Merrill Stevens Dry Dock Co. v. M/V Yeocomico II and YII Shipping Company, Ltd.

329 F.3d 809, 2003 A.M.C. 1228, 2003 U.S. App. LEXIS 8266, 2003 WL 1983543
CourtCourt of Appeals for the Eleventh Circuit
DecidedApril 30, 2003
Docket01-15127
StatusPublished
Cited by23 cases

This text of 329 F.3d 809 (Merrill Stevens Dry Dock Co. v. M/V Yeocomico II and YII Shipping Company, Ltd.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eleventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Merrill Stevens Dry Dock Co. v. M/V Yeocomico II and YII Shipping Company, Ltd., 329 F.3d 809, 2003 A.M.C. 1228, 2003 U.S. App. LEXIS 8266, 2003 WL 1983543 (11th Cir. 2003).

Opinion

*811 GOLDBERG, Judge:

Merrill Stevens Dry Dock (“Merrill Stevens”) appeals the district court’s Order Re: Pending Motions (August 1, 2001) (hereinafter “Findings II ”), which reversed, in part, the district court’s F000indings of Fact and Conclusions of Law (December 6, 2000) (hereinafter “Findings I ”). At issue is a Work Order and Ship Repair Contract (the “Contract”) between Merrill Stevens and YII Shipping Company (‘Til Shipping”) for repairs to the M/V YEOCOMICO II (the “Ship”). The district court found that Paragraphs 5 and 6 of the Contract were ambiguous. Thus, the terms of the Contract were interpreted against Merrill Stevens, the drafter.

Merrill Stevens also appeals the Findings I award of $55,441.49 to YII Shipping for fire damage to the Ship caused by Merrill Stevens. Merrill Stevens also appeals the award of $64,865.92 in damages for loss of use of the Ship while the fire damage was repaired.

YII Shipping cross-appeals, arguing that the district court erred by not awarding YII Shipping lost profits of $843,939.00. Second, YII Shipping contests the district court’s award to Merrill Stevens of prejudgment interest of 18 percent under the Contract’s terms.

For the reasons that follow, we reverse the district court and find that Paragraphs 5 and 6 of the Contract are not ambiguous; affirm the district court’s award of damages to YII Shipping for the fire damage to the Ship; affirm the award for loss of use of the Ship during the Ship’s fire damage repairs; affirm the district court’s denial of damages to YII Shipping for future lost profits; and affirm the district court’s determination to award Merrill Stevens pre-judgment interest of 18 percent.

I. BACKGROUND.

YII Shipping, a Bahamian cargo shipping company, contracted with Merrill Stevens for repairs of its Ship, M/V YEO-COMICO II. The Ship traveled between Port Dania, Florida and various ports in the Bahamas. The repairs were necessary in order to bring the Ship into compliance with United States Coast Guard Regulations, without which the Ship could not enter the United States. YII Shipping, by and through its president Lisbon Higgs, retained the services of Roy MacKeen of Bahamas Marine International, Inc. Higgs instructed MacKeen to “do what it takes” to bring the Ship into compliance with the Coast Guard’s regulations.

Some time after Merrill Stevens began repair work on the Ship, MacKeen signed the Contract, which listed the repair work to be done. On the reverse side, the Contract contained the exculpatory clauses, Paragraphs 5 and 6, that are at issue in this case. 1 The exculpatory clauses state the following:

Paragraph 5. CONTRACTOR undertakes to perform the Servicing and haul and launch of the vessel, provide ber-thage, wharfage, towage, and other services and facilities only upon condition that it shall not be liable, directly or *812 indirectly, in tort or contract except as expressly warranted, or otherwise to OWNER, the vessel, its charterers, underwriters, or any of their agents, servants or employees, or persons to whom they may be responsible, for any personal injury, death, or damage to the vessel, its cargo, equipment or movable stores, or for any consequences thereof, unless such personal injury, death or property damage, etc. is caused by CONTRACTOR’S negligence, which negligence shall not be presumed but must be affirmatively established. In no event, including the negligence and/or gross negligence and/or breach of contract, including express warranties, of CONTRACTOR, shall CONTRACTOR’S aggregate liability to all such parties in interest for personal injury, death, or damage sustained by them, or any other type of damage exceed the sum of $1,000,000, and in no event shall CONTRACTOR be liable to any extent to the vessel, OWNER, charterers and/or underwriters, for the cost of defending any claims asserted by third parties, including attorney’s fees, whether such actions shall be commenced by its employees or others. No claim for damages for negligence or otherwise shall be valid unless such claim is presented to CONTRACTOR within sixty (60) days after delivery of the vessel or completion of the Servicing, whichever first occurs. All limitations on CONTRACTOR’S liability which are contained in this Work Order shall remain in full force and effect following delivery of the vessel to OWNER.
Paragraph 6. In no event shall CONTRACTOR be liable to any person for incidental or consequential damages, for any breach of contract or for any negligence on the part of CONTRACTOR which might have given rise thereto.

Some time after the Contract was signed and the repair work commenced, a fire was caused by two Merrill Stevens workers while they were performing welding work. The fire damaged the Ship’s accommodation houses. In its Findings I, the district court determined that the fire was a proximate result of Merrill Stevens’ negligence. As a result of the fire an additional eight weeks to repair the damage to the accommodation houses was necessary. 2 During the period of repair for the fire damage the Ship was out of service. While out of service, YII Shipping claimed that it had lost certain shipping routes to competitors that it could not reclaim when the repairs were completed.

Merrill Stevens commenced this action on June 5, 1998, claiming that YII Shipping failed to pay the balance for the repair work, and sued for prejudgment interest of 18 percent, as provided by the Contract. They also claimed that Paragraphs 5 and 6 of the Contract precluded YII Shipping’s recovery for incidental or consequential damages. YII Shipping claimed that the Contract’s terms were void since Merrill Stevens breached the Contract by negligently setting fire to the Ship. Additionally, YII Shipping claimed that Paragraphs 5 and 6 of the Contract were ambiguous and, thus, unenforceable. Therefore, YII Shipping counter-sued for the fire damage to the Ship, lost profits sustained while the Ship underwent an additional eight weeks of repair, and lost *813 profits sustained after the Ship returned to service.

In its Findings I, the district court found that the fire was caused by Merrill Stevens’ negligence and as a proximate result of the fire, the Ship had to undergo an additional eight weeks of repair for the damaged accommodation houses. Finding Paragraphs 5 and 6 unambiguous, the district court awarded YII Shipping $55,441.49 in damages for the fire damage, and $64,865.92 in damages resulting from the loss of use of the Ship during the eight weeks of repairs.

The district court denied YII Shipping’s claim for lost profits after the Ship returned to service for failure to prove the lost profits to a “reasonable certainty.” Merrill Stevens was awarded prejudgment interest of 18 percent, as specified by the contract. Both parties moved for reconsideration and amendment.

Upon reconsideration, the district court issued its Findings II, which reversed, in part, its Findings I by finding Paragraphs 5 and 6 of the Contract ambiguous.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re: Freedom Unlimited
S.D. Florida, 2020
William Christopher Lewis v. United States
618 F. App'x 483 (Eleventh Circuit, 2015)
Perry Brown v. J.C. Penney Corporation, Inc.
521 F. App'x 922 (Eleventh Circuit, 2013)
Joel W. Green, North Florida Shipyard, Inc vs USA
418 F. App'x 862 (Eleventh Circuit, 2011)
Carmichael v. Kellogg, Brown & Root Services, Inc.
572 F.3d 1271 (Eleventh Circuit, 2009)
United States v. Joey K. Lansing
263 F. App'x 849 (Eleventh Circuit, 2008)
In Re New River Shipyard, Inc.
355 B.R. 894 (S.D. Florida, 2006)
United States v. Marissa Giselle Massey
443 F.3d 814 (Eleventh Circuit, 2006)
RDP Royal Palm Hotel, L.P. v. Clark Construction Group, Inc.
168 F. App'x 348 (Eleventh Circuit, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
329 F.3d 809, 2003 A.M.C. 1228, 2003 U.S. App. LEXIS 8266, 2003 WL 1983543, Counsel Stack Legal Research, https://law.counselstack.com/opinion/merrill-stevens-dry-dock-co-v-mv-yeocomico-ii-and-yii-shipping-company-ca11-2003.