Clayton Center Associates, a Missouri Limited Partnership by the Centor Company, Its General Partner v. Schindler Haughton Elevator Corporation

731 F.2d 536, 1984 U.S. App. LEXIS 23951, 15 Fed. R. Serv. 1246
CourtCourt of Appeals for the Eighth Circuit
DecidedApril 2, 1984
Docket83-1055
StatusPublished
Cited by3 cases

This text of 731 F.2d 536 (Clayton Center Associates, a Missouri Limited Partnership by the Centor Company, Its General Partner v. Schindler Haughton Elevator Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Clayton Center Associates, a Missouri Limited Partnership by the Centor Company, Its General Partner v. Schindler Haughton Elevator Corporation, 731 F.2d 536, 1984 U.S. App. LEXIS 23951, 15 Fed. R. Serv. 1246 (8th Cir. 1984).

Opinion

HEANEY, Circuit Judge.

Clayton Center Associates (Clayton Center) sued Schindler Haughton Elevator Corporation (Schindler) for breach of a contract to maintain the elevators in the Chro-malloy Plaza Building, which Clayton Center owns. After eight days of trial, the district court granted a directed verdict for the defendant, ruling that Clayton Center’s proof of damage was too speculative to submit to the jury. We hold that the district court erred in so ruling.

BACKGROUND

Clayton Center Associates is a partnership which owns the Chromalloy Plaza Building in Clayton, Missouri. 1 Ever since 1973, when the building opened, Schindler had maintained the elevators in the building under what is called a “turn key maintenance contract.” This contract provided that in exchange for a monthly fee (starting at $1,591 and subject to escalation based on the consumer price index), Schindler would maintain the elevator system, repairing and replacing major components as necessary. The contract provided that this arrangement would continue for a period of thirteen years.

In 1979 and 1980, Clayton Center experienced numerous problems with its elevators. Doors were opening and closing spontaneously and the elevator cars would stop without warning, would not go to the proper floors, and would fail to level properly. Tenants in the building complained of the elevator service on numerous occasions. Clayton Center became concerned about losing tenants as a result of the elevator problems. In the fall of 1980, Clayton Center’s building managers met with Schindler on two occasions to advise it of the continuing problems, and to request a prompt solution. After suggesting that they might have no other option than to terminate the contract, Clayton Center finally did so on December 5, 1980.

Clayton Center then hired Miller Elevator Company (Miller) to fix and service its elevators. Miller performed its work for Clayton Center initially on a time and mate *539 rials fee basis. This arrangement suited Clayton Center, because it was at that point hesitant to enter into another long term maintenance contract. The fee arrangement suited Miller, which was hesitant to perform the necessary repairs for a fixed fee.

Before commencing the repairs, a Miller worker observed from a preliminary inspection that the elevator system’s generators were dirty, the commutators were scored, brushes were too short, controllers were dirty, elevator car lights were burned out, door sills were excessively worn, car doors were flopping and not meeting properly, speeds were wrong, and the electric eyes were not working. Miller commenced its work in early December, 1980. Its employees worked on the elevators full-time.

In January, 1981, Miller notified Clayton Center that repair of the system would take longer than initially expected. Miller recommended that Clayton Center confirm its assessment of the elevators and estimate of the work remaining through an independent consultant — Lerch Bates of Denver, Colorado. Clayton Center agreed with this suggestion, and in early February, 1981, contacted that company. Eric Pankey, Regional Engineer with Lerch Bates, examined and tested the elevator system on February 9-10, 1981. He conferred with Lee Glaser, Miller’s supervisor of the work at the Chromalloy Plaza. Pan-key identified a long list of unsatisfactory conditions in the elevator system attributable to neglected maintenance. In his report to Clayton Center, Pankey stated that Glaser and the other Miller employees could perform the necessary repairs. He also recommended that Clayton Center enter into a maintenance contract with Miller.

Miller continued to work on the elevator system, and finally rendered it in good working order in July, 1981. One of the continuing problems had been that Schindler had used the wrong solvent on the system’s contact relays, which control the motion of the elevator cars and doors. Each elevator has several hundred contact relays. Miller had repeatedly attempted to clean them, but finally concluded that they could not be successfully cleaned and would have to be replaced.

Lerch Bates performed a follow-up inspection in June, 1981, and confirmed that the system was substantially repaired. Lerch Bates also suggested a format for a long-term maintenance contract, and this served as the basis for a contract Clayton Center entered into with Miller in July, 1981. Miller’s total bill to Clayton Center for the work performed from December, 1980, to July, 1981, came to some $208,000.

Clayton Center brought suit against Schindler to recover for the cost of repairing its elevator system. Schindler counterclaimed for the profits it lost due to the early termination of the contract. A jury trial began on November 29, 1982, and on December 10,1982, the district court granted a directed verdict for defendant at the close of Clayton Center’s case in chief. The court ruled that there was “no evidence before the jury to substantiate plaintiff’s measure of damages.” It bifurcated and deferred Schindler’s counterclaim pursuant to Fed.R.Civ.P. 42(b). Clayton Center then brought this appeal.

ANALYSIS

Clayton Center argues on appeal that it offered evidence of damage sufficient to enable the jury to fix an amount with reasonable certainty but that the trial court erroneously excluded this evidence. 2 It is clear from the transcript that plaintiff had a great degree of difficulty in presenting its case. Throughout the eight days of trial, plaintiff’s questions prompted continuous objections by defendant’s attorney, going primarily to the form of the questions, occasionally to lack of foundation, but frequently without a stated ground for the objection. These objections were nearly always sustained by the trial court. Consequently, plaintiff’s counsel ended up *540 making repeated offers of proof, with the jury being excused from the courtroom each time.

The case is in federal court by virtue of diversity jurisdiction; the parties agree the case is governed by Missouri law. In Missouri, upon proving the existence of a contract and its breach, a party has made a submissible case and may at least recover nominal damages. Sunny Baer Co. v. Slaten, 623 S.W.2d 595, 598 (Mo.App.1981). Clayton Center certainly submitted evidence sufficient to raise a jury question as to the existence and breach of the instant turn key maintenance contract. Moreover, we think it clear that the district court granted Schindler’s motion for a directed verdict only because it found the evidence of actual damages too speculative. We disagree with this finding. Based on admitted and proffered evidence, Clayton Center should have at least survived the directed verdict motion requested by Schindler, and been able to submit its case to the jury.

As with any contract case, the goal in awarding damages is to give the injured party the benefit of its bargain, that is, to place it in the position it would have enjoyed had the contract been fully performed. Sunny Baer Co. v. Slaten, supra, 623 S.W.2d at 597.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
731 F.2d 536, 1984 U.S. App. LEXIS 23951, 15 Fed. R. Serv. 1246, Counsel Stack Legal Research, https://law.counselstack.com/opinion/clayton-center-associates-a-missouri-limited-partnership-by-the-centor-ca8-1984.