Samuels v. Illinois Fire Insurance Company

354 S.W.2d 352
Missouri Court of Appeals·Decided February 5, 1962·No. 23364·Published·Cited by 18 cases

Opinions

[354] CROSS, Judge.

Plaintiffs, husband and wife, sue defendant insurance company to recover damages for breach of its duty to complete repairs on their dwelling house which was damaged by fire. Defendant appeals from a judgment entered on a jury verdict awarding plaintiffs damages in the sum of $7,667.00.

On December 9, 1955, defendant issued a fire insurance policy in the amount of $5000.00 on plaintiffs’ four room bungalow for a term of five years. On April 8, 1959, and while the policy was in force, the house was partially destroyed by a fire. Plaintiffs duly notified defendant of the fire and entered into negotiations with defendant for payment of their loss.

At the request of defendant, plaintiffs furnished two estimates of the cost of repairs, amounting to $4,475.00 and $4,485.50, respectively. Defendant secured a contractor’s bid in the amount of $1719.00 and an additional estimate in the sum of $1838.00, and informed plaintiffs it would not pay more than the first named amount for the repairs. Plaintiffs were also informed that they would have to employ the contractor. Plaintiffs refused the offer and the negotiations ended.

On April 24, 1959, plaintiffs gave defendant notice in writing to repair the building in accordance with the provisions of Section 379.150, V.A.M.S., which reads as follows:

“Whenever there is a partial destruction or damage to property covered by insurance, it shall be the duty of the party writing the policies to pay the assured a sum of money equal to the . damage done to the property, or repair the same to the extent of such damage, not exceeding the amount written in the policy, so that said property shall be in as good condition as before the fire, at the option of the insured”.

Defendant thereafter employed B. E. Baer, a contractor, to repair the house at a cost of $3143.00. Baer took over the property and began the repairs during the week of July 21, 1959, but discontinued after working a few days, and abandoned the property. No further repairs were ever made.

Plaintiffs filed this suit on August 4, 1959. In their amended petition they allege that defendant was not diligent in repairing the house; that with reasonable diligence the repairs could have been completed by June 24, 1959, and at a cost not to exceed $5000.-00; that defendant, after employing its contractor to do the work in July, 1959, stopped the repairs after a few days and refused to proceed further with them; that defendant abandoned and left the house open and without protection from the weather, permitting the entry of snow and rain; that the action of those elements, during the long delay that ensued without completion of the repairs, caused the repairable portion of the house which survived the fire to become weakened, deteriorated, irreparable, and unfit for use and beyond repair, and made it necessary to tear down and remove the remaining portion of the house and to build a new structure. Plaintiffs claim damages amounting to the cost of tearing down and rebuilding the house, and their loss of its rental value.

The principal issue of fact in this case is whether it was possible to repair the damaged structure as it stood at the time of trial, so that it would be in as good condition as before the fire. Defendant so contends — plaintiffs to the contrary. Plaintiffs claim it was not possible to use any of the damaged building (except the foundation, sewer and excavation), but that it was necessary to tear down and rebuild the standing portion in order to restore it to as good condition as it was in before the fire.

The house is of frame structure, with stucco exterior, containing three rooms on the first floor and a fully finished bedroom with a large closet on the second floor. It has a full basement which contains a sleeping room, a full bathroom, a hot water tank and .a furnace. The first and second floor walls are lath and plaster. The roof is cov[355] ered with asphalt shingles. The house has two porches, front and rear. A witness for plaintiffs estimated the age of the house at 20 years. Defendant’s witness estimated the house to be from 35 to 40 years old. It was agreed between the parties that the house was rented for $50.00 per month, at the time of the fire. For the previous nine years it had been leased and occupied by the same tenants.

The fire caused considerable damage to the millwork, walls and decorations in the three rooms on the first floor and in the second floor room. All the wood trim around the windows and doors was burned, and the floors and stairway to the second floor were scorched and blistered. The fire burned through the lath in many places on the walls. One exterior wall had a hole burned through it to the outside. All the windows were broken out. There were large holes in the ceilings of the first floor. The ceiling of the front porch was blistered and burned. The outside doors were burned and the guttering was destroyed. The outside stucco surface of the house was damaged and discolored by smoke.

It was plaintiffs’ testimony that soon after the fire they cleaned up the debris and boarded up the windows and doors, but that shortly after August 1,1959, they discovered that the boards had been removed and that all the windows in the house were open except those opening onto the porches, that some new window frames had been made and installed, but that the work had been abandoned. It appears that the house remained open and exposed to the weather until the date of trial, October 24, 1960.

Free access — add to your briefcase to read the full text and ask questions with AI

Samuels v. Illinois Fire Insurance Company, 354 S.W.2d 352 (Mo. Ct. App. 1962).

354 S.W.2d 352 (Samuels v. Illinois Fire Insurance Company) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Portell v. Farm Bureau Town & Country Insurance Co. of Missouri
888 S.W.2d 728 (Missouri Court of Appeals, 1994)
Stege v. Hoffman
822 S.W.2d 517 (Missouri Court of Appeals, 1991)
Perkins v. Schicker
641 S.W.2d 432 (Missouri Court of Appeals, 1982)
Hensic v. Afshari Enterprises, Inc.
599 S.W.2d 522 (Missouri Court of Appeals, 1980)
Continental Bank & Trust Co. v. American Bonding Co.
605 F.2d 1049 (Eighth Circuit, 1979)
McKinley v. Vize
563 S.W.2d 505 (Missouri Court of Appeals, 1978)
Forsythe v. Starnes
554 S.W.2d 100 (Missouri Court of Appeals, 1977)
F. C. Preuitt Construction Co. v. Doty
536 S.W.2d 908 (Missouri Court of Appeals, 1976)
North County School District R-1 v. Fidelity & Deposit Co. of Maryland
539 S.W.2d 469 (Missouri Court of Appeals, 1976)
Barber v. M. F. A. Milling Co.
536 S.W.2d 208 (Missouri Court of Appeals, 1976)
Dunning v. Alfred H. Mayer Company
483 S.W.2d 423 (Missouri Court of Appeals, 1972)
Daniels v. Smith
471 S.W.2d 508 (Missouri Court of Appeals, 1971)
Edmonds v. Stratton
457 S.W.2d 228 (Missouri Court of Appeals, 1970)
Jurgeson v. Romine
442 S.W.2d 176 (Missouri Court of Appeals, 1969)
Parker v. Wallace
431 S.W.2d 136 (Supreme Court of Missouri, 1968)
Hay v. Ham
364 S.W.2d 118 (Missouri Court of Appeals, 1962)