Erney v. Freeman

84 S.W.3d 529, 2002 Mo. App. LEXIS 1908, 2002 WL 31085944
CourtMissouri Court of Appeals
DecidedSeptember 19, 2002
Docket24610
StatusPublished
Cited by9 cases

This text of 84 S.W.3d 529 (Erney v. Freeman) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Erney v. Freeman, 84 S.W.3d 529, 2002 Mo. App. LEXIS 1908, 2002 WL 31085944 (Mo. Ct. App. 2002).

Opinion

JAMES K. PREWITT, Presiding Judge.

Warren and Linda Erney, as owners, and Phillip Freeman, as contractor, entered into a contract to finish the basement in the Erneys’ house. The Erneys contended that Freeman breached the contract by exercising poor workmanship, including the improper installation of insulation and portions of the electrical system. Freeman filed a counterclaim, alleging that the Erneys breached the contract by refusing to allow him to complete the work. Following non-jury trial, judgment was entered in favor of Freeman on the Erneys’ breach of contract claim and in favor of the Erneys on Freeman’s counterclaim. The Erneys appeal. 1

Under appellate review of a non-jury case, the trial court’s judgment is affirmed unless there is no substantial evidence to support it, it is against the weight of the evidence, or unless it erroneously declares or applies the law. Schaefer v. Rivers, 965 S.W.2d 954, 956 (Mo.App.1998). We presume that the trial court’s judgment is valid; it is the Erneys’ burden, as appellants, to demonstrate any error. Id. Due deference is given to the trial court to judge the credibility of the witnesses. Id.

We consider that all fact issues upon which no findings were made were found in accordance with the result reached. Id. Therefore, the judgment will be upheld on any reasonable theory that is supported by the evidence. Id.

The Erneys and Freeman entered into a contract on December 30, 1998 to finish the basement in the Erneys’ home, to include the building of a bedroom, office area, and bathroom. The contract stipulated that “[electrical, plumbing[,] along with all phases of the job[,] will be done to federal [and] local codes.” Although the proposal submitted by Freeman for the project indicated that insulation would be installed behind all framed walls, the contract called for drywall to be hung with one-inch insulation installed around all exterior walls. The contract included an express warranty for one year after the job *532 was complete and the Erneys “are unmistakable [sic] happy with the basement.”

The final contract price was $32,872, which the Erneys’ agreed to pay in three payments, each of which equaled approximately one-third of the total. The contract provided that the first payment would be made prior to the beginning of any work, the second after the dry wall was hung, and the third “when all phases are complete [and the Erneys] are content [and] happy.” The first payment, in the amount of $10,474, was made by check on January 30, 1999. On March 5, 1999, the Erneys made the second payment to Freeman, also by check for $10,474, even though the drywall had not yet been hung.

Also in March, Freeman took bids from three licensed electricians for that portion of the project. While taking bids from the electricians, Freeman was made aware by all three that there was a problem with the existing electrical panel box because, according to the plans, it would be in the bathroom, which is prohibited by the National Electrical Code (NEC). Jack Norton, one of those three electricians, submitted a bid of $4,568 that included $800 to $1,000 to move the panel.

According to Freeman, prior to hiring the electrical subcontractor, he informed Mrs. Erney of the problem and that the approximate cost to move the existing panel would be $5,000. He claimed that she vetoed moving either the box or the bathroom because of the cost. The Erneys denied that Freeman ever discussed the situation with them. Neither Norton nor the other licensed electricians who submitted bids, and informed Freeman of the problem, were hired as the electrical subcontractor. Rather, Freeman’s brother did the electrical work, which not only included keeping the existing panel in the bathroom, but also installing a sub-panel there. Freeman paid him $1,675 for the work.

Lane Baugh, another subcontractor hired by Freeman, began hanging sheet-rock during the first week of May. According to Baugh, he was only hired by Freeman to hang the sheetrock; Freeman was to install the insulation. Although Baugh knew it was common procedure not to hang the drywall without first insulating the walls, he began constructing the sheet-rock walls even though the only insulation was on the walls “up against the concrete.” Baugh testified that Freeman told him “not to worry about it[,]” that “there was to be no insulation” on the other walls.

Baugh encountered other problems while hanging the drywall, including studs made of low-grade lumber that were not aligned correctly or spaced the standard 16 or 18 inches apart. In addition, Baugh moved some of the electrical boxes because they were either too far in or too far out, which would cause the sheetrock to break.

Mrs. Erney approached Baugh while he was working and asked him why the insulation was not in the walls, and Baugh informed her that Freeman instructed him to hang the sheetrock without insulating first. Mrs. Erney told Baugh to cease working on the walls until she was able to speak with her son. The Erneys’ son (“Brad”) did inspect the walls at his mother’s request and he contacted Freeman, who told him that the walls were insulated. 2

According to Baugh, Freeman called him the next day to inquire about what had happened and then asked him to lie to Mrs. Erney and tell her that his comments regarding Freeman’s instructions to him *533 were incorrect. The next time Baugh saw Freeman at the house, Freeman was ripping off the sheetrock and attempting “to stick insulation down into the walls.” This was corroborated by Brad, who testified that he received a call from his mother that Freeman was taking down the sheet-rock. Apparently Mrs. Erney, who was not home at the time, but had been notified by a neighbor of Freeman’s actions, asked the neighbor to tell Freeman to leave the premises.

Over the next couple of days, Freeman paid Baugh, asked him to sign a lien waiver, and fired him as a subcontractor. Also during that time period, Brad spoke with both Freeman and Baugh. Brad was attempting to facilitate a meeting between his parents, Freeman, and Baugh to discuss the problems. During a conversation with Baugh regarding the insulation problem, Baugh mentioned that it was a violation of federal code (apparently the NEC) for the electrical panel box to be in the bathroom, which Brad testified he already knew based on earlier discussions he had with two electricians. 3

When Mr. Erney returned from out-of-town, Mrs. Erney informed him of the problems with the insulation and electrical system. On May 8, 1999, a meeting took place at the Erneys’ home. In addition to the Erneys, those present included Brad and Freeman. Freeman offered to fix the problems that were of concern to the Er-neys.

All parties agree that Mr. Erney presented Freeman with two options at the meeting. The first was to allow Freeman to stay on the project as the main contractor, but the Erneys would select the subcontractors for the electrical and drywall/insulation work. The Erneys wanted Norton and Baugh as the electrical and drywall/insulation subcontractors, respectively.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Consolidated Service Group, LLC v. Maxey
452 S.W.3d 768 (Missouri Court of Appeals, 2015)
Weitz Co. LLC v. MacKenzie House, LLC
665 F.3d 970 (Eighth Circuit, 2012)
LARRY SNYDER AND COMPANY v. Miller
648 F.3d 1156 (Tenth Circuit, 2011)
Cason v. King
327 S.W.3d 543 (Missouri Court of Appeals, 2010)
Stom v. St. Clair Corp.
153 S.W.3d 360 (Missouri Court of Appeals, 2005)
L.L. Lewis Construction, L.LC. v. Adrian
142 S.W.3d 255 (Missouri Court of Appeals, 2004)
LL LEWIS CONST., LLC v. Adrian
142 S.W.3d 255 (Missouri Court of Appeals, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
84 S.W.3d 529, 2002 Mo. App. LEXIS 1908, 2002 WL 31085944, Counsel Stack Legal Research, https://law.counselstack.com/opinion/erney-v-freeman-moctapp-2002.