DynaCon Builders v. Janowitz

892 S.W.2d 807, 1995 Mo. App. LEXIS 277, 1995 WL 57431
CourtMissouri Court of Appeals
DecidedFebruary 14, 1995
DocketNos. WD 49077, WD 49111
StatusPublished
Cited by5 cases

This text of 892 S.W.2d 807 (DynaCon Builders v. Janowitz) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
DynaCon Builders v. Janowitz, 892 S.W.2d 807, 1995 Mo. App. LEXIS 277, 1995 WL 57431 (Mo. Ct. App. 1995).

Opinion

SPINDEN, Presiding Judge.

Robert J. Janowitz and DynaCon Builders accuse each other of breaching a contract in which DynaCon Builders agreed to construct an addition to Janowitz’ house in Kansas City. Janowitz became dissatisfied ■with Dy-naCon Builders’ work and quit paying. Dy-naCon Builders sued for breach of contract. Janowitz countersued, contending that Dyna-Con Builders breached the contract by doing shoddy work.

The trial court tried the case without a jury. It issued findings of fact and conclusions of law and entered judgment for Dyna-Con Builders for $30,607 and ordered Janow-itz to pay prejudgment interest on $26,426.64 of the judgment award. The trial court took into account Janowitz’ expenditures, past and future, in repairing DynaCon Builders’ faulty work but discounted it.

In its appeal, DynaCon Builders claims that the trial court erred in allowing Janow-itz any repair costs because Janowitz had not given it an opportunity to correct the problems. We disagree and affirm this portion of the trial court’s judgment.

Janowitz cross-appeals. He claims that the trial court erred in ordering him to pay prejudgment interest on any portion of the award. He also filed a motion asking this court to sanction DynaCon Builders for filing a frivolous appeal. We agree that the trial court erred and reverse the order. We deny the motion for sanctions.

The dispute arose over DynaCon Builders’ construction of a two-story addition to Ja-nowitz’ house. DynaCon Builders estimated that the project would cost $117,240. Janow-itz contracted with DynaCon Builders on July 24, 1987, to erect the addition for cost plus 10 percent. It guaranteed that the project’s total cost would not exceed $125,000, and it provided that if the total cost were less than $125,000, the difference would “be applied toward painting and decorating of the existing home.” It provided that the $125,-000 guaranteed maximum would be increased by any changes ordered by Janowitz. It excluded “[cjosts due to the negligence of [DynaCon Builders] ..., including but not limited to the correction of defective or nonconforming Work[.]”

DynaCon Builders finished most of the project in December 1987. On November 17, 1987, Janowitz sent DynaCon Builders a letter in which he outlined his understanding of the amount he owed for the project:

The current account, according to my records, is as follows:

Remodel addition price to be
no more than: $125,000.00
Architect fees and tree trimming fees already paid: $7,500.00
Direct payment of carpet: $1,399.64
$8,899.64
Current status of account: Total cost of addition will be no more than: $116,100.36[.]

On January 6, 1988, Janowitz’ wife, Linda, sent to DynaCon Builders an invoice indicating that the “maximum balance” for the project was $116,100.36 and from that she subtracted $6689.81 in payments she and Janow-itz had made directly. The new “maximum balance,” she said, was $109,410.55.

On January 28, 1988, Janowitz paid Dyna-Con Builders $41,073.36. This, when added to his previous $7500 payment on September 20, 1987, brought the total paid to DynaCon Builders to $48,573.26.

[809]*809On April 11, 1988, DynaCon Builders sent Janowitz an itemized statement of the project’s cost in a spreadsheet format. A column labeled “Expenses or Invoice Amount” totalled $202,714.62. The items in this column also appeared in one of three columns: a column labeled “Base Contract” totalling $126,743.90; a column labeled “Additional Costs” totalling $29,245.65;1 and an unlabeled column totalling $40,482.79. For reasons not apparent to us, the three columns totalled $196,472.34 rather than $202,714.62.

On April 24,1988, he paid $50,000 to Dyna-Con Builders. This brought the total paid to $98,573.36. He complained of defective work and made no further payments. DynaCon Builders attempted repairs beginning on August 1, 1988. Its work continued through October 1988. On October 31, 1988, it billed Janowitz for an additional $10,064.60 “[f]or costs incurred from 8-1-88 to 10 — 31—88[.]” This was $3350.09 for labor and $6714.51 for interest on unpaid amounts DynaCon Builders claimed were due. The invoice explained that “[ijnterest is calculated on the outstanding balance after it is unpaid for thirty days. Interest is computed at a rate of 1-1/2% per month, (18 percent per year).”

Attached to the invoice was a statement of the account. It acknowledged payments to-talling $98,573.36 and indicated that the unpaid amounts owing were $117,936.39 in principal and $6714.51 in interest.

Janowitz became dissatisfied with Dyna-Con Builders’ repairs. After October 31, 1988, he did not ask DynaCon Builders to fix defects. Janowitz paid others $4311.21 for repairing the defects. Another firm estimated that $18,648.30 in more work was needed to correct the remaining problems.

DynaCon Builders sued Janowitz on August 25,1992, for $117,936.39 in principal. It also asked for prejudgment interest on that amount.

The case was tried to the court in a unique manner. The trial court toured the Janowitz residence to view the alleged defects. The parties then presented their factual testimony in writing. The parties presented booklets containing documents and statements in which they set forth their claim. The opposing party made written responses to each claim. The trial court received these booklets into evidence in lieu of “live” testimony concerning each party’s claims. The trial court engaged in a detailed, off-the-record discussion of each claim. From this, the trial court entered its judgment on January 14, 1994.

Sanctions for Frivolous Appeal

DynaCon Builders appealed on July 29, 1994. Janowitz responded by asking this court to sanction DynaCon Builders for filing a frivolous appeal. We now rule on the motion.

Rule 84.19 authorizes sanctions for a frivolous appeal. The purpose of sanctions is two-fold: (1) to prevent congestion of our dockets with cases lacking any merit and cause delay of cases with merit and (2) to compensate respondents for enduring a mer-itless expense. Vanschoiack v. Adkins, 854 S.W.2d 432, 435 (Mo.App.1993). An appeal is frivolous if it does not present a justiciable question and is so lacking of merit that it is obviously frivolous. Means v. Sears, Roebuck & Company, 550 S.W.2d 780, 789 (Mo.1977). It is a drastic remedy. We consider sanctions with extreme caution to avoid chilling an appeal of even slight, colorable merit. Hawthorne v. Hills, 861 S.W.2d 337, 842 (Mo.App.1993).

We do not order sanctions in this case. Although DynaCon Builders’ position on appeal is tenuous, it is not void of merit. We do not find evidence of bad faith.

DynaCon Builders’ Appeal

DynaCon Builders argues that the trial court erred in awarding damages to Janowitz for breach of contract because Janowitz did not give it an adequate opportunity to cure the alleged defects. DynaCon Builders relies primarily on Ballwin Plaza Corporation [810]*810v. H.B.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Erney v. Freeman
84 S.W.3d 529 (Missouri Court of Appeals, 2002)
Loeffler v. City of O'Fallon
71 S.W.3d 638 (Missouri Court of Appeals, 2002)
Miller v. Bakken
978 S.W.2d 518 (Missouri Court of Appeals, 1998)
Brown v. Whitaker
926 S.W.2d 1 (Missouri Court of Appeals, 1996)
Papineau v. Baier
901 S.W.2d 190 (Missouri Court of Appeals, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
892 S.W.2d 807, 1995 Mo. App. LEXIS 277, 1995 WL 57431, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dynacon-builders-v-janowitz-moctapp-1995.