Johnson Controls, Inc. v. City of Cedar Rapids, Iowa

713 F.2d 370, 1983 U.S. App. LEXIS 25261
CourtCourt of Appeals for the Eighth Circuit
DecidedAugust 2, 1983
Docket82-1412
StatusPublished
Cited by64 cases

This text of 713 F.2d 370 (Johnson Controls, Inc. v. City of Cedar Rapids, Iowa) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Johnson Controls, Inc. v. City of Cedar Rapids, Iowa, 713 F.2d 370, 1983 U.S. App. LEXIS 25261 (8th Cir. 1983).

Opinion

McMILLIAN, Circuit Judge.

The City of Cedar Rapids (the City) appeals from a final order entered in the District Court 1 for the Northern District of Iowa compelling the City to arbitrate a claim for cost over-runs submitted by Johnson Controls, Inc. (Johnson) pursuant to Johnson’s contract with the City. For reversal the City argues (1) that the district court misconstrued its contract with Johnson by finding that this dispute was subject to the contract’s mandatory arbitration clause and (2) that the tenth amendment to the United States Constitution precludes the court from ordering the City to arbitrate this dispute in contravention of Iowa state law. We affirm the order of the district court for the following reasons.

I. Background Facts

The City and Johnson entered into a construction contract in which Johnson agreed to provide the instrumentation and the computer for the City’s federally funded Water Pollution Control Facility. During Johnson’s phase of the project’s construction, a dispute between Johnson and the City arose over the amount of compensation that Johnson was entitled to for “additional” work. On September 4, 1981, Johnson *373 submitted an “equitable adjustment” claim to the City for damages and cost over-runs of about $1.2 million. The original total contract price for Johnson’s services was just over $2 million. The City denied Johnson’s claim on November 4, 1981. Nine days later Johnson filed a demand for arbitration of the dispute under the terms of the contract’s “mandatory” arbitration clause. The “mandatory” arbitration clause provides that if one party demands arbitration of a particular dispute governed by the clause, then the other party must submit to arbitration. The City rejected Johnson’s demand for arbitration on December 2, 1981, by claiming that the contract’s “voluntary” arbitration clause superseded the mandatory arbitration clause. Under the contract’s “voluntary” arbitration clause, a dispute can be arbitrated only if both parties agree to arbitrate that dispute. Thus, because the City did not wish to arbitrate the issue of additional compensation, arbitration could not be had under the terms of the contract. In response, Johnson filed this suit to compel arbitration based upon diversity jurisdiction, 28 U.S.C. § 1332 (1976), and the federal Arbitration Act, 9 U.S.C. § 4 (1976). The district court rejected the City’s tenth amendment challenge to forced arbitration and ruled that the mandatory arbitration clause governed this particular dispute. Johnson Controls, Inc. v. City of Cedar Rapids, No. C 81-140, slip op. at 3-6 (N.D.Iowa Mar. 26, 1982). The district court therefore ordered the City to arbitrate the cost over-run. This appeal ensued.

II. Contract Construction Under the Arbitration Act

When a party to an interstate contract invokes the Arbitration Act to enforce a putative arbitration clause within that contract, the court’s review is limited to two issues: (1) whether an express written agreement to arbitrate the subject matter of the present dispute exists between the parties, and (2) if so, whether the agreement to arbitrate has been breached. National R.R. Passenger Corp. v. Missouri Pacific R.R., 501 F.2d 423, 427 (8th Cir.1974). In addressing each issue, the court must apply federal substantive law, although applicable non-discriminatory state law may provide a helpful reference in formulating the federal rule of decision. Moses H. Cone Memorial Hospital v. Mercury Construction Corp.,-U.S.-, 103 S.Ct. 927, 941, 74 L.Ed.2d 765 (1983). See United States v. Kimbell Foods, Inc., 440 U.S. 715, 728-29, 99 S.Ct. 1448, 1458-59, 59 L.Ed.2d 711 (1979) (relying on state law to give content to the federal rule of decision). The court must also be guided by “the liberal federal policy favoring arbitration” in contracts governed by the Arbitration Act. Moses H. Cone Memorial Hospital, 103 S.Ct. at 941. Thus, any doubts about the construction or breach of the putative arbitration provision are to be resolved in favor of ordering arbitration. Id.; National R.R. Passenger Corp., 501 F.2d at 428. The parties stipulated to the facts relevant to the construction of the contract. There is no disagreement that the City is refusing to arbitrate under the contract. Thus, the only pertinent issue in this case is whether the City and Johnson entered into a unilaterally enforceable agreement to arbitrate this particular dispute. To resolve this issue, we need to decide what effect is to be given each of the two seemingly contradictory arbitration clauses.

The actual structure of a written document is often helpful in construing its contents. The present contract is divided into two main parts: the General Conditions, and the Supplemental Conditions. The mandatory arbitration clause is contained in § 30.1 of the General Conditions [hereinafter cited as General § 30.1]. It provides:

30 ARBITRATION
30.1 All claims, disputes and other matters in question arising out of, or relating to, the CONTRACT DOCUMENTS or the breach thereof ... shall be decided by arbitration .... This agreement to arbitrate shall be specifically enforceable under the prevailing arbitration law. - The award rendered by the arbitrators shall be final, and judgment *374 may be entered upon it in any court having jurisdiction thereof.

The voluntary arbitration clause is contained in § 7 of the Supplemental Conditions [hereinafter cited as Supplemental § 7]. It provides:

7. Remedies
Except as otherwise provided in this contract, all claims, counterclaims, disputes and other matters in question between the Owner and the Contractor arising out of or relating to this agreement or breach thereof will be decided by arbitration if the parties hereto mutually agree, or in a court of competent jurisdiction within the State in which the Owner is located.

Also of importance is § 1 of the Supplemental Conditions, which states that the provisions contained in the Supplemental Conditions “shall supersede any conflicting provisions of this contract.”

The City advances four main arguments relating to the construction of the contract. The City’s first argument is that the mandatory arbitration clause and the voluntary arbitration clause are “conflicting” and, therefore, under Supplemental § 1 the voluntary arbitration clause controls because it is contained in the Supplemental Conditions. As a corollary to this argument, the City asserts that the voluntary arbitration clause is more specific than the mandatory arbitration clause and under Iowa law the more specific clause will control a general clause.

This argument has superficial appeal.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Acosta v. Allen
W.D. Kentucky, 2022
meyer v. Merjanian
W.D. Missouri, 2021
Gosiger, Inc. v. Elliott Aviation, Inc.
823 F.3d 497 (Eighth Circuit, 2016)
Powell v. Yarbrough (In re Yarbrough)
540 B.R. 647 (E.D. Arkansas, 2015)
United States v. Hacker
565 F.3d 522 (Eighth Circuit, 2009)
United States v. Scott Hacker
Eighth Circuit, 2009
Cedar Rapids Television Co. v. MCC IOWA LLC
524 F. Supp. 2d 1127 (N.D. Iowa, 2007)
Husinga v. Federal-Mogul Ignition Co.
519 F. Supp. 2d 929 (S.D. Iowa, 2007)
Estate of Pearson v. Interstate Power & Light Co.
700 N.W.2d 333 (Supreme Court of Iowa, 2005)
Ex Parte Mountain Heating and Cooling, Inc.
867 So. 2d 1112 (Supreme Court of Alabama, 2003)
Cybertek, Inc. v. Bentley Systems, Inc.
182 F. Supp. 2d 864 (D. Nebraska, 2002)
Owen v. MBPXL CORP.
173 F. Supp. 2d 905 (N.D. Iowa, 2001)
Groover v. Michelin North America, Inc.
90 F. Supp. 2d 1236 (M.D. Alabama, 2000)
DeJong v. City of Sioux Center
980 F. Supp. 1010 (N.D. Iowa, 1997)
Kent P. Barker v. Ceridian Corp.
122 F.3d 628 (Eighth Circuit, 1997)
Barker v. Ceridian Corporation
122 F.3d 628 (Eighth Circuit, 1997)
Hoffman v. Cargill, Inc.
968 F. Supp. 465 (N.D. Iowa, 1997)
Buhler, Inc. v. Reuter Recycling of Florida, Inc.
889 F. Supp. 1126 (D. Minnesota, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
713 F.2d 370, 1983 U.S. App. LEXIS 25261, Counsel Stack Legal Research, https://law.counselstack.com/opinion/johnson-controls-inc-v-city-of-cedar-rapids-iowa-ca8-1983.