F. C. Preuitt Construction Co. v. Doty

536 S.W.2d 908, 1976 Mo. App. LEXIS 1971
CourtMissouri Court of Appeals
DecidedMay 3, 1976
DocketNo. KCD 27341
StatusPublished
Cited by9 cases

This text of 536 S.W.2d 908 (F. C. Preuitt Construction Co. v. Doty) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
F. C. Preuitt Construction Co. v. Doty, 536 S.W.2d 908, 1976 Mo. App. LEXIS 1971 (Mo. Ct. App. 1976).

Opinion

SWOFFORD, Judge.

This is an action for damages based upon an alleged breach of an oral contract. The respondent (hereafter Preuitt) was the general contractor for the construction of an addition to the Ervin Junior High School, Raytown, Missouri, and the oral contract sued upon covered certain excavation, grading and other earth work to be done by the appellants (hereafter Overland) as subcontractor on said construction. Overland filed a counterclaim seeking the sum of $4,242.58 for work based upon quantum meruit which it was alleged had been done on the job but not paid by Preuitt. A jury was waived and the evidence was presented to the court below sitting as the trier of facts. That court made extensive findings of fact and conclusions of law, and entered judgment in favor of Preuitt in the amount of $4,757.67 on its petition, and denied Overland any recovery on the counterclaim. After an unsuccessful motion to amend judgment, Overland appealed to this court.

Overland raises two assignments of error. The first of these (in summary) is that the court erred in failing to sustain Overland’s motion for directed verdict (sic) because: A) Overland’s objection to and motion to strike the evidence of Preuitt as to Overland’s specific contractual obligations, as a subcontractor, under the prime written construction contract between Preuitt and the school district, should have been sustained since such prime contract was not in evidence nor was any other substantive and admissible evidence offered by Preuitt to establish any obligation of Overland to perform such specific excavation services; and B) there was no proof that the charges paid by Preuitt to others to complete the originally required excavation work were reasonable, and thus there was a failure of proof as to monetary damages.

Overland’s second assignment of error (in summary) is that the court erred in denying Overland recovery on the counterclaim based upon work done but not paid for; that quantum meruit was pleaded, proved and conceded, and Overland was entitled to a judgment for $4,242.58 on the counterclaim.

Since this is an appeal of a court-tried case, the review is upon “both the law and the evidence as in suits of an equitable nature”; due regard must be given to the opportunity of the trial court to judge the credibility of the witnesses; and, the findings and judgment of the court below will not be disturbed if supported by substantial and credible evidence. Rule 73.01.

The transcript of evidence, record and exhibits entered below, and the authorities and legal arguments of counsel, have been carefully reviewed and independent legal research made. It is concluded that the judgment below be affirmed.

A summary of the facts necessary to the resolution of this appeal is as follows:

In 1965, Preuitt was a general contractor engaged primarily in the construction of commercial buildings and schools. It had constructed the original Ervin Junior High School in Raytown, Missouri and the first addition thereto, prior to 1965, as general contractor. In each of those jobs Overland had done the excavation and dirt work as a subcontractor at a fixed price, and not upon the basis of an hourly charge for machinery and equipment.

On February 4,1965, Preuitt was the low bidder on a second addition to be constructed to the school and was awarded the general contract at a fixed price of approximately $1.5 million dollars.

Prior to submitting its bid on the second addition to Ervin school, Preuitt arrived at its bid by preparing a “bid estimate sheet” which separated the various classifications of work to be performed on the job, some of which was to be performed by Preuitt and the remainder to be subcontracted by Preuitt to others. For the work to be per[911]*911formed by subcontractors, Preuitt requested them to submit to it their bids in accordance with the plans and specifications at a fixed price. Preuitt then used the low bid on each category to figure the overall total bid price to be submitted.

Knowing of Overland’s familiarity with the job site, location and nature of the work, sometime prior to February 4, 1965 Preuitt requested Overland, by telephone, to bid on the site grading and excavation work on the Ervin second addition, according to the plans and specifications. On February 4, 1965, Overland advised Preuitt over the telephone that it bid $18,412.00 on a base bid, $987.00 for additional work covered in Alternate # 6, and $510.00 for additional work covered in Alternate # 7, a total bid of $19,909.00 for the dirt work. Mr. Preuitt testified that it was a custom and practice in this area to solicit and receive bids from subcontractors to use in figuring a general contractor’s bid on the prime contract, by telephone. It has been Overland’s position throughout that any work undertaken or done on this job was not a fixed price contract but rather upon an hourly charge.

Preuitt used the Overland figures and incorporated them in its bid. On February 4,1965, when Preuitt was awarded the contract, Mr. Preuitt advised Overland over the telephone of this fact and that its bid for the dirt work was accepted. On February 16, 1965, Mr. Preuitt wrote Overland a letter, which his secretary testified was mailed to Overland that day. In pertinent part, this letter states:

“This is your authorization to proceed with items of dirt work on the Ervin Junior High School, as per your telephoned quotation of February 4, 1965, all according to plans and specifications prepared by Hollis & Miller, Architect.
The Board accepted alternates 6 and 7 which add to your base bid of $18,412.00, the sum of $1497.00 (alt. # 6 $987.00 & alt. # 7 $510.00) making a contract price of $19,909.00 to you.
⅝ * ⅝ # sfc
Have your insurance carrier send a Certificate of Insurance to me showing you are covered on this job for the amounts stated in the specifications.
* 9k *

Overland made no objections to the terms of this letter and provided Preuitt with the Certificate of Insurance as requested. However, Doty, the operating partner, of Overland, testified his company had never been notified that it had been awarded a specific dollar contract and had no recollection of the work covered by Alternates 6 and 7. He stated that he had no knowledge of the letter until discovery proceedings after suit.

The job did not proceed immediately because of weather conditions. In March or April, 1965, Mr. Doty was called by the Superintendent on the job and requested to move the site dirt and the footings on the building. On April 8,1965, Overland moved men and machines onto the job, and according to Mr. Preuitt, worked thereafter until the latter part of May or early June, when it left the job site. Mr. Preuitt testified that Doty stated that he had to leave for “three or four days” to “finish another job” but that “he would be right back”. Doty testified that Overland worked the job from about April 8, 1965 through June 23, 1965. The work was further delayed by a cyclone and some difficulty with a high pressure line. Doty stated that on June 23,1965, the job was a “great, big general mess” and “bogged down” and so “we left the job”. Some of the Overland work had been completed, but a substantial amount remained to be done.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Erney v. Freeman
84 S.W.3d 529 (Missouri Court of Appeals, 2002)
Asbury v. Crawford Electric Cooperative, Inc.
51 S.W.3d 152 (Missouri Court of Appeals, 2001)
State v. Jordan
751 S.W.2d 68 (Missouri Court of Appeals, 1988)
Sassenrath v. Sassenrath
750 S.W.2d 95 (Missouri Court of Appeals, 1988)
Lewis v. Bucyrus-Erie, Inc.
622 S.W.2d 920 (Supreme Court of Missouri, 1981)
State v. Cameron
604 S.W.2d 653 (Missouri Court of Appeals, 1980)
State v. MacKe
594 S.W.2d 300 (Missouri Court of Appeals, 1980)
State v. Barber
587 S.W.2d 325 (Missouri Court of Appeals, 1979)
Vaughan v. Singleton
584 S.W.2d 186 (Missouri Court of Appeals, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
536 S.W.2d 908, 1976 Mo. App. LEXIS 1971, Counsel Stack Legal Research, https://law.counselstack.com/opinion/f-c-preuitt-construction-co-v-doty-moctapp-1976.