Evans v. Graden

28 S.W. 439, 125 Mo. 72, 1894 Mo. LEXIS 368
CourtSupreme Court of Missouri
DecidedNovember 26, 1894
StatusPublished
Cited by24 cases

This text of 28 S.W. 439 (Evans v. Graden) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Evans v. Graden, 28 S.W. 439, 125 Mo. 72, 1894 Mo. LEXIS 368 (Mo. 1894).

Opinion

Black, P. J.

On the twenty-second day of May, 18.89, Col. George S. Park and James Rider & Son entered into a written contract whereby Rider & Son agreed to furnish all the material and erect for Park building at Parkville in this state, for the use of Park College. The contract provides that the building shall be a frame structure, and shall be erected according to specifications prepared by Mr. Hogg and certain other specifications prepared by Mr. Park. Park agreed to pay Rider & Son $5,800, Rider & Son “not drawing at any time over seventy per cent, of the work done, the whole work to be completed” by October 1, 1889. On the same day Rider & Son gave bond to secure the performance of the contract, with the defendant Graden and others as sureties. Rider & Son abandoned the work on September 1, 1889, so that Park was obliged to complete the building himself. The amount paid by him to Rider & Son and for completing the building, exceeds the contract price some $1,408. Park died, and the plaintiff, as his administrator, brought this suit against the defendant surety on the bond to recover the last named sum. He claims other damages for other alleged breaches of the contract, but no question is made in this court over the other alleged breaches.

The defendant, by his answer, admits the execution of the contract and bond, and then follows a general denial. For a further defense he sets up the same contract pleaded by the plaintiff, and states facts to the effect that Park, from time to time, paid Rider & Son more than seventy per cent, of the value of the work done. For $ further affirmative defense, he says Park [77]*77and Rider & Son, without his consent, changed the contract as set forth in the specifications in these several particulars, namely: First, so that the front doorway was cut down and lowered three feet; second, so that the building was to be heated by a hot air furnace instead of stoves; and third, from a tar and gravel roof to a tin roof.

At the close of the evidence the court gave four instructions at the request of the plaintiff, ten at the request of the defendant, and of its own motion contributed nineteen more, in all covering some twenty pages of printed matter. Thus enlightened as to the law, the' jury found for the defendant.

1. The liability of a surety is not to be extended beyond the terms of his contract. He is bound to the extent of his contract, but no further. He is also entitled to the benefit of the securities taken by the creditor from the principal debtor. These principles of law are applicable to sureties on these bonds given by contractors to secure the performance of their contracts for the erection of buildings. The defendant, as a surety, has a right to stand upon the agreement that Park would not pay Rider & Son during the progress of the work more than seventy per cent, of the value of the work done; and if Park, during the progress of the work, paid Rider & Son more than seventy per cent, of the value of the work done, without the consent of the sureties, he thereby discharged the defendant. Taylor v. Jeter, 23 Mo. 244; Ryan v. Morton, 65 Texas, 258; Bragg v. Shain, 49 Cal. 131. If the defendant surety consented to the overpayments, if any there were, then he is not discharged. These principles-of law are set forth in the instructions given, and we see no objection to them so far as they relate to this branch of the case.

Mr. Byers, agent for Park and a witnessforthe plaintiff, testified on direct and on cross-examination to the [78]*78following effect: That he paid Rider & Son $500 at a time until he paid them $1,500, when some misunderstanding arose and he refused to pay more; that James Rider, the defendant Graden, and another surety by the name of Paul came to see him, and upon their assurance that Rider & Son were going on with the work, he paid Rider another $500; that he paid on vouchers for material some $1,200 in addition thereto. We understand these payments were all made prior to September 1, 1889, the date at which Rider & Son abandoned the work. This witness says the framework, roof, and a large part of the plastering had been completed at that time, and he thinks the entire work was about three fourths performed. There was some other evidence having a little bearing on the same subject. We think this evidence made a case for the jury on the question whether Park made overpayments, and the question whether defendant gave his consent thereto.

2. Some of the instructions informed the jury that if there was an agreement between Park and Rider & Son, made after the execution of the bond, whereby the main doorway was to be, and was, cut down, and this agreement was contrary to the specifications, then the finding should be for the defendant. This instruction should not have been.given for this reason, among others: There was no evidence,'whatever, tending to show any change in the main entrance of the doorway. The giving of this instruction is reversible error.

3. By another instruction the court made it the duty of the jury, in passing upon an alleged change in the terms of the contract, to first “determine what the contract and specifications required as to the construction.” The ninth and more specific instruction is to this effect: If the jury find from the evidence that the contract and specifications agreed upon for the construction of the building provided for heating by [79]*79stoves, or provided for a tar and gravel roof; that after the bond was executed Park and Rider & Son made an agreement whereby the work was changed so that the building could be heated by a furnace by putting in hot air pipes, or the' roof was changed from tar and gravel to tin, all without the consent of defendant, then.the jury should find for defendant.

If changes were made in the contract after it was executed, in either of the respects mentioned in this instruction, without the consent of the defendant, then the defendant ceased to be bound as a surety on the bond. Such changes would discharge the surety, unless he gave his consent thereto. Beers v. Wolf, 116 Mo. 179. But there are several objections to these instructions. In the first place the court should have told the jury what the terms of the contract were in these respects, instead of leaving it to the jury to say whether the specifications called for hot air flues, or for a gravel roof. The specifications are in writing, and they constitute a part and parcel of the contract. It is useless to cite authorities to show that it is the duty of the court, and not of the jury, to construe written contracts.

In the next place, on turning to the specifications prepared by Mr. Hogg, we find that the roof was to be a mansard roof, the “rake” of the sides to be covered with shingles, and the deck with I. C. tin. There is not a thing in the specifications prepared by Mr. Park to modify or change this call for a tin roof. The specifications prepared by Park and made a part of the contract, contain this as the last clause: “A door may be made at the foundation at the proper place for heating the building, and the tin piping through the house at necessary places, to be in readiness for the hot air furnace.” It is, therefore, plain that the contract for the performance of which the defendant [80]*80became a surety, called for a tin roof and for hot air-flues. The issues made by the pleadings in respect to the alleged change in the roof and flues should have been instructed out of the case instead of being submitted to the jury.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State Ex Rel. Union Indemnity Co. v. Shain
66 S.W.2d 102 (Supreme Court of Missouri, 1933)
Bowman v. C. O. Jones Building Co.
58 S.W.2d 718 (Supreme Court of Missouri, 1933)
Kennedy v. Bowling
4 S.W.2d 438 (Supreme Court of Missouri, 1928)
Barton v. Title Guaranty & Surety Co.
183 S.W. 694 (Missouri Court of Appeals, 1916)
Bullard v. Norton
182 S.W. 668 (Texas Supreme Court, 1916)
City of Chicago v. Agnew
182 Ill. App. 499 (Appellate Court of Illinois, 1913)
McKnight v. Lange Mfg. Co.
155 S.W. 977 (Court of Appeals of Texas, 1913)
Roennigke v. Essig
151 S.W. 765 (Missouri Court of Appeals, 1912)
Harris v. Taylor
129 S.W. 995 (Missouri Court of Appeals, 1910)
Bartlett & Kling v. Illinois Surety Co.
119 N.W. 729 (Supreme Court of Iowa, 1909)
Litchgi v. Gottlieb
113 S.W. 1134 (Missouri Court of Appeals, 1908)
Eager v. Seeds
1908 OK 127 (Supreme Court of Oklahoma, 1908)
Martin v. Whites
106 S.W. 608 (Missouri Court of Appeals, 1907)
Reissaus v. Whites
106 S.W. 603 (Missouri Court of Appeals, 1907)
Tinsley v. Kemery
84 S.W. 993 (Missouri Court of Appeals, 1905)
Lawhon v. Toors
84 S.W. 636 (Supreme Court of Arkansas, 1905)
Wehrung v. Denham
71 P. 133 (Oregon Supreme Court, 1903)
Burnes Estate v. Fidelity & Deposit Co.
70 S.W. 518 (Missouri Court of Appeals, 1902)
Chapman v. Eneberg
68 S.W. 974 (Missouri Court of Appeals, 1902)