Internaves de Mexico S.A. de C v. v. Andromeda Steamship Corporation

CourtCourt of Appeals for the Eleventh Circuit
DecidedAugust 1, 2018
Docket17-12164
StatusPublished

This text of Internaves de Mexico S.A. de C v. v. Andromeda Steamship Corporation (Internaves de Mexico S.A. de C v. v. Andromeda Steamship Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eleventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Internaves de Mexico S.A. de C v. v. Andromeda Steamship Corporation, (11th Cir. 2018).

Opinion

Case: 17-12164 Date Filed: 08/01/2018 Page: 1 of 20

[PUBLISH]

IN THE UNITED STATES COURT OF APPEALS

FOR THE ELEVENTH CIRCUIT ________________________

No. 17-12164 ________________________

D.C. Docket No. 9:16-cv-81719-DMM

INTERNAVES DE MEXICO S.A. DE C.V.,

Plaintiff - Appellee,

versus

ANDROMEDA STEAMSHIP CORPORATION, AMERICAN NAVIGATION, INC., PEGASUS LINES, LTD. S.A., PANAMA, JAMES KARATHANOS,

Defendants - Appellants.

________________________

Appeal from the United States District Court for the Southern District of Florida ________________________

(August 1, 2018)

Before MARCUS, FAY, and HULL, Circuit Judges.

MARCUS, Circuit Judge: Case: 17-12164 Date Filed: 08/01/2018 Page: 2 of 20

This case arises out of a battle over where the parties have agreed to arbitrate

this admiralty and maritime dispute. Andromeda Steamship Corporation and

Internaves de Mexico s.a. de C.V. entered into a shipping contract (the “Contract”)

whereby Andromeda agreed to furnish Internaves with a vessel to transport an

electric transformer from Brazil to Mexico. Internaves claimed that Andromeda

failed to tender the vessel on the agreed-upon date, while Andromeda countered

that Internaves never delivered the transformer to the vessel. The Contract

unambiguously required the parties to submit their dispute to arbitration. However,

the Contract contained conflicting provisions regarding where the parties agreed to

arbitrate. The district court could not ascertain the site of arbitration from the

agreement itself and, therefore, resorted to the statutory default forum, compelling

arbitration in its own district -- the Southern District of Florida.

Andromeda appealed, arguing that the district court had erred in proclaiming

the Contract hopelessly ambiguous as to the selection of a forum. Had the court

waded through the Contract’s interpretive tangles, Andromeda says, it would have

discovered the parties’ mutually agreed-upon intent to arbitrate in London, where it

claims the arbitration must be held. Internaves suggests, however, that due to the

Contract’s murkiness, the district court properly ordered arbitration in Miami.

The Contract hardly represents a model of clarity. Nevertheless, we agree

with Andromeda and discern from the document an agreement to arbitrate in

2 Case: 17-12164 Date Filed: 08/01/2018 Page: 3 of 20

London. Accordingly, we reverse the judgment of the district court and remand

with instructions to compel arbitration in London under English law.

I.

A.

Andromeda and Internaves entered into the Contract, a charter party

agreement, in June 2016. A “charter party” is simply a contractual arrangement

whereby a ship owner agrees to lend a ship to a charterer for the transportation of

goods from one port to another. See Hawkspere Shipping Co. v. Intamex, S.A., 330

F.3d 225, 228 (4th Cir. 2003); see also Soumyadipta Chanda, A Comparison of

Rights and Liabilities Under a Charter Party and a Bill of Lading, 24 U.S.F. Mar.

L.J. 65, 67–68 (2011).

The Contract is divided into two parts. Part I contains terms specific to the

parties’ particular transaction. Part II includes general boilerplate terms that are

typically incorporated into shipping contracts of this kind. Part I includes Box 25,

labeled “Law and Arbitration.” Box 25 instructs, “[S]tate 19(a), 19(b) or 19(c) of

Cl[ause] 19; if 19(c) agreed also state Place of Arbitration (if not filled in 19(a)

shall apply).” Clause 19, in turn, also labeled “Law and Arbitration,” appears in

Part II of the agreement. Clause 19 is divided into sub-clauses 19(a) through 19(d).

Affixed to each sub-clause is an asterisk, and the asterisk notation reads, “(a), (b)

and (c) are alternatives; indicate alternative agreed in Box 25.” Clause 19(a)

3 Case: 17-12164 Date Filed: 08/01/2018 Page: 4 of 20

provides for arbitration in London under English law and imposes additional terms,

including a scheme for appointing arbitrators. Clause 19(b) calls for arbitration in

New York under U.S. law and prescribes similar supplemental conditions. Clause

19(c) reads this way: “Any dispute arising out of this Charter Party shall be

referred to arbitration at the Place indicated in Box 25, subject to the procedures

applicable there. The laws of the place indicated in Box 25 shall govern this

Charter Party.” Finally, 19(d) explains that if Box 25 is not filled in, then 19(a)

governs. In sum, Clause 19 of the Contract, located in Part II, provides a list of

forum alternatives and instructs the parties to indicate their selection among those

alternatives in Box 25. Box 25, located in Part I, also directs the parties to write

their selection among Clause 19’s options within that space.

Inside Box 25, the parties clearly wrote these words: “London arbitration,

English Law.” However, in Clause 19, the parties crossed out 19(a), 19(c), and

19(d), leaving only 19(b) -- New York arbitration under U.S. law -- unstruck.

Thus, while the parties wrote in the words “London arbitration, English Law” in

Box 25 in Part I, they signaled some desire to arbitrate in New York under U.S.

law in Part II. Finally, above the signature page, the Contract reads, “It is mutually

agreed that this Contract shall be performed subject to the conditions contained in

this Charter Party which shall include PART I as well as PART II. In the event of a

4 Case: 17-12164 Date Filed: 08/01/2018 Page: 5 of 20

conflict of conditions, the provisions of Part I shall prevail over those of Part II to

the extent of such conflict” (the “Conflict Clause”) (emphasis added).

B.

In October 2016, Internaves sued Andromeda in the Southern District of

Florida for breach of contract, conversion, and fraud. Internaves claimed that,

although it prepaid Andromeda, Andromeda failed to tender the vessel on the

agreed-upon date, in violation of the Contract. Andromeda moved to compel

arbitration of the dispute in London under English law pursuant to the selection the

parties made in Part I, Box 25. The district court granted Andromeda’s motion in

part, compelling arbitration, but concluded that it could not ascertain from the

terms of the agreement where the parties had agreed to arbitrate the dispute. The

court observed that, because Part I stipulated “London arbitration, English Law,”

while Part II indicated a contrary agreement to arbitrate any dispute arising from

the Contract in New York under U.S. law, the Parts were hopelessly in conflict.

The court continued this way: “This conflict is compounded by ambiguities in the

very provisions ostensibly designed to resolve internal inconsistencies.”

Elaborating, the court recognized that, under the Conflict Clause, in the event of

conflict, Part I superseded Part II. However, the court also observed that 19(c),

“which also provide[d] for the supremacy of Part I,” was crossed out. In light of

that puzzle, the district court could not determine whether the Conflict Clause

5 Case: 17-12164 Date Filed: 08/01/2018 Page: 6 of 20

remained applicable to the instant dispute. Accordingly, it held that the parties had

failed to provide for a specific arbitral forum and, therefore, it could compel

arbitration only within its own district pursuant to 9 U.S.C. § 4.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rose v. M/V "GULF STREAM FALCON"
186 F.3d 1345 (Eleventh Circuit, 1999)
Wright Ex Rel. Wright v. Hanna Steel Corp.
270 F.3d 1336 (Eleventh Circuit, 2001)
Access Now, Inc. v. Southwest Airlines Co.
385 F.3d 1324 (Eleventh Circuit, 2004)
Mastrobuono v. Shearson Lehman Hutton, Inc.
514 U.S. 52 (Supreme Court, 1995)
Orient Mid-East Lines, Inc. v. Shipment of Rice
496 F.2d 1032 (Fifth Circuit, 1974)
Larry Bonner v. City of Prichard, Alabama
661 F.2d 1206 (Eleventh Circuit, 1981)
Lindo v. NCL (Bahamas), Ltd.
652 F.3d 1257 (Eleventh Circuit, 2011)
Ishwar Jain v. Henri Courier De Mere
51 F.3d 686 (Seventh Circuit, 1995)
United States v. Adrian Pielago, Maria Varona
135 F.3d 703 (Eleventh Circuit, 1998)
Alan I. Begner, Cory Begner v. United States
428 F.3d 998 (Eleventh Circuit, 2005)
Interface Kanner, LLC v. JP Morgan CHase Bank, N.A.
704 F.3d 927 (Eleventh Circuit, 2013)
American Express Co. v. Italian Colors Restaurant
133 S. Ct. 2304 (Supreme Court, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
Internaves de Mexico S.A. de C v. v. Andromeda Steamship Corporation, Counsel Stack Legal Research, https://law.counselstack.com/opinion/internaves-de-mexico-sa-de-c-v-v-andromeda-steamship-corporation-ca11-2018.