Smock v. Associated Elec. Coop., Inc.

567 S.W.3d 211
CourtMissouri Court of Appeals
DecidedNovember 13, 2018
DocketWD 81326
StatusPublished
Cited by6 cases

This text of 567 S.W.3d 211 (Smock v. Associated Elec. Coop., Inc.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Smock v. Associated Elec. Coop., Inc., 567 S.W.3d 211 (Mo. Ct. App. 2018).

Opinion

Karen King Mitchell, Chief Judge

Robert C. Smock, as trustee of the Robert C. Smock Revocable Living Trust; T & K Smock, LLC; and Joshua and Jessie Smock (collectively, the Smocks) appeal an order granting summary judgment to Associated Electric Cooperative, Inc. (Cooperative) on the grounds that the Smocks' claims are time-barred. The Smocks argue that the motion court erred in granting summary judgment because their claims fall within the continuing-wrong exception to accrual of the limitations periods. If applicable, the exception would allow the Smocks to recover for damage occurring during the limitations period immediately preceding the filing of their petition. The Smocks further argue that the motion court erred in granting summary judgment on their contract claim because it accrued when Cooperative refused payment *215and, thus, was timely filed. Because we find that the Smocks' claims are barred by the applicable statutes of limitations, we affirm the motion court's grant of summary judgment on all counts.

Background1

On December 20, 1990, William and Jeanette Smock granted Cooperative a 150-foot-wide electric-transmission-line easement over a portion of their farm in Holt County, Missouri.2 Under the easement agreement, William and Jeanette, as Grantors, granted Cooperative

a perpetual easement right, privilege and authority to enter upon the lands of the Grantor to construct, reconstruct, erect, add to, rebuild, modify, level, repair, replace, patrol, operate and maintain on, over and under the described lands, ... an electric transmission line of one or more circuits, including, but not limited to, poles, towers, wires, buried cable, guys, brace poles, guy wires, anchors and other appurtenances necessary thereto....

Other pertinent provisions of the easement agreement include the following:

Grantor does also hereby grant, bargain, sell and convey to Cooperative the perpetual right to clear and keep clear by cutting, trimming, spraying or removing by any other manner all brush, trees and timber within seventy-five (75) feet of the centerline of said electric transmission line and all other trees which, in the opinion of the Cooperative, would endanger or be a hazard to the operation and maintenance of the lines.
The sole consideration to be paid by Cooperative to Grantor for the rights and privileges herein granted shall be thirteen thousand two hundred thirty dollars ($13,230.00 ) to be paid within ninety (90) days from the execution of this instrument. No construction on this easement shall be commenced until said amount is paid.
Cooperative agrees to pay additional to Grantor the actual damages to Grantor's real property, growing annual crops and fences when and if such damage occurs, occasioned by the exercise of any of the rights granted herein, it being understood that this agreement for further payment is not intended to and shall not provide additional payment for the cutting and trimming of trees, nor for the exercise of any of the rights of the easement itself, which rights are granted for the sole consideration specified in the paragraphs set forth above.

(Emphasis in original.)3

After the easement was executed, Jeanette granted Cooperative's contractor access to the area covered by the easement agreement to begin the clearing process, which was completed by early 1992. Robert observed the clearing of several large oak trees from the pasture area and of "many more" trees from the area closer to the Nodaway River, which borders the *216Smocks' farm to the east. The contractor cleared only those trees that were within the easement's boundaries.

A portion of the easement covers a slope of ground on the Smock farm leading down to the river. Over time, the root systems of the cleared trees deteriorated, and without roots to hold the soil in place, the land in that area of the easement destabilized and began sliding into the river. By or before the spring of 2005, the Smocks became aware of damaging erosion of the slope within the easement boundaries as is evidenced by the fact that they moved the part of their livestock fence that was on the easement back from the river to prevent the fence from collapsing. Robert testified that he thinks "it was 2005 ... where [he] started to really see the damage start." Later he clarified that it was "probably spring" of 2005. Both Travis and Joshua testified that erosion of the slope became an issue for the family in 2005.4 Travis believed that the livestock fence had been moved back from the river even before 2005.5 Robert had to replace the fence three times, moving the fence line back roughly twenty feet each time. Eventually, the Smocks decided to exit the livestock business; in 2015, they began planting crops in this portion of their farm, including within the easement boundaries along the Nodaway River.

Robert and Joshua testified that the rate of erosion accelerated in 2012. Sometime in the last five years, the erosion extended beyond the boundaries of Cooperative's easement. And the eroded area continues to grow, encroaching on additional tillable farmland.

In 2014, Robert demanded that Cooperative address the erosion pursuant to the easement, but Cooperative declined, concluding that its clearing activities were not the cause of the erosion.

The Smocks filed their initial Petition on September 11, 2015,6 and later filed a First Amended Petition that included four counts: (1) breach of contract, (2) negligence, (3) trespass and violation of § 537.340,7 and (4) temporary nuisance and inverse condemnation. Cooperative moved for summary judgment on all claims.8 The court heard arguments on Cooperative's motion and, on December 12, 2017, issued an "Order Granting Summary Judgment" on all counts.9 This appeal follows.

*217Standard of Review

Whether the circuit court properly entered summary judgment "is purely an issue of law which th[e c]ourt reviews de novo. " Hill v. Ford Motor Co. , 277 S.W.3d 659, 664 (Mo. banc 2009) (citing ITT Commercial Fin. Corp. v. Mid-Am. Marine Supply Corp. , 854 S.W.2d 371, 376 (Mo. banc 1993) ). Under the de novo standard of review, appellate courts use the same decision criteria as the lower courts. Id. Thus, we will affirm summary judgment if there is no genuine dispute as to any material fact and the moving parties are entitled to judgment as a matter of law. Rule 74.04(c)(6);10 ITT Commercial Fin. Corp.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
567 S.W.3d 211, Counsel Stack Legal Research, https://law.counselstack.com/opinion/smock-v-associated-elec-coop-inc-moctapp-2018.