Hensic v. Afshari Enterprises, Inc.

599 S.W.2d 522, 1980 Mo. App. LEXIS 2542
CourtMissouri Court of Appeals
DecidedMay 13, 1980
Docket40653
StatusPublished
Cited by37 cases

This text of 599 S.W.2d 522 (Hensic v. Afshari Enterprises, Inc.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hensic v. Afshari Enterprises, Inc., 599 S.W.2d 522, 1980 Mo. App. LEXIS 2542 (Mo. Ct. App. 1980).

Opinion

SATZ, Judge.

Defendant, Afshari Enterprises, Inc., d/b/a Missouri Real Estate Company and Missouri Construction Company (Afshari), contracted to build a house for plaintiffs, George Hensic and Jeanette Hensic (Hen-sics). In a three count petition, the Hensics sued Afshari for breach of contract, breach of implied warranty and misrepresentation based upon alleged defects in construction. At the close of the Hensics’ case, the trial court directed verdicts against the Hensics on the warranty and misrepresentation counts. The cause was submitted on breach of contract and the jury awarded the Hen-sics $25,000.00 as damages. Afshari appeals. We affirm.

By written contract entered into in July, 1973, Afshari agreed to construct a five-bedroom, two-car, custom house, according to specifications, and agreed to sell the house to the Hensics for $51,950.00. In December, 1973, the Hensics occupied the house. During their early occupancy, the Hensics requested Afshari to correct some defects and it did so. However, at final disbursement, the Hensics notified the mortgage lender that the house was not completed to their satisfaction because certain items of construction were not completed. The Hensics did not sign a certificate of completion and brought suit against Afshari.

The cause was tried in March, 1978. At trial, an architect, hired by the Hensics to inspect the house, testified that he found 31 deficiencies in construction. Without objection, an appraiser hired by the Hensics testified that, if the house had been constructed in a workmanlike manner, the land and the house would have been worth $71,600.00 in July, 1973. According to him, the loss in value in 1973 due to the construction defects would have been $16,700.00. He also testified that, if the house were constructed in a workmanlike manner in December, 1977, the value of the house and land, at that time, would have been $92,100.00, while its value as actually constructed would have been $69,800.00, reflecting a loss in value of $22,300.00. A general contractor also testified on behalf of the Hen-sics. He inspected the house in February, 1976. Over Afshari’s objections to any testimony about the cost of repairs, he testified that, at the time of his inspection, the cost of repairs of the 31 noted deficiencies, including overhead and profit, would be $33,716.65, or $27,061.65 if one defect were fixed by an alternative method of construction. In addition, he testified, at the time of trial, these costs would have increased by *524 15 percent to 20 percent. 1 George Hensic testified about the loss of use and enjoyment of his property due to the alleged defects.

The Hensies submitted M.A.I. 4.01 as the proper damage instruction, which was refused by the trial court. Instead, at Af-shari’s request, the court gave a modified M.A.I. 4.02, which measured the Hensies’ damage by the difference in the fair market value of the house as promised and as constructed. 2

Afshari raises four points on appeal, all of which are centered on the issue of damages. Afshari contends that the trial court erred by (1) permitting the Hensies’ contractor to testify about the cost of repairs; (2) permitting the Hensies’ counsel to argue that the proper measure of damages in this case was the cost of repairs; (3) “entering an excessive judgment”, based upon “improperly” admitted evidence of the cost of repairs and upon an “improper” argument of the Hensies’ counsel that the cost of repairs was the correct measure of damages; and (4) permitting the Hensies’ counsel to incorrectly state, in his closing argument, the unsupported fact that Joseph Af-shari, Afshari’s president, signed a building permit application listing the construction costs as some $16,000.00 less than the contract price.

In our review, we take the trial record as it stands and so must Afshari’s present counsel on appeal. We address only those issues properly preserved for review, and we find none of Afshari’s assertions of error were preserved for our review.

As noted, Afshari first contends that the evidence of the cost of repairs was improperly admitted. This issue was not raised in Afshari’s motion for a new trial, and, thus, is not preserved for review. Rule 78.07; Ramacciotti v. Zinn, 550 S.W.2d 217, 223 (Mo.App.1977); Cato v. Modglin, 545 S.W.2d 307, 309 (Mo.App.1976). Moreover, had Afshari preserved this issue, it still would not have prevailed. When a building contractor breaches his contract by defective performance, as Afshari allegedly did here, two methods are commonly used to measure the resulting damages. 3 One method, called “cost of repair” is, as its name implies, the cost of repairing the defective work. 5 Corbin, Contracts, § 1089 (1964); Restatement of Contracts, § 346(l)(a) (1932). The second method, called “diminution in value”, is the difference between the value of the building as promised and its value as actually constructed. See Kahn v. Prahl, 414 S.W.2d 269, 282-283 (Mo.1967); Hotchner v. Liebowits, 341 S.W.2d 319, 332 (Mo.App.1960). The particular facts of each case determine which measure of damages is to be used. Kahn v. Prahl, supra; Hotchner v. Liebowits, supra; accord, Forsythe v. Starnes, 554 S.W.2d 100, 109 (Mo.App.1977); and see M.A.I. 4.02, Committee’s Comment. 4 Thus, *525 it was proper for the Hensics to elicit testimony both as to the cost of repairs and as to the diminution in value of the property in question. Delong v. Broadston, 272 S.W.2d 493, 497 (Mo.App.1954); compare, DeArmon v. City of St. Louis, 525 S.W.2d 795, 800-801 (Mo.App.1975). Defendant’s appropriate remedy may have been to request a withdrawal instruction on the evidence related to the cost of repairs. Beaty v. N. W. Electric Power Cooperative, Inc., 296 S.W.2d 921, 925 (Mo.App.1956). We rule against Afshari on this point.

Afshari next contends the Hen-sics’ counsel misstated the law in his closing argument by urging that the proper measure of damages in this case was the cost of repairs. No objection was made to this statement during closing argument, and this issue was not raised in Afshari’s motion for a new trial. Thus, this point has not been preserved for review. Vaeth v. Gegg, 486 S.W.2d 625, 631 (Mo.1972); Coffel v. Spradley, 495 S.W.2d 735, 740 (Mo.App.1973).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Matt Miller Co. v. Taylor-Martin Holdings, LLC
393 S.W.3d 68 (Missouri Court of Appeals, 2012)
Riddell v. Bell
262 S.W.3d 301 (Missouri Court of Appeals, 2008)
St. Louis, LLC v. FINAL TOUCH
899 A.2d 1018 (New Jersey Superior Court App Division, 2006)
Porter v. Toys 'R' US-Delaware, Inc.
152 S.W.3d 310 (Missouri Court of Appeals, 2004)
Ince v. Money's Building & Development, Inc.
135 S.W.3d 475 (Missouri Court of Appeals, 2004)
Morgan Publications, Inc. v. Squire Publishers, Inc.
26 S.W.3d 164 (Missouri Court of Appeals, 2000)
Guess v. Escobar
26 S.W.3d 235 (Missouri Court of Appeals, 2000)
McLane v. Wal-Mart Stores, Inc.
10 S.W.3d 602 (Missouri Court of Appeals, 2000)
Coats v. Hickman
11 S.W.3d 798 (Missouri Court of Appeals, 1999)
Williams v. Jacobs
972 S.W.2d 334 (Missouri Court of Appeals, 1998)
McConnell v. Stallings
955 S.W.2d 590 (Missouri Court of Appeals, 1997)
Business Men's Assurance Co. of America v. Graham
891 S.W.2d 438 (Missouri Court of Appeals, 1994)
Elfrink v. Burlington Northern Railroad
845 S.W.2d 607 (Missouri Court of Appeals, 1992)
McCutcheon v. Cape Mobile Home Mart, Inc.
796 S.W.2d 901 (Missouri Court of Appeals, 1990)
Pathway Financial v. Schade
793 S.W.2d 464 (Missouri Court of Appeals, 1990)
Williams v. Hubbard
789 S.W.2d 810 (Missouri Court of Appeals, 1990)
Westerhold v. Mullenix Corp.
777 S.W.2d 257 (Missouri Court of Appeals, 1989)
Hernandez v. Westoak Realty & Investment, Inc.
771 S.W.2d 876 (Missouri Court of Appeals, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
599 S.W.2d 522, 1980 Mo. App. LEXIS 2542, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hensic-v-afshari-enterprises-inc-moctapp-1980.