LARRY SNYDER AND COMPANY v. Miller

648 F.3d 1156, 2011 U.S. App. LEXIS 16832, 2011 WL 3559928
CourtCourt of Appeals for the Tenth Circuit
DecidedAugust 15, 2011
Docket10-5045
StatusPublished
Cited by3 cases

This text of 648 F.3d 1156 (LARRY SNYDER AND COMPANY v. Miller) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
LARRY SNYDER AND COMPANY v. Miller, 648 F.3d 1156, 2011 U.S. App. LEXIS 16832, 2011 WL 3559928 (10th Cir. 2011).

Opinion

EBEL, Circuit Judge.

In this appeal, Plaintiff-Appellant Larry Snyder and Company (Snyder) argues that the district court erred by granting summary judgment to Defendant-Appellee Clark Miller, doing business as American Underground Utilities (Miller), on Snyder’s breach of contract claim. Snyder and Miller entered into a subcontract *1158 agreement, under which Miller would install utility trenches underneath what would become a parking lot for an apartment complex. Miller performed the work, but once the asphalt for the parking lot was installed, the trenches settled and the parking lot was damaged. Snyder requested that Miller repair the entire parking lot, but Miller refused, arguing that the subcontract only required it to repair the areas of the parking lot that actually settled.

We agree with the district court that the subcontract unambiguously governed the extent of the repair required of Miller. Accordingly, no genuine issue of material fact exists concerning Miller’s liability for repair work that exceeded the requirements of the subcontract and summary judgment was appropriate. Exercising jurisdiction pursuant to 28 U.S.C. § 1291, we AFFIRM.

I. Background

Snyder entered into an agreement with the Housing Authority of the Osage Tribe (Osage), under which Snyder agreed to be the general contractor on the Stoneridge Estates apartment complex. In the contract between Snyder and Osage, Osage required every subcontract to have the following “flow-through” clause:

Contractor shall include with every Subcontractor agreement the following language: Subcontractor binds itself to Contractor and Owner and is obligated to Contractor and Owner in the same manner and to the same extent that Contractor is bound and obligated to Owner under the Prime Contract. All rights which Owner may exercise and enforce against Contractor may be exercised and enforced by Contractor against Subcontractor, in the event of any dispute between the Owner and Contractor. Subcontractor shall be bound by all decisions, directives, interpretationfs] and rulings of the owner or the Architect, at Owner[’]s option, including Owner’s termination or suspension of Contractors.

(Aplt. App., vol. I at 91.)

Snyder then entered into a subcontract agreement with Miller, under which Miller agreed to install utility trenches underneath what would become a parking lot for the apartment complex. Snyder’s subcontract with Miller contained the language of the flow-through clause as specified in the contract between Snyder and Osage. The subcontract also contained the following provision explaining Miller’s responsibilities:

Responsible for all bedding and compaction of trenches per contract documents, city requirements and the geotechnical report. This to include 18" minimum of crushed stone base material placed in 8" lifts in all utility and storm sewer trenches under areas receiving paving per plans. All trenches to be compacted to 95% per contract documents. In the event that settlement or failure should occur under parking lots, sidewalks, curb and gutter, and landscaped areas resulting in damage to other trades work, this subcontractor is responsible to remove the damaged area, acquire proper compaction and replace area at this subcontractor’s expense.

(Id. at 59 (emphasis added).) We will refer to the last clause in that provision as the repair clause.

Miller excavated, filled, and compacted the trenches, and then another subcontractor installed the asphalt for the parking lot. After the installation of the parking lot asphalt, the trenches settled, resulting in damage to the parking lot.

Miller’s engineers, Standard Testing and Engineering Company, inspected the settled areas and recommended that “[t]he asphalt in the paved areas ... be cut back so that it is wider than the trench (over cut) by two feet on each side before repav *1159 ing.” (Id. at 219.) Osage, relying on the recommendation of its engineers, Kaw Valley Engineering, instead insisted that Miller repair the entire parking lot, not just the damaged areas. So after conferring with Osage, Snyder sent a letter to Miller requesting eight repairs: (1) set up traffic control and coordinate phasing with Osage and Snyder, (2) sawcut and remove asphalt paving in the marked areas, (3) sawcut and remove the curb and gutter that are marked, (4) excavate the trenches and backfill the material with flowable fill up to the bottom of the asphalt paving, (5) form and place the curb and gutter, (6) mill the top 1/6" of asphalt and repair the entire parking lot, (7) re-strip the entire parking lot, and (8) remove all excess demolished material and clean-up.

Miller agreed to make most of the repairs requested except for (6) mill the top 1)6" of asphalt and repair the entire parking lot and (7) re-strip the entire parking lot. Miller continued to refuse to perform those two repairs, and so Snyder contracted with another subcontractor to perform all of the repairs requested.

Miller filed suit against Snyder for damages arising out of a contract dispute on a related project. Then, Snyder filed a counterclaim for breach of contract regarding Miller’s failure to repair the trenches, seeking $295,352.92, the damages incurred in repairing the entire parking lot. The parties stipulated to the amount of payment due on the related project, so those claims were dismissed by Miller. Then, the district court realigned the parties with Snyder as plaintiff and Miller as defendant.

After discovery, both Snyder and Miller filed motions for summary judgment. The district court entered an order on December 30, 2009, granting summary judgment in favor of Miller. Then, Snyder filed a motion to reconsider. The district court issued a new order on March 2, 2010, but it reached the same conclusion. Snyder timely appealed.

II. Discussion

We review the district court’s grant of summary judgment de novo. Evers v. Regents of Univ. of Colo., 509 F.3d 1304, 1308 (10th Cir.2007). Summary judgment is appropriate when “there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.” Fed.R.Civ.P. 56(a).

According to the subcontract, Missouri law governs this case. Under Missouri law, a contract is ambiguous only if its terms are susceptible to fair and honest differences. Eisenberg v. Redd, 38 S.W.3d 409, 411 (Mo.2001) (en banc). “In contractual interpretation, the primary rule is to ascertain the intent of the parties and then give effect to that intent. When there is no ambiguity in the contract, the intent of the parties is to be gathered from [the contract] alone.” Lueckenotte v. Lueckenotte, 34 S.W.3d 387, 395 (Mo.2001) (en banc) (per curiam) (alteration in original).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jackson v. Education & Employment Ministry
686 F. App'x 577 (Tenth Circuit, 2017)
Phillips v. Long (In re Long)
555 B.R. 31 (D. Utah, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
648 F.3d 1156, 2011 U.S. App. LEXIS 16832, 2011 WL 3559928, Counsel Stack Legal Research, https://law.counselstack.com/opinion/larry-snyder-and-company-v-miller-ca10-2011.