Sides Construction Co. v. Arcadia Valley R-II School District

565 S.W.2d 761, 1978 Mo. App. LEXIS 2032
CourtMissouri Court of Appeals
DecidedApril 4, 1978
Docket38582
StatusPublished
Cited by19 cases

This text of 565 S.W.2d 761 (Sides Construction Co. v. Arcadia Valley R-II School District) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sides Construction Co. v. Arcadia Valley R-II School District, 565 S.W.2d 761, 1978 Mo. App. LEXIS 2032 (Mo. Ct. App. 1978).

Opinion

DOWD, Presiding Judge.

This appeal involves a dispute between Sides Construction Company, respondent, and Arcadia Valley R-II School District, appellant, concerning the construction of a school and gymnasium. Respondent contended the appellant owed it $15,000 as the final payment on a construction contract plus $1,510 for additional work. Appellant counterclaimed alleging breaches of the contract in the amount of $158,000.

In this court tried case the trial judge heard complicated and diverse testimony from fourteen witnesses and, we believe, resolved the issues in a fair and reasonable judgment. The judgment entered awarded respondent $3,933.73, representing the $15,-000 due on the contract plus $1,265.04 for additional work offset by damages for breaches of the contract totaling $12,331.31 with costs assessed against respondent.

Arcadia Valley R-II School District appeals. . This court has been aided by scholarly briefs filed by both parties and commends the attorneys. For reasons hereinafter given, we affirm.

*764 The principal parties to this dispute, Sides Construction Company and Arcadia School District, entered into a standard form “owner and contractor” agreement on September 10, 1969, for the construction of a classroom building and gymnasium for the sum of $1,096,531. The architect for the project was Haywood Snipes, who aided in the designation of specifications and drawings to be incorporated into the contract. Other provisions of the contract provided for monthly progress payments and for final payment, “provided the Work has then been completed, the Contract fully performed, and a final Certificate for Payment has been issued by the Architect.”

Work proceeded on the project and, although it was not fully completed, the school district took possession of the classroom building in January of 1971. The gymnasium was available for occupancy in late August of 1971. Monthly progress payments of 90% of the contract price were made as scheduled and in June of 1971 the architect made arrangements for release of the final 10% due on the contract with the exception of $15,000 withheld to guarantee completion of “punch list” items and to cover possible damages for late completion. Prior to occupation of the classroom building and subsequent thereto Mr. Snipes, the architect, prepared “preliminary” punch lists of incomplete or defective aspects of the work. He conceded that the usual practice calls for the preparation by the architect of one punch list after the contractor gives notice that the building is complete, but claimed the preliminary lists were made at the request of Sides and were motivated by the necessity of getting the buildings ready for occupancy due to deteriorating conditions in the old school.

Subsequent to the payment of the 10% holdback a dispute continued concerning the existence of defects and whether they had been corrected. Beginning in 1972 Arcadia contacted several of Sides’ subcontractors directly as well as several other companies and paid them to correct alleged defects in the work and in 1975 contracted with Walter Brockmiller, Inc., a second general contractor, to complete work on hardware and locks, power outlets, folding partitions, roof repairs, exterior painting, a backed up exterior drain, and water-damaged ceiling tile. For much of this work Brockmiller utilized the same subcontractors who had performed the initial work for Sides.

Legal action concerning the project was initiated when Robbins Floors, Inc., one of Sides’ materials suppliers, sought recovery of $650. Sides subsequently entered a stipulation that it was liable in that amount to Robbins. Sides impleaded Arcadia School District in the amount of the Robbins claim and further alleged Arcadia’s liability to them for the balance due on the construction contract, stating that it had performed all conditions precedent and terms of the contract. In its amended counterclaim Arcadia alleged compliance with the contract and that Sides had breached the contract by defective and improper installation and by failure to conform its work to plans and specifications with respect to the following items: (a) the roof, with resulting damage to ceiling tiles, plaster, paint, walls and flooring due to leakage, (b) wiring, (c) intercom system, (d) ventilation and heating system, (e) exterior paint, (f) stage doors, (g) carpeting, (h) locks and hardware, (i) outside drain, and (j) electrical, mechanical, heating and ventilation equipment.

The court’s judgment awarded Sides the $15,000 due on the contract and $1,265 for additional work on extension of a drain. As an offset to the final payment the court awarded to Arcadia $12,331.31 representing amounts paid by Arcadia to correct defects. 1

(a) $250 Sides had agreed to pay for testing exterior paint to determine if a “primer” coat had been applied, (b) $5,380.47 paid to Brock-miller, Inc. (the second general contractor) for performance of its work with the court expressly deducting from the Brockmiller bill of $9,585.82 the amount attributable to its exteri- or painting ($3,672 expressly allocated to painting and $533.35 of the general contractor fee allocable to the painting), (c) $105.15 paid to *765 Vans Electric Company to correct electrical circuitry in the home economics area, (d) $437.07 paid to M.C.S. Engineering for rewiring the public address system in the gymnasium, (e) $1,430.10 paid to Simplex Time Recorder Company to connect several clocks into the master system, (f) $1,207.82 paid to Gale’s Heating & Cooling, Inc., $398.35 paid to Phillip Frueh and $122.35 paid to Barber Coleman for work related to the heating system not automatically starting, and (g) $3,000 of the architectural fee paid by Arcadia for work performed more than 30 days after the contract’s completion dates.

Appellant Arcadia School District’s first alleged ground of error alleges that the trial court erroneously received and used evidence of an attempted “settlement” agreement in arriving at its final judgment, as evidenced by the failure to award appellant that portion of the Brockmiller bill attributable to exterior painting. Appellant claims the court was enforcing a settlement agreement reached in a meeting held at the Arcadia School on October 3,1973, at which appellant claims respondent agreed to repaint an exterior canopy and correct other agreed upon defects within sixty days if appellant would release its claim for defects in other exterior painting and damages for late completion. This action is claimed to be improper because (a) even if a settlement agreement had been reached, the uncontradicted evidence established that the defects had not been corrected within sixty days if at all, (b) offers of settlement are inadmissible, and (c) the offer of settlement was beyond the scope of the pleadings.

We hold that the trial court correctly admitted evidence of the meeting between the parties and their attorneys in October of 1973. In a court-tried case the trial judge is allowed wide latitude in the admission of evidence, the court being more qualified than a jury to consider evidence of a transaction and utilize only that part which is competent in arriving at its judgment. Lee v. Rolla Speedway, Inc., 539 S.W.2d 627, 632 (Mo.App.1976).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Catroppa v. Metal Building Supply, Inc.
267 S.W.3d 812 (Missouri Court of Appeals, 2008)
Boyd v. Lollar
985 S.W.2d 403 (Missouri Court of Appeals, 1999)
Ken Cucchi Construction, Inc. v. O'Keefe
973 S.W.2d 520 (Missouri Court of Appeals, 1998)
Ballenger v. Castle Rock Building Corp.
904 S.W.2d 62 (Missouri Court of Appeals, 1995)
Blackwelder v. Blissett
861 S.W.2d 343 (Missouri Court of Appeals, 1993)
Luna v. Smith
861 S.W.2d 775 (Missouri Court of Appeals, 1993)
Weindel v. DeSoto Rural Fire Protection Association, Inc.
765 S.W.2d 712 (Missouri Court of Appeals, 1989)
Havens Steel Company v. Randolph Engineering Company
813 F.2d 186 (Eighth Circuit, 1987)
Fort Zumwalt School District v. Recklein
708 S.W.2d 754 (Missouri Court of Appeals, 1986)
McDermott v. Burpo
663 S.W.2d 256 (Missouri Court of Appeals, 1983)
Twin River Construction Co. v. Public Water District No. 6
653 S.W.2d 682 (Missouri Court of Appeals, 1983)
State v. Reggins
645 S.W.2d 113 (Missouri Court of Appeals, 1982)
Barry v. Barrale
598 S.W.2d 574 (Missouri Court of Appeals, 1980)
Dan Ficken Pools, Inc. v. Flynn
592 S.W.2d 213 (Missouri Court of Appeals, 1979)
Haggard v. Mid-States Metal Lines, Inc.
591 S.W.2d 71 (Missouri Court of Appeals, 1979)
C. E. Preston, Inc. v. Four County Farm Center, Inc.
589 S.W.2d 114 (Missouri Court of Appeals, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
565 S.W.2d 761, 1978 Mo. App. LEXIS 2032, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sides-construction-co-v-arcadia-valley-r-ii-school-district-moctapp-1978.