LaGasse v. Gardner

298 S.E.2d 393, 60 N.C. App. 165, 1982 N.C. App. LEXIS 3262
CourtCourt of Appeals of North Carolina
DecidedDecember 21, 1982
Docket8129SC1346
StatusPublished
Cited by6 cases

This text of 298 S.E.2d 393 (LaGasse v. Gardner) is published on Counsel Stack Legal Research, covering Court of Appeals of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
LaGasse v. Gardner, 298 S.E.2d 393, 60 N.C. App. 165, 1982 N.C. App. LEXIS 3262 (N.C. Ct. App. 1982).

Opinion

*166 BECTON, Judge.

I

At trial, without a jury, plaintiffs’ evidence tended to show that they entered into a contract with defendant, Shorn Construction Company, for the construction of a Nationwide Modular Home. After moving into the house, plaintiffs found structural defects —no footing under the basement floor — and cracks in the walls and floor. Plaintiffs also testified that paint cracked and peeled off and that defendant failed to rough-grade the yard. Further, two experts in construction testified, among other things, (1) that an eight-inch retaining wall was used instead of the twelve-inch retaining wall required by the North Carolina State Building Code (Code); (2) that window and door lintels did not conform to the Code; (3) that there was no termite shield; (4) that the basement wall was out of plumb about one-quarter of an inch; and (5) that a two by twelve inch strap which should have been placed on each truss was not installed, causing a two-inch separation at the peak of the roof. The cost of repairs of the defects was estimated at $10,000 to $12,000.

Defendant, through his testimony and the testimony of other witnesses, responded to each of plaintiffs’ allegations by showing that he was willing to correct certain alleged defects that had never been brought to his attention; that the house was built according to the contract and conformed to the Code; and that none of the alleged defects affected the house structurally.

Judgment was entered in favor of plaintiffs, and plaintiffs were awarded damages of $10,000. Defendant appealed.

II

Combining related assignments of error, defendant first argues that the trial court erred by allowing testimony by the two expert witnesses concerning requirements and violations of the Code and by making findings based on the experts’ testimony, when (i) the Code was not in evidence; (ii) the trial court did not take judicial notice of the Code; and (iii) neither the Code nor the particular sections relied upon was pleaded as required by county ordinance. We have three responses. First, the North Carolina State Building Code is a statewide Code, not a county ordinance. *167 See N.C. Gen. Stat. § 143438(e) (1981). Second, plaintiffs’ Amended Complaint refers to the Code, and defendant, therefore, cannot claim surprise. Third, essentially identical testimony to that complained of by defendant was admitted without objection. The expert witness Rowe testified that Transylvania County had enacted the statewide Code. Finally, the formal taking of judicial notice was not necessary under the facts of this case.

HH HH HH

Defendant next argues that the trial court erred in (i) allowing the expert witnesses to testify about the likely result of building a load-bearing wall at the edge of a floating slab; (ii) the likelihood of structural cracks in the basement floor as a result of building a load-bearing wall at the edge of the floating slab; and (iii) the structural stability of the house based on the defects in the basement wall and floor. We find no error in this aspect of the trial. N.C. Gen. Stat. § 8-58.12 (1981) allows opinion testimony without hypothetical questions. Further, the expert witness Rowe testified that when a slab floor in a basement is built about four inches thick on a “floating slab,” with certain conditions present, the wall would get “out of plumb.” Rowe testified that the walls as built in plaintiffs’ house were likely to cause structural cracks in the basement floor.

IV

Defendant finally contends that the trial court used the wrong measure of damages and, therefore, erred when it found as a fact and concluded, as a matter of law, that plaintiffs were damaged in the sum of $10,000. Defendant argues that damages for defects or omissions in the performance of a building contract, when part of the work must be undone and when plaintiff is already in possession of the house, are measured, not by the cost of repairs, but by determining the difference in value between what the house cost and what it is worth. See, Robbins v. Trading Post, Inc., 251 N.C. 663, 111 S.E. 2d 884 (1960).

In this case, the trial court, after making the following findings of fact concerning defects and deficiencies in “workmanship,” specifically found “[t]hat the reasonable costs of repair of these matters will be $10,000:”

*168 4. That the footings in the house constructed by defendant construction company do not extend three inches beyond the load-bearing walls, as required by the North Carolina Building Code and the contract between the parties.
5. That 8-inch concrete block was used on load-bearing walls on which there was a fill in excess of 4 feet against these walls; that the use of 8-inch block instead of 12-inch block under these circumstances does not comply with the North Carolina Building Code or the contract between the parties.
6. That the Defendant construction company did not use masonry caps as set forth in the material specifications and its failure to do so constitutes a violation of the North Carolina Building Code.
7. That the Defendant construction company failed to install termite shields on the house as required by the material specifications.
8. That the Defendant construction company did not complete the painting of the house as specified in the material specifications.
9. That the Defendant construction company did not extend metal lintels at least 4 inches over beyond the aperture as required by the North Carolina Building Code.
10. That the Defendant construction company installed no anchor bolts as required by the material specifications and the North Carolina Building Code.

Based on the facts found, the trial court concluded that “defendant Shorn Construction Company breached its contract with the plaintiffs and that the plaintiffs have been damaged as a result of said breach in the sum of $10,000. . . .” In Robbins, our Supreme Court said:

‘The fundamental principle which underlies the decisions regarding the measure of damages for defects or omissions in the performance of a building or construction contract is that a party is entitled to have what he contracts for or its equivalent. What the equivalent is depends upon the cir *169 cumstances of the case. In a majority of jurisdictions, where the defects are such that they may be remedied without the destruction of any substantial part of the benefit which the owner’s property has received by reason of the contractor’s work, the equivalent to which the owner is entitled is the cost of making the work conform to the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Charlotte v. Skidmore, Owings & Merrill
407 S.E.2d 571 (Court of Appeals of North Carolina, 1991)
Warfield v. Hicks
370 S.E.2d 689 (Court of Appeals of North Carolina, 1988)
Waynick Construction, Inc. v. York
319 S.E.2d 304 (Court of Appeals of North Carolina, 1984)
Kenney v. Medlin Construction & Realty Co.
315 S.E.2d 311 (Court of Appeals of North Carolina, 1984)
Stiles v. Charles M. Morgan Co., Inc.
307 S.E.2d 409 (Court of Appeals of North Carolina, 1983)
Burke County Public Schools Board of Education v. Juno Construction Corp.
306 S.E.2d 557 (Court of Appeals of North Carolina, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
298 S.E.2d 393, 60 N.C. App. 165, 1982 N.C. App. LEXIS 3262, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lagasse-v-gardner-ncctapp-1982.