State Ex Rel. Seibel v. Trimble

253 S.W. 215, 299 Mo. 164
CourtSupreme Court of Missouri
DecidedJune 3, 1923
StatusPublished
Cited by7 cases

This text of 253 S.W. 215 (State Ex Rel. Seibel v. Trimble) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State Ex Rel. Seibel v. Trimble, 253 S.W. 215, 299 Mo. 164 (Mo. 1923).

Opinion

GRAVES, P. J.

Certiorari to Kansas City Court of Appeals. The present proceeding grows out of the case of Arthur E. Price and Edna S. Price, Administrators, (Plaintiffs) Respondents, v. Louis L. Seibel and E. W. Lawson, (Defendants) Appellants, decided by the Kansas City Court of Appeals, and in which the judgment of the Jackson County Circuit Court was affirmed. The relators here (defendants in the court below) were the sureties upon a contractors bond, executed by John R. Murphy, as principal, and these relators as sureties, to P. W. Price, and was givén to secure the faithful performance of a builder’s contract between Murphy and Price. Price sued the sureties, but not the principal in the bond. In the lower court he had judgment for the penalty of the bond ($5,000), to be satisfied upon the payment of .$1469.21, the damages found, and the payment of the costs of the action. The general outlines of the case are thus stated by the Court of Appeals:

“This is a suit on a building contractor’s bond executed by one John R. Murphy, the contractor, as principal, and Louis L. Seibel and E. W. Lawson, the defendants herein, as sureties. This action is against the sureties only.
“By a contract entered into July 10, 1912, Murphy agreed with P. W. Price to construct an eight-apartment *169 building at Linwood Boulevard and Wabash Avenue in Kansas City, Missouri, for the sum of $21,150, subject to additions and deductions as provided in the contract. Payments were to be made upon certificates of the architects to the amount of eighty-five per cent of the receipted bills to be presented by the contractor from time to time. It was provided the east half and all of the basement should be ready for occupancy by October 15, 1912, and the entire building completed by December 1st, of the same year. It was agreed that the owner should carry insurance during the progress of the construction to cover all work incorporated in the building and for all materials for the same in and about the premises, payable to the owner and contractor as their interests should appear.
“The defendants herein, as sureties, gave bond to plaintiff in the sum of $5,000 for the faithful performance by the principal of all the terms of the contract and for the payment for all labor and 'materials used in the construction of the building, so that no liens of any kind would be created. There was also a stipulation in the bond that no alterations in the terms of the contract or waivers by the parties of the provisions thereof, nor any forbearance or overpayment on the part of the obligee to the principal, should operate as a release or affect the liability of the sureties.
“The contractor entered upon the performance of the contract and continued work until January 5, 1913, when, by reason of a fire, the building was damaged in the amount of $6,956.60, which amount was determined by the insurance companies and by a representative selected by the owner and contractor. At the time of the fire, plaintiff had paid the sum of $14,477.65, on warrants signed by the architects, which amount was an excess of $873.78 over the disbursements made by the contractor as shown by the receipts for disbursements. The testimony tends to show that the contractor performed certain extra work amounting to $782, so that his total credit, exclusive of the insurance, was $21,932.-
*170 “The insurance policies were taken out during the progress of the work in the name of the owner. The total amount of the insurance was paid to the owner. The insurance was taken out pursuant to the contract, but as it was taken in the name of the owner instead of the owner and contractor, it was not in strict accordance with its terms. Plaintiff and the contractor joined in making proof of loss.
“The testimony tends to show that of the total amount of the insurance, $6,433.01 was allowed by the contractor, Murphy, as damage to the work, and the remainder, $523.59, was allowed as damage to other parts of the building which was the work of other contractors.
“On December 30, 1912, the contractor was served with written notice that unless the building* was completed by February 1, 1913, plaintiff would take charge and complete it. This notice was based upon complaint that the contractor was not proceeding* with the work with due diligence. The fire intervened, however, and caused the work to cease and the notice was abandoned. Some delay was encountered in securing brick and extra work, and the contractor was entitled to some extension of time, for which proper allowance was made.
“It appears from the evidence that it was tacitly understood by plaintiff and the contractor that work on the building would be suspended until the insurance was adjusted and that the insurance fund would be used to repair the fire damage. When the insurance was adjusted the contractor claimed all of said fund and demanded that he be paid an additional sum of $700, or he would not proceed with the work. Plaintiff refused to comply with this demand, whereupon Murphy abandoned the contract. Plaintiff took charge about February 1, 1913, repaired the damage caused by the fire, and completed the building*.
“Further it appears that Murphy made no demand for any of the insurance money other than the whole *171 sum, and that no tender of any part of the amount was made to him. It required about one month to repair the fire damage and two months more to complete the building. To repair the fire damage plaintiff paid the sum of $4,070.32, and for material to finish the building, on bills previously incurred by Murphy, the sum of $10,025.25, together with the payment previously made to the contractor, making a total of $23,573.22. Among the bills paid was one for mill work, $2,700. The evidence tends to show that about $1,000 worth of this material had been used in the construction of the building prior to the time of the fire; part of the remainder was destroyed by fire, and that not so destroyed was used in the construction after the fire. None of the disbursements in the repair of the fire damage and in the completion of the building was audited or certified by the architects, as provided by the contract.
‘‘ The amended petition is formal and charges breach of contract in that the contractor failed to complete the building within the time specified, and the resultant loss of rentals, failure to prosecute the work with due diligence, and abandonment of the contract. Further the amended petition pleads payment of amounts chargeable to the contractor, as set out above. Judgment is praved in the sum of $5,000 and interest.
“The answer is, first, a general denial, and for further answer admits the execution-of the contract and states that the bond charged in the petition was executed; and as special defenses, pleads failure of plaintiff to secure insurance payable to the contractor and owner

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Meade v. Barrett & Co.
453 S.W.2d 632 (Missouri Court of Appeals, 1970)
State Ex Rel. Alton Railroad Co. v. Shain
143 S.W.2d 233 (Supreme Court of Missouri, 1940)
State Ex Rel. Talbott v. Shain
66 S.W.2d 826 (Supreme Court of Missouri, 1933)
State Ex Rel. Union Indemnity Co. v. Shain
66 S.W.2d 102 (Supreme Court of Missouri, 1933)
State Ex Rel. English v. Trimble
9 S.W.2d 624 (Supreme Court of Missouri, 1928)
State Ex Rel. Union Biscuit Co. v. Becker
293 S.W. 783 (Supreme Court of Missouri, 1927)
State Ex Rel. John Hancock Mutual Life Insurance v. Allen
267 S.W. 832 (Supreme Court of Missouri, 1924)

Cite This Page — Counsel Stack

Bluebook (online)
253 S.W. 215, 299 Mo. 164, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-ex-rel-seibel-v-trimble-mo-1923.