McCARTHY BROTHERS CONSTRUCTION COMPANY v. PIERCE

832 F.2d 463, 1987 U.S. App. LEXIS 14108
CourtCourt of Appeals for the Eighth Circuit
DecidedOctober 22, 1987
Docket86-2415
StatusPublished

This text of 832 F.2d 463 (McCARTHY BROTHERS CONSTRUCTION COMPANY v. PIERCE) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McCARTHY BROTHERS CONSTRUCTION COMPANY v. PIERCE, 832 F.2d 463, 1987 U.S. App. LEXIS 14108 (8th Cir. 1987).

Opinion

832 F.2d 463

McCARTHY BROTHERS CONSTRUCTION COMPANY, a Missouri
Corporation, Appellant,
v.
Samuel R. PIERCE, Jr., in his official capacity as Secretary
of the United States Department of Housing & Urban
Development, and National Church Residences of St. Charles,
Missouri, an Ohio non-profit corporation, Appellees.

No. 86-2415.

United States Court of Appeals,
Eighth Circuit.

Submitted June 12, 1987.
Decided Oct. 22, 1987.

Jeffrey T. Demerath, St. Louis, Mo., for appellant.

Eugene Lipscomb of H.U.D., Kansas City, Mo., for appellees.

Before ARNOLD and WOLLMAN, Circuit Judges and HENLEY, Senior Circuit Judge.

WOLLMAN, Circuit Judge.

McCarthy Brothers Construction Company appeals from a district court1 judgment that denied its claim for an incentive fee under a construction contract and granted the counterclaim of National Church Residences of St. Charles, Missouri, for overpayment on that contract, 626 F.Supp. 981. We affirm.

* On September 29, 1981, National Church Residences of St. Charles, Missouri (National Church), entered into a contract with McCarthy Brothers Construction Company (McCarthy) for the construction of 134 units of housing for the elderly known as Jaycee Fairgrounds Village of St. Charles, Missouri (the Project). The Project was financed by a building loan secured by a mortgage and subject to the terms of the Building Loan Agreement between National Church and the Department of Housing and Urban Development (HUD) pursuant to the Housing Act of 1959, 12 U.S.C. Sec. 1701q.

Included in the construction contract between National Church and McCarthy were FHA Form 2442A, "Construction Contract--Cost Plus,"2 and AIA Document A201, "General Conditions of the Contract for Construction," a document prepared by the American Institute of Architects. Under the contract, McCarthy was entitled to receive the actual cost of construction plus a fee of $247,272, with a stated maximum.

In addition to the basic contract fee, McCarthy was eligible for an incentive fee if its work was completed at a cost savings by the prescribed date. Specifically, Article 3A(3) of the contract provided:

If the work is completed prior to the time for completion specified in this contract, the Owner shall make an incentive payment to the Contractor. The amount of the payment shall be ascertained according to the instructions on the attachment entitled Incentive Payment Computation which is made a part hereof.

The parties have stipulated that the amount of the incentive fee calculated pursuant to the attachment is $131,850. The only controversy is whether McCarthy's work was "completed prior to the time for completion specified in [the] contract."

The original contract required completion by November 30, 1982. This completion date was extended to March 14, 1983, by change orders executed by McCarthy, National Church, and National Church's architect, Mackey and Associates (Mackey), and approved by HUD in accordance with the terms of the contract. The dispute involves the following four contract provisions:

Article 2D provides:

The date of substantial completion shall be the date the HUD representative signs the hUD [sic] Representatives Trip Report, (Form HUD 5379), which indicates construction is complete and which Report is substantially endorsed by the Chief Architect as being the Final Inspection Report.

Article 2C states in pertinent part:

If the work is not substantially completed in accordance with the Drawings and Specifications, including any authorized changes, by the date specified above, or by such date to which the contract time may be extended, the maximum sum stated in Article 3A(1) below shall be reduced by $2,472.82 as liquidated damages, for each day of delay until the date of substantial completion.

Article 8.1.33 of AIA Document A201 provides:

The Date of Substantial Completion of the Work or designated portion thereof is the Date certified by the Architect when construction is sufficiently complete, in accordance with the Contract Documents, so the Owner can occupy or utilize the Work or designated portion thereof for the use for which it is intended.

Article 1A states that "[t]he provisions of [Form 2442A] * * * take precedence over all inconsistent provisions in the said AIA General Conditions."

The parties have stipulated to the following chronology of events concerning the issue of substantial completion.

On February 10, 1983, McCarthy submitted Change Order No. 16 to National Church and Mackey concerning the installation of 120 "grab bars" for Project bathtubs that were not reflected in the original specifications. Referenced in Attachment A to Change Order No. 16 was a letter from McCarthy to Mackey pertaining to the grab bar work, which advised Mackey that "[t]ime is of the essence, inasmuch as we are nearing final acceptance of this project and estimated completion of the work outlined by this Proposal is six weeks from the date of the Change Order approval." The line item of Change Order No. 16 labeled "Delay due to the Above Changes" was left blank, however. Mackey and National Church executed Change Order No. 16 on February 14, 1983, and HUD approved it on March 9, 1983.

On March 1, 1983, McCarthy executed and submitted AIA Document G704, "Certificate of Substantial Completion," to National Church and Mackey, who executed it on March 4, 1983.

On March 14, 1983, St. Charles city officials inspected the Project and certified it as available for occupancy and in compliance with the St. Charles Fire Department's Fire Safety Survey.

During the morning of March 15, 1983, McCarthy, National Church, Mackey, and HUD Project Representatives conducted a walk-through of the building and an inspection of the final punch list. That afternoon a public dedication and ribbon-cutting ceremony was held at the Project, National Church took occupancy of the Project, its resident managers moved into the building, and its liability insurance went into effect. In addition, Mackey executed the "Architect's Certificate" portion of FHA Form 2403-A, whereby Mackey approved McCarthy's request for payment of 100% of the contract balance and certified that on March 14, 1983, "all prior work and the work, labor and materials to be paid for under this Request for Payment are satisfactory and in accordance with the Contract Documents."

On March 23, 1983, National Church moved its first subsidized tenants into the Project, which achieved full occupancy on May 20, 1983. Also on March 23, HUD, McCarthy, and Mackey met at the Project and executed FHA Form No. 2485, "Permission to Occupy--Project Mortgages," which had been executed by National Church on March 16.

On March 25, 1983, HUD advised McCarthy that HUD's Final Inspection Report for the Project was not completed at either the March 15 or March 23 meetings.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Johnson Controls, Inc. v. City of Cedar Rapids, Iowa
713 F.2d 370 (Eighth Circuit, 1983)
McCarthy Bros. Const. Co. v. Pierce
626 F. Supp. 981 (E.D. Missouri, 1986)
Juengel Const. Co., Inc. v. Mt. Etna, Inc.
622 S.W.2d 510 (Missouri Court of Appeals, 1981)
Twin River Construction Co. v. Public Water District No. 6
653 S.W.2d 682 (Missouri Court of Appeals, 1983)
Lile v. Hancock Place School District
701 S.W.2d 500 (Missouri Court of Appeals, 1985)
Massman Construction Co. v. Lake Lotawana Ass'n
210 S.W.2d 398 (Missouri Court of Appeals, 1948)
Fullington v. Ozark Poultry Supply Co.
39 S.W.2d 789 (Supreme Court of Missouri, 1931)
Modern American Mortgage Corp. v. Skyline Park
614 F.2d 1009 (Fifth Circuit, 1980)
McCarthy Bros. Construction Co. v. Pierce
832 F.2d 463 (Eighth Circuit, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
832 F.2d 463, 1987 U.S. App. LEXIS 14108, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mccarthy-brothers-construction-company-v-pierce-ca8-1987.