Robinson v. Powers

777 S.W.2d 675, 1989 Mo. App. LEXIS 1423, 1989 WL 116686
CourtMissouri Court of Appeals
DecidedOctober 5, 1989
Docket15849
StatusPublished
Cited by14 cases

This text of 777 S.W.2d 675 (Robinson v. Powers) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Robinson v. Powers, 777 S.W.2d 675, 1989 Mo. App. LEXIS 1423, 1989 WL 116686 (Mo. Ct. App. 1989).

Opinion

HOGAN, Judge.

Plaintiffs Dennis and Dale Robinson, excavating contractors, brought this action in three counts against defendant Rick Powers, a general contractor, and Freeman Hospital of Joplin. The action was based on a construction contract by the terms of which Rick Powers (whom we shall refer to as the defendant) undertook to build an office center for the Freeman Hospital according to drawings and specifications prepared by Joplin architects. A blueprint of the site plan indicates, if our calculations are correct, that the office building is an L-shaped structure which occupies approximately 10,800 square feet just south of McIntosh Circle Drive in the south part of the city of Joplin.

The construction contract, prepared on standard AIA forms which have been modified, indicates it was drawn up in June 1986, although neither the precise date of the contract nor the total contract price appear in the document laid before this court. Shortly before bids were due on the contract, defendant Powers solicited Dennis Robinson and his. son Dale, who operated the Robinson Excavating Company, to do the “site work” or “dirt work” necessary to prepare the building site for construction. The site work consisted of excavation and filling, or “cutting and filling” so as to bring the building pad and the surrounding parking lot to grade. The proposed elevation of the building pad itself was 1,016 feet. 1 As the defendant has accurately put the matter in his brief, the elevation of the terrain varied greatly across the building site, and in order to bring the elevation of the building pad and the surrounding area to that specified, it was necessary to lower or “cut” some areas and to fill others. The plaintiffs were experienced excavation contractors.

During his initial meeting with the plaintiffs, defendant gave plaintiffs the site plan and “told [plaintiff] that he was looking for a total and complete excavation price for that project.” Plaintiff Dennis Robinson testified that he, his son and Powers “[discussed the site and the nature of the work to be done; and we took the prints and the specs, took them home and studied them.” Subsequently, the plaintiffs offered to do the excavation work for $20,000. The plaintiffs were the only excavators on the job. At some time after the work had been begun, a written subcontract was tendered to the plaintiffs. This contract, received in evidence as plaintiffs’ exhibit “B,” recites an agreement by the plaintiffs to “site clear and grub, dispose of tree limbs, stumps; site [and] building cut [and] fill; undercut footings [and] slab as specified” and to do certain other work for the sum of $20,000. This contract, or subcontract, was not sent to the plaintiffs for some time after work had been commenced and was never signed by or on behalf of either party.

A few days after the parties’ initial discussion, plaintiffs began work on the building site. As the defendant recalled, the Robinsons moved on the site and started work on August 6, 1986. The site work progressed and on August 20, plaintiff Dale Robinson submitted a request for payment in the amount of $12,600, representing 70 percent of the work bid less a 10 percent retent. Plaintiffs’ evidence was that both the defendant and the architect approved this request for payment.

Controversy developed at some time after August 20th when it appeared there was a possibility there would not be enough fill dirt unless additional dirt was *677 imported. Whether there was an actual shortage of dirt for fill purposes was a matter of controversy on trial. Plaintiff Dennis Robinson testified that “after we had worked there about 20 days straight, it was discussed on the job that there wasn’t enough dirt to complete the job.” The “lack of dirt” was explained in part by plaintiff Dennis as follows (using a site drawing, apparently, to make his point):

“Q. Now, this particular site, it’s true is it not that a gully ran through the—
A. Right there where the dish is in the middle. Right in the middle of the building. Right in the middle of the building.
Q. Right here?
A. No. Middle of the building, the L, the L.
Q. All right.
A. You’re getting close.
Q. You point—
A. In the middle of the L. This is your gully coming right up through the middle.
Q. All right. The gully ran through here, and you can see some grading at lines there that shows—
A. Yes, sir.
Q. —it got as low as about 18 feet below the building site; is that true?
A. Yes, sir. Yes, sir.
Q. Now, when you had the pad completed and graded to level, that gully was not fulled [sic]; was it? Well, let’s get it up where everybody can see it.
A. This pad, when we had it completed, we were filled out to a point about in here, the edge we lacked dirt. At the building area the pad was complete, they had run the final inspection on the testing and had accepted it.”

The defendant argues, and there was some evidence tending to show, that additional fill dirt could have been imported to fill up the “gully,” but according to the defendant, he and his construction superintendent discovered that approximately 2,000 yards of fill would be required to bring the grade to the proper elevation as shown on the original plans. Plaintiff Dale Robinson, according to the defendant, agreed. Several possibilities were discussed; it was finally determined, as the defendant recites the facts, that the building pad would be lowered to avoid the importation of fill. After the building pad had been lowered 18 inches, plaintiff Dennis Robinson “showed up on the job” and took the position that he was entitled to extra compensation for the additional work involved in lowering the pad. When the defendant refused to agree to Robinson’s demand for additional compensation, Robinson “pulled his people off the site.”

The plaintiffs filed a petition in three counts. In the first count, plaintiffs pleaded the execution of an express contract between defendant, as prime contractor, and Dennis Robinson, as owner of the Robinson Excavating Company. Plaintiffs pleaded a breach of the contract and damages in the amount of $29,327.50. In the second count, plaintiffs sought to impress a mechanic’s lien upon the completed office center. In the third count plaintiffs sought recovery of $26,872.50 in quantum meruit. Defendant Powers filed an answer and counterclaim. Defendant Freeman Hospital, the owner, also filed an answer and counterclaim. Freeman’s counterclaim was voluntarily dismissed prior to trial. On May 17, 1988, the cause was tried to the court without the intervention of a jury. On June 7, the trial court found for plaintiffs Robinson and against the defendants on Counts I and II. It was ordered that plaintiffs have judgment against defendant Powers in the amount of $14,000 plus interest at the rate of 9 percent per annum from and after August 20, 1986; that a mechanic’s lien be impressed upon the completed office building and that plaintiffs take nothing upon Count III of their petition.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jenn Baier v. Darden Restaurants
Missouri Court of Appeals, 2014
Baier v. Darden Restaurants
420 S.W.3d 733 (Missouri Court of Appeals, 2014)
Bellemere v. Cable-Dahmer Chevrolet Inc.
423 S.W.3d 267 (Missouri Court of Appeals, 2013)
Weitz Co. v. MH WASHINGTON
631 F.3d 510 (Eighth Circuit, 2011)
Heritage Roofing, LLC v. Fischer
164 S.W.3d 128 (Missouri Court of Appeals, 2005)
Flooring Systems, Inc. v. Staat Construction Co.
100 S.W.3d 835 (Missouri Court of Appeals, 2003)
Schell v. LifeMark Hospitals of Missouri
92 S.W.3d 222 (Missouri Court of Appeals, 2002)
Housley v. Mericle
57 S.W.3d 360 (Missouri Court of Appeals, 2001)
Ken Cucchi Construction, Inc. v. O'Keefe
973 S.W.2d 520 (Missouri Court of Appeals, 1998)
Birdsong v. Bydalek
953 S.W.2d 103 (Missouri Court of Appeals, 1997)
Pilgram v. Missouri Real Estate Commission
835 S.W.2d 545 (Missouri Court of Appeals, 1992)
Stege v. Hoffman
822 S.W.2d 517 (Missouri Court of Appeals, 1991)
State, Department of Social Services v. Beckner
813 S.W.2d 353 (Missouri Court of Appeals, 1991)
Cunningham v. Cunningham
805 S.W.2d 363 (Missouri Court of Appeals, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
777 S.W.2d 675, 1989 Mo. App. LEXIS 1423, 1989 WL 116686, Counsel Stack Legal Research, https://law.counselstack.com/opinion/robinson-v-powers-moctapp-1989.