appeals, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
407 S.E.2d 571, 103 N.C. App. 667, 1991 N.C. App. LEXIS 928, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-charlotte-v-skidmore-owings-merrill-ncctapp-1991.