Ballwin Plaza Corp. v. H. B. Deal Construction Co.

462 S.W.2d 687
CourtSupreme Court of Missouri
DecidedFebruary 8, 1971
Docket54059
StatusPublished
Cited by15 cases

This text of 462 S.W.2d 687 (Ballwin Plaza Corp. v. H. B. Deal Construction Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ballwin Plaza Corp. v. H. B. Deal Construction Co., 462 S.W.2d 687 (Mo. 1971).

Opinion

*688 ROBERT LEE CAMPBELL, Special Judge.

Plaintiff filed suit against defendant H. B. Deal Construction Co. (hereinafter referred to as defendant), who then filed a Third Party Petition against D. F. Edwards Heating Co. (hereinafter referred to as Edwards). Plaintiff did not amend its petition to seek judgment against Edwards. Defendant also filed a counterclaim against plaintiff for some moneys allegedly due under the contract. After a lengthy trial, the court entered judgment pursuant to a jury verdict in favor of defendant and against plaintiff, and against defendant on its counterclaim, and also found in favor of Edwards and against defendant on defendant’s Third Party Petition. Plaintiff filed a timely motion for new trial, alleging innumerable errors therein. The motion for new trial was overruled, and this appeal followed. Defendant did not appeal from the judgment entered in favor of Edwards and against defendant on defendant’s Third Party Petition against Edwards or from the judgment against it on its counterclaim.

We are first met with plaintiff’s “Motion to Expunge Third Party Defendant’s (Edward’s) Statement, Brief and Argument From the Record”, which we took as submitted at the time of argument of this case. Inasmuch as defendant did not file a motion for new trial or appeal from the judgment in favor of Edwards and against defendant, such judgment became final. Defendant has therefore preserved nothing for appellate review with respect to its Third Party Claim against Edwards. Edwards is thus not a party to this appeal, and plaintiff’s Motion to Expunge is sustained. We consider only the briefs of plaintiff and defendant in reaching our decision.

Plaintiff was the owner of a tract of ground on Manchester Road in St. Louis County, Missouri. On September 14, 1959, plaintiff entered into a contract with defendant to erect a shopping center on plaintiff’s real estate to be known as Ball-win Plaza Shopping Center. Defendant acted as general contractor in the construction of the Ballwin Plaza complex for plaintiff. The air-conditioning system therein was installed by Edwards. Difficulties ensued as a result of alleged inadequacies and failures of the heating and air-conditioning system to operate properly in the stores and offices located in Ballwin Plaza. As a result, plaintiff filed suit against defendant in two counts, one for breach of contract and another for breach of warranty contained within the building contract. Plaintiff abandoned Count II of its petition on breach of warranty and went to the jury on County I of its petition for breach of contract.

Despite the numerous trial errors alleged by plaintiff in its motion for new trial, only two issues are presented in plaintiff’s brief and preserved for review. They pertain to whether or not the statute of limitations is applicable to the facts in this case and, if so, whether or not defendant’s Instruction No. 5, submitting a factual issue to the jury with respect thereto, was properly worded. Inasmuch as we rule that the statute of limitations was not a bar to plaintiff’s cause of action as a matter of law, an instruction submitting that issue to the jury should not have been given. It is therefore not necessary to consider further plaintiff’s complaints pertaining to the phraseology of the instruction.

Plaintiff’s cause of action was for breach of the contract entered into between the parties on September 14, 1959, and in particular for breach of the following provision of the contract:

“It is understood that the cooling and heating capacities will be the same as specified and all work will be installed to give proper results and distribution.”

The contract of September 14, 1959, further provided that defendant “shall remedy any defects due thereto and pay for any damages to other work resulting there *689 from, which shall appear within a period of one year from date of substantial completion.” The specifications, incorporated in the contract by reference, also provided that the heating and air-conditioning subcontractor (Edwards) “shall guarantee all workmanship and materials furnished by him for a period of one year from the date of final acceptance of installation”.

Instruction No. 5, given by the court at defendant’s request, instructed the jury that the verdict must be for defendant whether or not the contract was breached if they believed that prior to September 9, 1961, defendant had completed all of the stores then requested to be done by plaintiff and that plaintiff and defendant had concluded the contract sued upon prior to said date. Plaintiff’s suit was filed against defendant on September 9, 1966. Edwards completed installation of the heating and air-conditioning units by March 1961, and tenants were moving into the shopping center at approximately the same time as the completion of the air-conditioning work by Edwards. On May 26, 1961, defendant delivered to plaintiff all of the remaining keys to the stores in the shopping center which defendant had in its possession. At plaintiff’s request, defendant sent plaintiff a final bill dated June 27, 1961. On August 10, 1961, plaintiff made payment to defendant on the final billing. Various miscellaneous items with respect to the billing and payment remained in dispute at that time, although the major portion of defendant’s billings had been paid by plaintiff.

On September 28, 1961, Deal wrote a letter to plaintiff, as follows: “In accordance with the drawings and specifications for the work performed in connection with the construction with the Ballwin Plaza Shopping Center, located at Ballwin, St. Louis County, Missouri, we hereby guarantee to remedy any defects due to faulty materials or workmanship which may appear within a period of one (1) year from date of May 1, 1961”.

The parties agree that the five-year statute of limitations set forth in § 516.120, RSMo., 1969, V.A.M.S., is the applicable limitations statute. This section does apply to a suit for breach of a written contract. Sam Kraus Company v. State Highway Commission, Mo., 416 S.W.2d 639. The time when a cause of action accrues for the purpose of the statute of limitations is governed by § 516.100, which provides, “the cause of action shall not be deemed to accrue when the wrong is done or the technical breach of contract or duty occurs, but when the damage resulting therefrom is sustained and is capable of ascertainment, and, if more than one item of damage, then the last item, so that all resulting damage may be recovered, and full and complete relief obtained”.

Suit was filed September 9, 1966. Plaintiff advances three separate dates as the earliest at which its cause of action accrued and the statute of limitations began to run, September 29, 1961, (the date of final payment by plaintiff to defendant); May 1, 1962, (the last date when defendant was obligated under the contract to correct defects appearing in workmanship and materials) ; or the Spring of 1963 (the time when defendant and Edwards refused to do anything further to correct any defects in the air-conditioning system).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Smock v. Associated Elec. Coop., Inc.
567 S.W.3d 211 (Missouri Court of Appeals, 2018)
Loeffler v. City of O'Fallon
71 S.W.3d 638 (Missouri Court of Appeals, 2002)
Miller v. Bakken
978 S.W.2d 518 (Missouri Court of Appeals, 1998)
DynaCon Builders v. Janowitz
892 S.W.2d 807 (Missouri Court of Appeals, 1995)
Hodges v. Hodges
692 S.W.2d 361 (Missouri Court of Appeals, 1985)
Lato v. Concord Homes, Inc.
659 S.W.2d 593 (Missouri Court of Appeals, 1983)
Arst v. Max Barken, Inc.
655 S.W.2d 845 (Missouri Court of Appeals, 1983)
Davis v. Laclede Gas Co.
603 S.W.2d 554 (Supreme Court of Missouri, 1980)
Moore v. City of Pacific
534 S.W.2d 486 (Missouri Court of Appeals, 1976)
Neal v. Laclede Gas Company
517 S.W.2d 716 (Missouri Court of Appeals, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
462 S.W.2d 687, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ballwin-plaza-corp-v-h-b-deal-construction-co-mo-1971.