Noonan v. Independence Indemnity Co.

41 S.W.2d 162, 328 Mo. 706, 76 A.L.R. 931, 1931 Mo. LEXIS 410
CourtSupreme Court of Missouri
DecidedJuly 28, 1931
StatusPublished
Cited by13 cases

This text of 41 S.W.2d 162 (Noonan v. Independence Indemnity Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Noonan v. Independence Indemnity Co., 41 S.W.2d 162, 328 Mo. 706, 76 A.L.R. 931, 1931 Mo. LEXIS 410 (Mo. 1931).

Opinion

*710 ATWODD, J.'

This is a suit on a bond given to secure the performance of a building contract. The case was tried to a jury which returned a verdict in favor of plaintiff/ Elizabeth E. Noonan, and against defendant, Independence Indemnity Company, upon which judgment for $13,787.64 was rendered, and from this judgment defendant has appealed.

The evidence showed that plaintiff was the owner of vacant ground in De Mjun Park, a subdivision adjoining the city of St. Louis, and desiring to erect a four-family apartment building thereon for which she had plans and specifications, she entered into said building contract with the J. W. Caldewey Construction Company, Inc., under date of September 20, 1923. Thereafter, under date of September 24,-: 1923, plaintiff, through an insurance broker named Mulligan, for a premium of $¡421.50, procured defendant’s said bond-in the penal sum of $28,100 executed by Orr C. Frazier as defendant’s attorney in fact, he being of the firm of Muckerman & Cushman, who were at that time defendant’s agents. Said J. W. Caldewey Construction Company, by- J. W. Caldewey, president, executed said bond as principal and defendant as surety, plaintiff herein being named as obligee.

The evidence further showed that on October 5, 1923, plaintiff delivered to J. W. Caldewey, president of said construction com *711 pany, at said company’s office, the two deeds of trust and accompanying notes, one deed of trust securing the principal sum of $5,000 and the other securing the principal sum of $4500, $750 having been paid upon the latter, leaving a balance of $3750, the aggregate principal amount of the notes secured by said two deeds of trust-being $8,750; that work was begun under said contract on October 10, 1923, and progressed to the point where the foundation was put in and the joists were.laid for the first floor; that thereafter the work practicálly ceased, and early in December, 1923, plaintiff discovered that the contractor -was going to fail in the construction of the building within the time fixed by the .contract, and under date of December 12, 1923, she wrote a letter to defendant, advising defendant that the business with said contractor was in a very unsatisfactory shape, that she was receiving unpaid bills and notices of liens, that material seemed to be arriving* on the premises and nothing was being paid for; that it seemed impossible for her to get in touch with Mr. Caldewey, that “he seems to be full of promises and never respects any of them,” and plaintiff asked defendant’s speedy attention. This letter was received by Muckerman & Cush-man, defendant’s agents aforesaid, but plaintiff was given no reply. About a week thereafter plaintiff called upon Mr. Cushman of said firm of Muckerman & Cushman and'was referred to the aforesaid Orr C. Frazier and was told by Mr. Cushman that Mr. Frazier - was attending to this business and would give the matter attention. It further appears that on the occasion of this visit plaintiff 'waited for the arrival of Mr. Frazier and when he came in she told him that Mr. Caldewey had not been working on the building and would not get it finished in the time specified, and Mr-. Frazier thereupon told her that he would take the matter up with the construction company; that she waited to hear from Mr. Frazier and when he failed to communicate with her she telephoned him, and .was asked to come down to see him and when she went down he was not there; that she finally got to see Mr.Frazier again and told him that, she was unable to see Mr. Caldewey, that she had been to his office several times and that he was always out; that Frazier then said: “Well, I will see him tomorrow, I am going to see him tomorrow at three o’clock;” that plaintiff went to Frazier’s office at the time thus indicated and discussed with Caldewey and Frazier tho lack of progress that was being made on the building; that thereafter plaintiff called to see Frazier again and was referred to ‘ defendant’s claim agent; that plaintiff.went to see said claim agent about said contractor’s failure to complete the work on said building and said claim agent asked and obtained from her the contract, bond 'and papers and told her to return; that she returned twice and said claim agent stated that he wanted to see Mr. Cushman about *712 the matter; that upon her next call plaintiff was confronted with said claim agent and defendant’s attorney. Thereupon she employed counsel who testified at the trial that he had conferences with defendant’s claim agent and counsel and that neither said anything to him with reference to plaintiff’s failure to give notice, and that no claim was ever made by them that there was no liability because of failure of notice. The evidence further showed that mechanics’ liens were filed against plaintiff’s property; ■ that plaintiff paid the Missouri Portland Cement Company $707.24 and the Reis Lumber Company $419.65 in settlement of lien claims, and paid cost bills in connection with lien claims in the sums of $20.05 and $5 and paid her counsel a fee of $100 for settling up these claims-. The evidence further showed that plaintiff made diligent but unsuccessful efforts to find J. AY. Caldewey, president of said construction company, and to get service upon said company; that the office of said company had been closed by the sheriff. The evidence further showed that plaintiff had never been repaid any part of the $8,750 in notes delivered by her to said company; that the building was never completed; that under date of March 6, 1924, her counsel wrote defendant advising it of the liens above mentioned and of the fact that plaintiff had delivered said deeds of trust and notes to the contractor pursuant to said building contract, and again called upon defendant to complete the building or indemnify her for damages sustained through failure of said contractor to complete the work. Plaintiff testified that she did not appoint an architect, that she had the option of having an architect or not and that she did not want one because Mr. C'aldewey was a very good architect. The evidence also showed that the contractor had never arranged for the building loan as provided by said building contract, although plaintiff had asked that such be done; that plaintiff had never received any interest on her deeds of trust since she turned them over to said company; and that at the time defendant’s bond was executed by Orr C. Frazier as defendant’s attorney in fact the said Frazier was the secretary of said construction company.

There was substantial evidence that the cost of, the work done by said contracting company was $1842; that the fair market value of constructing said building according to plans and specifications was $29,400, exclusive of cost of financing; that the reasonable charge for procuring a $18,600 building loan was $930. It was agreed that the reasonable time required to finish the building would have been three months; and that the fair rental value of each of the flats in the building was $110 per month, or a total rental of $440 per month for the building.

Defendant offered no evidence, and under the evidence submitted by plaintiff the jury returned a verdict for plaintiff in the sum of *713 $11,704 principal, and $2,083.64 interest, or tbe aggregate sum $13,-787.64.

Appellant’s chief contention is that the building contract “contained two vital provisions: First,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

First State Bank v. Reorganized School District R-3, Bunker
495 S.W.2d 471 (Missouri Court of Appeals, 1973)
Edmonds v. Stratton
457 S.W.2d 228 (Missouri Court of Appeals, 1970)
Meade v. Barrett & Co.
453 S.W.2d 632 (Missouri Court of Appeals, 1970)
EE Rabalais & Son, Inc. v. United Bonding Ins. Co.
226 So. 2d 528 (Louisiana Court of Appeal, 1969)
Samuels v. Illinois Fire Insurance Company
354 S.W.2d 352 (Missouri Court of Appeals, 1962)
BOLIVAR REORG. SCHOOL DIST., ETC. v. American Sur. Co.
307 S.W.2d 405 (Supreme Court of Missouri, 1957)
Garden City Floral Co. v. Hunt
255 P.2d 352 (Montana Supreme Court, 1953)
Massachusetts Bonding & Insurance Co. v. Feutz
182 F.2d 752 (Eighth Circuit, 1950)
Feutz v. Massachusetts Bonding & Ins.
85 F. Supp. 418 (E.D. Missouri, 1949)
Stubblefield v. Montgomery Ward & Co.
98 P.2d 14 (Oregon Supreme Court, 1940)

Cite This Page — Counsel Stack

Bluebook (online)
41 S.W.2d 162, 328 Mo. 706, 76 A.L.R. 931, 1931 Mo. LEXIS 410, Counsel Stack Legal Research, https://law.counselstack.com/opinion/noonan-v-independence-indemnity-co-mo-1931.