Litchgi v. Gottlieb

113 S.W. 1134, 134 Mo. App. 237, 1908 Mo. App. LEXIS 635
Missouri Court of Appeals·Decided November 17, 1908·Published·Cited by 5 cases

Opinion

BLAND, P. J.

The action is against a surety on a builder’s bond. The bond provided that the builder should build the bouse according to contract. The only portion of the contract directly bearing upon the issues as made by the pleadings is- the clause in respect to the payment of the contract price of $1,781.50. This clause reads as follows: “The said party of the first part agrees and binds itself for and in consideration of the erection of said buildings as aforesaid, to pay unto the party of the second part the sum of $1,781.50.” The proof shows that plaintiff paid the contractor $200 when the foundation of the house was completed and at about the same time executed bis note to the builder for the sum of $970, securing the same by a deed of trust on the lot of ground upon which the building was in the course of construction, which note and deed of trust the builder immediately sold for cash, which be retained. The proof further shows that the builder, after erecting the walls of the bouse and partially inclosing it, abandoned bis contract and left the State. After the builder abandoned bis contract, plaintiff [239] paid the sum of $614.97 in debts incurred by the builder for material used in the construction of the bouse and for labor done upon it; be also paid $905.15 for the completion of the structure after the contractor abandoned it. By the terms of the contract, the builder agreed to complete the bouse on or before September 10, 1905. It was not completed until June 1, 1906, and it was agreed that the rental value of the bouse was $25 per month.

The defense set up in the answer was that defendant was discharged from bis obligation as a surety on the bond,, for the reason plaintiff departed from the terms of the contract by making the payment of $200, and indirectly the one of $970, to the contractor before the completion of the building. The court, to whom the issues were submitted, ruled against this defense and found the issues for the plaintiff, assessing bis damages at $993.20, and rendering judgment therefor in bis favor. As there was no time agreed upon when the contract price should be paid, the builder could not demand payment of any portion of the contract price prior to the completion of the building. [Coburn v. City of Hartford, 38 Conn. 290; Shanks v. Griffin, 14 B. Mon. (Ky.) 153; Thompson v. Phelan, 22 N. H. 339.] Plaintiff concedes that be was not bound to pay the contract price or any part thereof until the building was completed, but contends that as the contract does not prohibit the payment of the contract price before the completion of the building, be was at liberty to pay as be chose, in advance, as the work progressed, or on the completion of the building and in these circumstances, the payment made before the building was completed was not a departure from the terms of the contract. In support of this contention, plaintiff’s learned counsel cite the following cases: Fidelity & Deposit Co. of Maryland v. Robertson, 136 Ala. 379; Hand M'fg. Co. v. Marks, 36 Ore. 523; DeMattos v. Jordan, 15 Wash. 378.

[240] Fidelity & Deposit Co. v. Robertson was a suit on a builder’s bond. The contract provided that the amount agreed upon was to be paid in equal installments upon the approval of the architect, and that fifteen per cent should be reserved on all payments until the building was completed. It Avas held that this provision was solely for the benefit of the owner and that the answer by his surety in which a departure from it was pleaded, as a defense to the action on the bond, was demurrable. In Hand Mfg. Co. v. Marks it was ruled that a surety on a contractor’s bond was not .discharged by the owner making a premature payment to the contractor when the payment did not impair any security reserved under the contract and which would inure to the benefit of the surety. In DeMattos v. Jordan it was held: “Where a building contractor was to be paid monthly, as the work progressed, upon the supervising architect’s estimate of the amount of work completed, the fact that the owner accepts an order from the contractor in favor of a materialman and agrees to pay same, on the day the estimate becomes due, paying at the time cash, however, a small percentage of the claim to accommodate the materialman, does not constitute such a payment in advance as Avill release the sureties upon the contractor’s bond.”

The Am. and Eng. Ency. of Law, vol. 27, p. 496, states the laAV to be that, “Where the contract provides, as it usually does, that the OAvner shall withhold a- certain per cent of the contract price until the contractor has completed the building, the failure to withhold such money will discharge the surety, not only on the ground that it is an alteration of the contract, but that it is a surrender of security agreed to be held for his benefit.” In the same paragraph it is noted that in some jurisdictions the surety is not discharged by the failure to retain such reserve percentage.

Free access — add to your briefcase to read the full text and ask questions with AI

Litchgi v. Gottlieb, 113 S.W. 1134, 134 Mo. App. 237, 1908 Mo. App. LEXIS 635 (Mo. Ct. App. 1908).

113 S.W. 1134 (Litchgi v. Gottlieb) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Meade v. Barrett & Co.
453 S.W.2d 632 (Missouri Court of Appeals, 1970)
Padgett v. Brezner
359 S.W.2d 416 (Missouri Court of Appeals, 1962)
State Ex Rel. Union Indemnity Co. v. Shain
66 S.W.2d 102 (Supreme Court of Missouri, 1933)
Chernus v. Kennedy-Coats Construction Co.
55 S.W.2d 744 (Missouri Court of Appeals, 1932)