Meade v. Barrett & Co.

453 S.W.2d 632, 1970 Mo. App. LEXIS 646
CourtMissouri Court of Appeals
DecidedMarch 24, 1970
DocketNo. 33592
StatusPublished
Cited by5 cases

This text of 453 S.W.2d 632 (Meade v. Barrett & Co.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Meade v. Barrett & Co., 453 S.W.2d 632, 1970 Mo. App. LEXIS 646 (Mo. Ct. App. 1970).

Opinion

CLEMENS, Commissioner.

The issue here is whether a surety for a building contractor, having given an unconditional bond to the owner guaranteeing payment of the contractor’s labor and material bills, is relieved of liability to the owner when the owner, knowing of unpaid labor and material bills, pays the contractor in full.

This issue comes up as the by-product of a mechanic’s lien suit. Therein several subcontractors of the general contractor, Barrett & Company, Inc., (Barrett), got $8,263 in judgments and liens against the owner, Sperry & Hutchinson Co. (S & H), and its new store building in St. Louis County. By its third-party petition S & H sought judgment over against the United Bonding Insurance Co. (United) who had guaranteed payment of Barrett’s labor and material bills. Neither the construction contract nor United’s bond made any provision for S & H withholding payment from Barrett after completion of construction. In defense to S & H’s claim United pleaded that S & H had breached the bond when it paid Barrett in full, knowing Barrett had not paid for all labor and materials. The bond imposed no such condition on S & H. The trial court struck this defense from United’s third-party answer and upon trial gave S & H judgment over against United for the $8,263 of lienable accounts, and also judgment for an $826 ten per cent penalty and $3,000 attorneys’ fee for vexatious delay.. United appeals.

S & H solicited construction bids for a store building in St. Louis County in November, 1966 and Barrett’s bid was accepted. He had been the successful bidder for some forty S & H store buildings during the three preceding years. No performance bonds were required the first two years and at the end of each job Barrett had to make proof of payment of subcontractors before S & H would pay Barrett the contract price. Barrett complained this requirement unduly delayed S & H’s payments, which were needed promptly to pay Barrett’s subcontractors for labor and materials. S & H assured Barrett payment could be speeded up if Barrett posted bonds. In October, 1965 Barrett began posting bond on each S & H contract; thereafter no proof of payment to subcontractors was required. Invoices were submitted, S & H would pay promptly and Barrett would use the money to pay subcontractors.

December 2, 1966 Barrett made a written $17,831 bid to S & H, agreeing therein to furnish a construction performance bond and upon S & H’s acceptance Barrett delivered United’s bond to S & H. It declared: “Now Therefore, the condition of this obligation is such that if the Principal [Barrett] * * * shall pay all persons who have contracts directly with the Principal for labor or materials, then this obligation shall be null and void, otherwise it shall remain in full force and effect.” (Our emphasis).

[634]*634Barrett completed construction to S & H’s satisfaction in March, 1967 and billed S & H for the $17,831 contract price. March 27th S & H paid Barrett in full. April 17th, three weeks later, S & H learned that Barrett still owed substantial amounts to its subcontractors and on May 1st S & H notified United of Barrett’s unpaid accounts. June 15th United denied liability on the ground S & H had paid Barrett without first determining that Barrett had paid for all laborers and ma-terialmen. Barrett’s subcontractors soon began mechanic’s lien procedures against S & H and this lawsuit followed, ending with judgments and liens against S & H but in favor of S & H against United.

United’s only attack on the issue of its liability is that the trial court erred in striking its affirmative defense from its answer to S & H’s third-party petition. Therein United had answered it was relieved from liability to S & H because S & H, with knowledge of. Barrett’s outstanding labor and material bills, had paid Barrett the full contract price instead of diverting part of it to Barrett’s unpaid laborers and materialmen. The record does not justify this assumption that S & H had the duty to withhold payment from Barrett until assured that all subcontractors had been paid.

United relies primarily on the case of Chouteau Trust Co. v. Massachusetts Bonding & Ins. Co., 8 Cir., 1 F.2d 136. The case is not in point. It concerns a surety’s rights against a contractor’s assignee under a public contract, not a surety’s rights against an owner under a private contract. The only Missouri case cited by United is National Surety Corporation v. Fisher, Century Indem. Co., Mo., 317 S.W.2d 334, but it is not in point. It too concerns a surety’s rights against a contractor, not as here a surety’s rights against an owner. The case not only fails to support United’s claim but refutes it, saying at 1. c. 345: “ * * * when sums earned under the contract are paid generally to the contractor, such funds are thereby freed of any equity or right of subrogation in the surety.”

Actions on contractors’ bonds come in many varieties, differing widely as to parties litigant, terms of the bonds and construction contracts, purposes of the bonds, and nature of defaults. (See the 138 topics in the table of contents to Contractors’ Bonds, 17 Am.Jur.2d, pp. 187-191). From a welter of Cases from other jurisdictions, none like the one here, United has culled sweeping legal phrases such as “a surety must be dealt with in fairness and good faith”, “wrongful act of payment” and “equitable lien.” To these catch phrases United adds such argumentative platitudes as “bad faith”, “contemptuous disregard” and “unwritten rights and duties.” All this obscures the nature of United’s liability.

For example, United relies on § 33, Contractors’ Bonds, 17- Am.Jur.2d, headed: “Failure to withhold payments as required by contract, bond, or statute.” United thus ignores the fact that here neither the construction contract nor its bond required or authorized S & H to withhold payment from Barrett. United also fails to state that § 33 is a qualification of the preceding §31 which cites Noonan v. Independence Indemnity Co., 328 Mo. 706, 41 S.W.2d 162, 76 A.L.R. 931, in support of the general rule: “Generally speaking, and in the absence of any express provision to the contrary in the bond, payment, in accordance with the terms of the construction contract, made by the owner to the contractor does not release the surety on the contractor’s bond from liability to the owner.”

Our case fits snugly within that general rule. The construction contract gave S & H no authority to withhold funds from Barrett upon completion of the contract. When Barrett’s work was done the contract obligated S & H to pay Barrett. See 127 A.L.R. 34-36 annotating cases holding sureties liable where construction contracts, as here, are silent as to time and conditions of payment. This annotation cites Litchgi [635]*635v. Gottlieb, 134 Mo.App. 237, 113 S.W. 1134 [2]:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Nervig v. Workman
285 S.W.3d 335 (Missouri Court of Appeals, 2009)
Earney v. Clay
516 S.W.2d 59 (Missouri Court of Appeals, 1974)
Cady v. Kansas City Southern Railway Co.
512 S.W.2d 882 (Missouri Court of Appeals, 1974)
Adams v. White
488 S.W.2d 289 (Missouri Court of Appeals, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
453 S.W.2d 632, 1970 Mo. App. LEXIS 646, Counsel Stack Legal Research, https://law.counselstack.com/opinion/meade-v-barrett-co-moctapp-1970.