Phoenix Assurance Company of New York v. Appleton City, Missouri

296 F.2d 787, 1961 U.S. App. LEXIS 3029
CourtCourt of Appeals for the Eighth Circuit
DecidedDecember 7, 1961
Docket16721_1
StatusPublished
Cited by13 cases

This text of 296 F.2d 787 (Phoenix Assurance Company of New York v. Appleton City, Missouri) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Phoenix Assurance Company of New York v. Appleton City, Missouri, 296 F.2d 787, 1961 U.S. App. LEXIS 3029 (8th Cir. 1961).

Opinion

VAN OOSTERHOUT, Circuit Judge.

Plaintiff Phoenix Assurance Company of New York (Phoenix), a corporate surety writing bonds for compensation, brought this action for declaratory judgment to have its rights and liabilities determined upon a construction bond and a statutory bond it had furnished the City of Appleton City, Missouri (City) on behalf of Reser, d/b/a Continental Construction Company, a contractor who had entered into a written contract to construct a sewage system for the City. The City in a counterclaim and cross-petition asserted that Reser had not completed the contract in accordance with its terms, that the City is entitled to liquidated damages specified in the contract for delay, and to actual damages for the amount necessary to complete the construction, *789 and asked that plaintiff’s liability upon its bonds for such damages be established and allowed. The City also prayed that it be allowed penalties and attorneys’ fees pursuant to V.A.M.S. § 375.420, for vexatious delay.

Various parties holding claims for labor and material furnished on the project intervened in the action and prayed for establishment of their claims and for judgment against Phoenix upon its bonds for the amounts found due them.

Final judgment was entered determining that Reser had not substantially performed his contract with the City and that Phoenix was liable on its bonds for liquidated damages for delay, actual damages, penalties and attorneys’ fees for vexatious delay. The judgment fixes the amount of such damages. The claims of the intervenors were established against Phoenix. Phoenix has appealed from the final judgment. Jurisdiction is based upon diversity of citizenship.

Phoenix asserts points entitling it to a reversal as follows:

“I.
The trial court erred in entering judgment for the defendant on its cross claim and against plaintiff because the contract itself states that the decisions of the engineer shall be final and conclusive on all parties. ■K* í!* #
II.
The trial court erred in finding and rendering money judgment against plaintiff on defendant City’s counterclaim. * * *
III.
The court erred in finding for the defendant and against the plaintiff on plaintiff’s claim for additional sums due from the defendant on account of work performed under the contract. * * *
IV.
The court erred in adjudging that the intervenor Lee Matthews Machinery and Rental Company recover against plaintiff.
V.
The court erred in allowing interest on the claims of certain intervenors against plaintiff.”

Said points will be considered in the order stated.

I.

Phoenix contends that the contract between Reser and the City specifically provided that the decision of the City’s engineer was to be conclusive as to all parties upon the question of whether the materials and workmanship conformed to the specifications, and that the city engineer approved and accepted the performance of the contract by his letter to the City dated May 20, 1957.

As a result of a pretrial conference, the parties agreed that certain issues of law be determined by the court, leaving the question of amount of damages that might be due either party for later adjudication. The issues thus submitted, as stated by the court, are:

“(1) Were the regulations of the State Division of Health integrated within the terms of the contract so that approval of the construction by that body was necessary before the project could be complete?
(2) Under the terms of the contract was the governing body of Appleton City required to accept the system as complete, or was approval by its engineer binding upon the city?
(3) If approval by the city engineer, Uri Seiden, was binding on the city, did he, in fact, approve the project?”

The court in a memorandum opinion (not reported), dated March 30, 1959, expresses its views upon such issues. The court treated the submission of the above stated issues as a motion for summary judgment on certain issues of liability alone, as contemplated by Rule 56 (c) of the Federal Rules of Civil Procedure, 28 U.S.C.A.

*790 Upon the first issue, the court found that the State Health Department regulations were not expressly made a part of the specifications or the contract, and expressed doubt whether the standards of performance set out in such regulations constitute part of the contract, but found it' unnecessary to determine such issue because of its view that the contract called for acceptance by the governing body of the City, and that the City had never accepted the work.

In Missouri and generally, it appears to be'well-established that parties to a building contract may agree that a designated person, such as a named architect or engineer, shall determine questions relating to the performance of the contract and the amount due, and that such determination shall be final and conclusive, absent fraud or gross mistake. Martinsburg & Potomac R. R. Co. v. March, 114 U.S. 549, 5 S.Ct. 1035, 29 L.Ed. 255; Kihlberg v. United States, 97 U.S. 398, 24 L.Ed. 1106; United Const. Co. v. City of St. Louis, 334 Mo. 1006, 69 S.W.2d 639; Stiers Bros. Const. Co. v. Moore, Mo.App., 158 S.W.2d 253.

In the cases just cited and in other cases relied upon by Phoenix, the court found that the contracts clearly placed the responsibility for finally determining a disputed issue upon a designated person. Here, the City contends and the court determined that the contract required acceptance by the governing body of the City. Our reading of the contract satisfies us that the contract is ambiguous with respect to the issue of who was to approve the performance.

A contract is ambiguous if it is reasonably susceptible of different tenable constructions. Maritz, Inc., v. ACF-Wrigley Stores, Inc., 8 Cir., 283 F.2d 75, 78; Paisley v. Lucas, 346 Mo. 827, 143 S.W.2d 262, 267.'

In the Maritz case, supra, we quoted and applied the rules of construction pertaining to ambiguous contracts as stated by the Supreme Court of Missouri in Veatch v. Black, 363 Mo. 190, 250 S.W.2d 501, 507, as follows:

“ ‘A contract of doubtful meaning will be given a construction which will make it fair and reasonable between the parties and will not give one party an unfair advantage of another. Mecartney v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Haney v. Portfolio Recovery Associates, L.L.C.
837 F.3d 918 (Eighth Circuit, 2016)
Daniel Haney v. Portfolio Recovery Associates
895 F.3d 974 (Eighth Circuit, 2016)
Schaub v. VonWald
638 F.3d 905 (Eighth Circuit, 2011)
McCarthy Bros. Construction Co. v. Pierce
832 F.2d 463 (Eighth Circuit, 1987)
McCARTHY BROTHERS CONSTRUCTION COMPANY v. PIERCE
832 F.2d 463 (Eighth Circuit, 1987)
McCarthy Bros. Const. Co. v. Pierce
626 F. Supp. 981 (E.D. Missouri, 1986)
Sides Construction Co. v. Arcadia Valley R-II School District
565 S.W.2d 761 (Missouri Court of Appeals, 1978)
Barnwell & Hays, Inc. v. Glen T. Sloan
564 F.2d 254 (Eighth Circuit, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
296 F.2d 787, 1961 U.S. App. LEXIS 3029, Counsel Stack Legal Research, https://law.counselstack.com/opinion/phoenix-assurance-company-of-new-york-v-appleton-city-missouri-ca8-1961.