Bowman v. C. O. Jones Building Co.

58 S.W.2d 718, 332 Mo. 520, 1933 Mo. LEXIS 492
CourtSupreme Court of Missouri
DecidedMarch 16, 1933
StatusPublished
Cited by3 cases

This text of 58 S.W.2d 718 (Bowman v. C. O. Jones Building Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bowman v. C. O. Jones Building Co., 58 S.W.2d 718, 332 Mo. 520, 1933 Mo. LEXIS 492 (Mo. 1933).

Opinion

ATWOOD, J.

The above cause was transferred to this court by the Kansas City Court of Appeals because one of the judges therein sitting deemed the majority opinion (reported with dissenting opinion in 50 S. W. (2d) 203) contrary to certain decisions of the Supreme Court. The cause must now be determined as in case of jurisdiction obtained by ordinary appellate process. [Constitution of Missouri, Art. 6, See. 6 of Amendment adopted in 1884.]

The action is for recovery of an amount claimed to be due on account of alleged extras furnished under a plumbing and heating contract, and to establish a mechanic’s lien therefor. Yerdict and judgment went for plaintiff in the sum of $2371.99 as a lien claim and against defendants on their counter claim, from which judgment defendant C. O. Jones Building Company only has appealed.

The petition alleged existence of a contract between the parties by the terms of which plaintiff was to furnish all labor and material necessary for the complete installation of the plumbing and heating contemplated in the construction of two hotel and apartment buildings in. Kansas City, Missouri, “in accordance with certain plans and specifications submitted to said plaintiff and being and forming a part of said contract;” that the sum agreed upon for the original work designated was $37,500, said work to be done according to and under one general contract with- said defendant; “that said plans *523 and specifications incorporated by reference in said contract and ma part thereof, provided that said contracting parties, at any time dur ing the course of the construction of said work might add to or require certain additional labor, and fixtures as by them might be deemed advisable;” that certain extras were ordered by defendant, including “slop sinks, drinking fountains, connecting gas stoves, installing ice water cocks, ice water lines, and other miscellaneous items,” all of which were to be paid for at their reasonable value; that the total amount that became due and was owing to plaintiff was $40,341.88; that the sum of $37,940 had been paid, and that the balance of $2,401,88 was due plaintiff.

The answer admitted execution of the contract as alleged, stated that plaintiff had been paid in full for all work and material furnished by him, and denied other allegations of the petition. By way of further answer and counter claim it also alleged that plaintiff had breached his contract in several respects, particularly by failing to to furnish a 4-inch water pipe known as a “fire line” with proper connections and installing in lieu thereof a “dummy” line consisting of a 2-inch water pipe without connections; and by reason of the breaches pleaded defendant was damaged in the sum of $4,116. Plaintiff’s reply was in the nature of a general denial.

The points for decision on this appeal involve plaintiff’s right to recover for the installation of “slop sinks” 'shown to be of the reasonable value of $1,362.74, and defendant’s right to recover on its counter claim for the item of plaintiff’s failure to furnish the “fire line.” Appellant contends that by the terms of the contract plaintiff was bound to furnish both of these items. Respondent construes the contract to the contrary, and further contends that even if defendant had a right to require plaintiff to furnish these items under the contract, such right was subsequently waived and that the slop sinks were ordered as extras.

The “fire line” which appellant says should have been installed was not expressly called for in any of the plans and specifications. but appellant relies on a provision in the plumbing specifications, which it is conceded plaintiff received prior to submitting his proposal, stating that “all work is to be done and tested in strict accordance with the Ordinances in force in this city,” and on proof at the trial that the ordinances of Kansas City in force at the time these buildings were erected required the installation of such a fire line in the construction of buildings of that character. However, plaintiff testified that when he discussed this item with defendant’s president, C. O. Jones, Mr. Jones stated that he did not really want a fire line as he had mechanical extinguishers, but he was afraid that the building inspector would insist on putting them in, although he did not know what the regulations were as to size, but that defendant *524 “should run something up over there that I could get by the building inspector; that is all I care.” Plaintiff then said: “Shall I run a two-inch galvanized pipe up there?” Jones replied: “Yes, we ought to run them up in the first building, and if it is not all right we will have to do what the building inspector says on the next one.” There was evidence that plaintiff’s installation was in accordance with this agreement, that defendant did in fact “get by” as the work was approved by the city inspector, and plaintiff testified that he received no complaint about the fire line prior to the filing of this suit. Defendant’s counter claim as to this item was properly submitted and there was sufficient evidence to support the jury’s verdict denying same.

Appellant’s contention with respect to the item of “slop sinks” arises out of the trial court’s refusal to give a peremptory instruction in the nature of a special demurrer requested by defendant at the close of the whole case. The instruction is as follows:

“The court instructs you that as to plaintiff’s claim for $1,362.71 for work and material in respect to the item of slop-sinks mentioned in evidence the same are covered in the express written contract between plaintiff and defendant Building Company, and plaintiff is not entitled to recover therefor and you must therefore allow nothing therefor. ’ ’

Counsel for appellant say that this instruction should have been given under the familiar rule that it is the court’s duty to construe unambiguous written instruments and declare their legal effect. [Black River Lumber Co. v. Warner, 93 Mo. 374, 384, 6 S. W. 210; Evans v. Graden, 125 Mo. 72, 79, 28 S. W. 439; Ford v. Dyer, 148 Mo. 528, 541, 41 S. W. 1091.] Counsel for respondent, on the other hand, contends that this rule is not applicable because the plans and specifications were ambiguous with respect to whether or not slop sinks were required, and the question was one for the jury under all the evidence.

Plaintiff testified that the only plans and specifications he received before submitting his proposal were a typical floor and attic piping-plan marked Exhibit D, the foundation and first floor plan marked Exhibit E, and the plumbing and gas fitting specifications marked Exhibit F. According to defendant’s evidence plaintiff received a full set of plans and specifications before submitting his proposal, a part of which was a typical floor plan plainly calling for slop sinks and shown on Exhibit G.

Exhibit F, which plaintiff admits he had before him when his bid was prepared and submitted, contained this requirement: “Stop sinks too shall have separate risers with cut-offs.” The architect testified at the trial that this use of the word “stop” was a typographical error and meant “slop.” Plaintiff and a plumber *525 in his employ both testified that they did not know of any such thing as a “stop” sink.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Coffman Industries, Inc. v. Gorman-Taber Co.
521 S.W.2d 763 (Missouri Court of Appeals, 1975)
Hopkins v. Kurn
171 S.W.2d 625 (Supreme Court of Missouri, 1943)
Baker v. Sovereign Camp Woodmen of the World
116 S.W.2d 513 (Missouri Court of Appeals, 1938)

Cite This Page — Counsel Stack

Bluebook (online)
58 S.W.2d 718, 332 Mo. 520, 1933 Mo. LEXIS 492, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bowman-v-c-o-jones-building-co-mo-1933.