Ken Cucchi Construction, Inc. v. O'Keefe

973 S.W.2d 520, 1998 Mo. App. LEXIS 1374, 1998 WL 567957
CourtMissouri Court of Appeals
DecidedJuly 14, 1998
Docket72465
StatusPublished
Cited by48 cases

This text of 973 S.W.2d 520 (Ken Cucchi Construction, Inc. v. O'Keefe) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ken Cucchi Construction, Inc. v. O'Keefe, 973 S.W.2d 520, 1998 Mo. App. LEXIS 1374, 1998 WL 567957 (Mo. Ct. App. 1998).

Opinion

AHRENS, Presiding Judge.

I. Facts

Plaintiff, Cucchi Construction, filed a five-count petition against defendants, Jerry and Bernice O’Keefe, arising out of the defendants’ refusal to pay plaintiff the balance on a contract for the construction of the defendants’ house. Defendants filed a counterclaim, alleging that plaintiff breached its obligations under the contract. The trial court *523 entered judgment in favor of defendants on both plaintiffs claim and their counter-claim and ordered plaintiff to pay defendants $5,155.19. Plaintiff appeals from the trial court’s judgment. We affirm in part, and reverse in part and remand.

Viewing the record in the light most favorable to the trial court’s judgment, the following evidence was adduced at trial. A fire destroyed defendants’ home in September 1993. In late November 1993 plaintiff agreed to rebuild defendants’ home in exchange for $105,000. The contract specified that the defendants would pay plaintiff $35,-000 at the inception of construction, $35,000 after plaintiff put on the roof, $30,000 after plaintiff completed construction and $5,000 after plaintiff completed a “walk-thru”.

Defendants timely made the first two installment payments of $35,000. Plaintiff then sent defendants an invoice in September 1994 after it had completed construction of the residence. In this invoice, plaintiff credited defendants’ account in the amount of $10,472 for their purchase of materials from subcontractors that plaintiff was responsible for. Also, plaintiff charged defendants $3,911.23 for additional work that plaintiff alleged the defendants had ordered. Thus, plaintiff’s invoice showed that defendants owed plaintiff a balance of $28,439.23 on the contract.

The defendants refused to pay any additional amount above the $70,000 they had already paid, asserting that the quality of plaintiffs work was unacceptable and that plaintiff had not conducted the walk-thru. Plaintiff, in response to defendants’ refusal to pay the balance due on the contract, filed a five-count petition against defendants in Jefferson County Circuit Court. Plaintiff contended in Count I that the defendants breached the contract by failing to pay the remaining balance on the contract. In Counts II and III plaintiff asserted that it was entitled to the balance on the contract under either a promissory estoppel or quantum meruit theory. Plaintiff asserted in Counts IV and V that it was entitled to either a mechanic’s lien or an equitable lien on defendants’ property to secure payment of the debt. Plaintiff also requested that the court order defendants to pay its attorney’s fees, a service charge and interest.

Defendants filed a counter-claim against plaintiff, asserting that plaintiff breached the contract by failing to perform its work in a workmanlike manner and that plaintiff failed to provide for some of the materials required in the contract. In a bench-tried case, the trial court entered judgment against plaintiff on all five of its counts and in favor of defendants on their counter-claim.

In calculating defendants’ damages, the trial court began with the assumption that plaintiff was entitled to the $105,000 contract price. The trial court then ■ deducted the $70,000 the defendants had already remitted to plaintiff. The trial court also subtracted a $6,200 payment the defendants’ insurance company paid to plaintiff for debris removal prior to the beginning of construction. The trial court further deducted $5,000 off the contract price because plaintiff had not conducted the walk-thru as required by the contract. These subtractions left a balance of $23,800 on the contract price.

The trial court then credited defendants for the cost of replacing plaintiffs defective workmanship and the amount of money defendants spent on purchasing materials that plaintiff was required to purchase under the contract. The trial court found defendants’ cost to repair or replace plaintiffs defective workmanship was $15,450. The trial court also determined that the defendants purchased materials in the amount of $13,-505.19 that plaintiff was required to provide. Accordingly, the trial court calculated defendants’ damages to be $28,955.19. Subtracting these damages from the balance remaining on the contract price, the trial court ruled that the defendants were entitled to $5,155.19. The trial court denied plaintiffs motion for a new trial. This appeal follows.

II. Analysis

In a court-tried case, we will affirm the trial court’s judgment unless there is no substantial evidence to support it, unless it is against the weight of the evidence or unless it erroneously declares or applies the law. Murphy v. Carron, 536 S.W.2d 30, 32 (Mo. *524 banc 1976). Further, in determining whether there is sufficient evidence to support the trial court’s judgment, we will review the evidence in the light most favorable to the judgment. Mason v. Mason, 873 S.W.2d 631, 633-34 (Mo.App.1994). Also, the trial court, as the trier of fact, determines the credibility of witnesses and may believe or disbelieve all or a part of any witnesses’ testimony. Rule 73.01(c)(2); Gee v. Payne, 939 S.W.2d 383, 388 (Mo.App.1997).

A. Plaintiff’s Substantial Performance

Plaintiff asserts sixteen points of error on appeal. However, many of plaintiffs points are derivative of one another and can be reduced to four assertions of error. Plaintiff first asserts that the trial court erred in finding that it breached the contract with defendants. Plaintiff argues that although there may have been slight defects in its work, it did substantially comply with its contractual obligations. Even if a contractor does not strictly comply with its obligations under the contract, it may recover on the contract if it substantially complied with its requirements. Daugherty v. Bruce Realty & Development, Inc., 892 S.W.2d 332, 335 (Mo.App.1995). When a contractor has substantially complied with its obligations under the contract, it is entitled to recover the contract price minus the sums necessary to correct any defects. Sides Construction Co. v. Arcadia Valley R-II School Dist., 565 S.W.2d 761, 772 (Mo.App.1978).

Here, the trial court found that plaintiff did not substantially perform its obligations under the contract and therefore could not recover on its breach of contract claim. However, the trial court then proceeded to calculate defendants’ damages from the perspective that plaintiff was entitled to the $105,000 contract price. Thus, the manner in which the trial court calculated defendants’ damages was identical to the manner it would have calculated these damages if it had found that plaintiff substantially complied with its contractual obligations. 1

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Perficient, Inc. v. Munley
E.D. Missouri, 2023
Clark v. Kinsey
558 S.W.3d 573 (Missouri Court of Appeals, 2018)
Ordower v. NRT Missouri, LLC
528 S.W.3d 463 (Missouri Court of Appeals, 2017)
Frontenac Bank v. GB Investments, LLC
528 S.W.3d 381 (Missouri Court of Appeals, 2017)
Kansas City Live Block 139 Retail, LLC v. Fran's K.C. Ltd.
504 S.W.3d 725 (Missouri Court of Appeals, 2016)
AB Realty One, LLC v. Miken Technologies, Inc.
466 S.W.3d 722 (Missouri Court of Appeals, 2015)
Richard Brown v. Susan Brown-Thill
437 S.W.3d 344 (Missouri Court of Appeals, 2014)
Desu v. Lewis
427 S.W.3d 843 (Missouri Court of Appeals, 2014)
Kelley v. Widener Concrete Construction, LLC
401 S.W.3d 531 (Missouri Court of Appeals, 2013)
Smith v. Davenport (In re Davenport)
491 B.R. 911 (W.D. Missouri, 2013)
Matt Miller Co. v. Taylor-Martin Holdings, LLC
393 S.W.3d 68 (Missouri Court of Appeals, 2012)
Comens v. SSM St. Charles Clinic Medical Group, Inc.
335 S.W.3d 76 (Missouri Court of Appeals, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
973 S.W.2d 520, 1998 Mo. App. LEXIS 1374, 1998 WL 567957, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ken-cucchi-construction-inc-v-okeefe-moctapp-1998.