Eager v. Seeds

1908 OK 127, 96 P. 646, 21 Okla. 524, 1908 Okla. LEXIS 150
CourtSupreme Court of Oklahoma
DecidedJune 24, 1908
DocketNo. 2046, Okla. T.
StatusPublished
Cited by15 cases

This text of 1908 OK 127 (Eager v. Seeds) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Eager v. Seeds, 1908 OK 127, 96 P. 646, 21 Okla. 524, 1908 Okla. LEXIS 150 (Okla. 1908).

Opinion

WILLIAMS, C. J.

(after stating the facts as above). A jury having been waived and said cause tried by the court, and the issues found in favor of .the defendants in error Ward and Latta, the sureties on said bond, there being testimony reasonably tending to support the findings of the- lower court, such finding is conclusive in this court.

The plaintiffs in error, however,, insisted that there was error in rendering judgment in favor of said defendants in error, and it becomes necessary to determine whether or not, as a matter of law, under the facts found, the court erred in rendering judgment in their behalf. In the ease of Board of Commissioners of Morgan County v. Branham et al., (C. C.) 57 Fed. 180, Baker, District Judge, says:

“It is well settled that a surety is bound only by the strict terms of his engagement; and, as he assumes the burdens of the contract without sharing in its benefits, he has the right to pre *533 scribe the exact terms upon which he will enter into an obligation, and to insist upon a discharge if those terms are not observed. An innocent surety is always the subject of legal protection. State v. Gutting, 2 Ohio St. 1; Raymond v. Whitney, 5 Ohio St. 201; Hall v. Williamson’s Adm’rs, 9 Ohio St. 17. It is not a question whether he is harmed or benefited by a disregard of the of the terms to which he has assented. Miller v. Stewart, 9 Wheat. (U. S.) 681, 6 L. Ed. 189; Manufacturing Co. v. Kimmel, 87 Ind. 560; Post v. Losey, 111 Ind. 74, 12 N. E. 121, 60 Am. Rep. 677. Where, by the terms of the contract, the principal is to be paid by the debtor or obligee in installments, and the payments are made in advance of the time specified in the contract, the surety will be discharged.. Brandt, Sur. (Ed. 1878) § 102; Id. § 371. Calvert v. Dock Co., 2 Keen, 639, is a case similar to the one at bar. One Streather contracted to build certain works for the dock company, and to furnish the materials. The company was to pay the agreed price.of 52,200 pounds in installments, to wit, three-fourths of the cost of the work done to be paid for every two months, on the certificate of the company’s engineer, and the residue on the completion of the contract. Walburton and Laycock became sureties upon the bond of Streather for 'the performance of the contract. Streather entered upon work, but failed to complete it, and finally abandoned it, and suit was instituted upon the bond. Streather had been paid, from time to time, more than three-fourths of' the estimated cost of the work performed, and it was held that thereby the sureties were released. In the course of his opinion Lord Langdale, M. R., said: ‘What the company did was perhaps calculated to make it easier for Streather to complete the work, if he acted with prudence and good faith; but it tlso took away that particular sort of pressure which, by the contract, was intended to be applied to him. And the company, instead of keeping themselves in the-situation of debtors, having in their hands one-fourth of the value of the work done, became creditors tea large amount, without any security; and, under the circumstances, I think that their situation, with respect to Streather, was so far altered that his sureties must be considered to be discharged from their suretyship.’ ”

In the case of Bragg v. Shain et al., 49 Cal. 131, Chief Justice Wallace, delivering the opinion of the court, in effect held that where a contractor agrees with the owner to erect for him *534 a building and furnish the materials, and deliver the same discharged from all liens, and by the terms of the contract the owner is to pay 75 per cent, of the contract price each month as the work progresses, and the other 25 per cent, when the work is completed, and a third person becomes surety for the contractor, if the owner, during the progress' of the work, pays the contractor more than the 75 per cent., the surety is discharged from his liability.

In the case of Simonson v. Grant, 36 Minn. 439, 31 N. W. 861, the plaintiffs were sureties for the faithful performance by defendants of their building contract with their codefendant, Grant. Said plaintiffs also furnished materials used in the building erected in pursuance 'of tire contract, and claimed a lien thereon in this action. Grant’s objections against the enforcement of the lien rested on the claim that the engagements of plaintiffs as sureties estopped them from claiming any lien for materials furnished under the same contract. Plaintiffs replied that they had been released from the obligation of their bond before any materials were furnished by them. The building contract in that case contained a provision that the contractors would protect said Grant, and save him harmless from all claims and liens for labor and. materials contracted by them on said building. The contract provided that a certain installment was to be paid when all the lumber was on .the ground except siding and flooring, and the first floor laid, and the second when the building was inclosed, sheathed, shingled, and back-plastered, chimneys built, and roof painted. It further provided that so much of these payments as should be necessary to pay for materials and labor furnished should be used for that-purpose, and after the first payment, and before the others were made, said contractors should furnish Grant with a written statement from the parties furnishing the materials and labor, or other satisfactory evidence that the money paid had been so used. After the payment of the first installment according to the terms of the contract, said Grant, having discovered that the greater part *535 thereof had not been applied as required by the terms of the contract, thereupon refused to make any further payments directly, but thereafter from time to time made payments upon their orders to divers parties who had valid claims against them, and which, if not seasonably paid, might be enforced against the building by filing liens therefor in pursuance of the statute. The trial court found “ ‘that the contractors did not perform the work called for by said contract in the order provided for, and the payments made by defendant Grant were made without reference to the state of the work at the time of such payments, or conditions prescribed by said contract in respect to the progress of the work, but that said Grant made only such payments as were necessary to be nrade to protect the house from liens aforesaid/ ” and that plaintiffs had notice of such payments and of his object in making them; but it does not appear that they ever authorized or consented to any departure from the terms of the contract, or any change or modification thereo.f. Mr. Justice Van-derburgh, delivering the opinion on behalf of the court, held that said sureties were released.

In the ease of Bell et al. v. Paul, 35 Neb. 240, 52 N. W.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Durant v. Changing, Inc.
891 P.2d 628 (Court of Civil Appeals of Oklahoma, 1995)
Matteson v. James
131 Okla. 142 (Supreme Court of Oklahoma, 1928)
In Re Estate of James
1928 OK 328 (Supreme Court of Oklahoma, 1928)
Youngblood v. Rector
259 P. 579 (Supreme Court of Oklahoma, 1927)
Lena v. Patterson
1925 OK 779 (Supreme Court of Oklahoma, 1925)
Quapaw Pumping & Royalty Co. v. Camblin
232 P. 84 (Supreme Court of Oklahoma, 1925)
Shuttee v. Coalgate Grain Co.
1918 OK 246 (Supreme Court of Oklahoma, 1918)
Evatt v. Dulaney
1915 OK 580 (Supreme Court of Oklahoma, 1915)
Dolese Bros. Co. v. Chaney Rickard
1915 OK 611 (Supreme Court of Oklahoma, 1914)
Dockstader v. Gibbs
1912 OK 541 (Supreme Court of Oklahoma, 1912)
Hilsmeyer v. Blake
1912 OK 460 (Supreme Court of Oklahoma, 1912)
Kennedy v. Pawnee Trust Co.
1912 OK 133 (Supreme Court of Oklahoma, 1912)
Davis v. Smith
1911 OK 145 (Supreme Court of Oklahoma, 1911)
Lamm & Co. v. Colcord
1908 OK 216 (Supreme Court of Oklahoma, 1908)

Cite This Page — Counsel Stack

Bluebook (online)
1908 OK 127, 96 P. 646, 21 Okla. 524, 1908 Okla. LEXIS 150, Counsel Stack Legal Research, https://law.counselstack.com/opinion/eager-v-seeds-okla-1908.