Beers v. Wolf

22 S.W. 620, 116 Mo. 179, 1893 Mo. LEXIS 277
CourtSupreme Court of Missouri
DecidedMay 22, 1893
StatusPublished
Cited by46 cases

This text of 22 S.W. 620 (Beers v. Wolf) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Beers v. Wolf, 22 S.W. 620, 116 Mo. 179, 1893 Mo. LEXIS 277 (Mo. 1893).

Opinion

Black, P. J.

The plaintiff entered into a contract with the defendants, whereby they agreed to furnish all the labor and materials, and build and complete an addition to a hotel, according to the plans, elevations and specifications furnished by the superintending architect; for which the plaintiff agreed to pay them the sum of $31,070, in installments as the work progressed. The defendants, Strimple & Son, proceeded with the work until nearly completed and then abandoned it, leaving unpaid bills. The plaintiff was obliged to employ others to complete the work and to lay out money in the discharge of mechanic’s liens created by the Strimples, and hence this suit. The Strimples made no defense. Wolf, Hayden and Reitz defend on the ground that they were sureties for the Strimples and that the plaintiff and the Strimples altered and changed the terms of the contract without theirdmowledge or consent..

The contract describes the defendants as “Joab Strimples & Son, principals, and A. Wolf, T. E. Hayden and John Reitz, sureties, parties of the second part.” The agreements throughout the contract are expressed to be by and between the parties of the first [182]*182part and “the parties of the second part” until it speaks of the final payments, when it provides: “The last two payments to be paid on orders of said principal second parties, on the party of the first part, through orders of the superintendent.”

By agreement the cause was heard by a referee, who found for the plaintiff as against the Strimples.in the sum of $5,203.54; and, ás to the affirmative defense, he found that the plaintiff and the Strimples made, without the knowledge or consent of the other defendants, changes and ¿Iterations in the plans and specifications forming a part of the contract as follows :

“First. The large sliding doors provided by the plans for the dining room were omitted, and a pair of smaller sliding doors inserted in the room on the second floor used for a parlor, the smaller doors being less costly than the doors omitted.

Second. The closets in the rooms on the second floor were differently arranged, and the doors, as you enter from the old building on the third, fourth and fifth floors were changed, so as to face the opening from the old building instead of being around on the north side coming from the hall.

Third. That by reason of the bottom of the basement being lower than the sewer for the new building, a bulk-head was put in the basement to enable the plumber to connect with the sewer for said addition.^

Fourth. That flitch-plates provided for the fifth story were omitted from that story, and used in the. openings of the first story to form girders instead of lintels.

Fifth. The closets in said addition were made six inches deeper than provided for by said plans.

Sixth. The basement of said addition was made six inches deeper than provided for by said plans.

[183]*183From the evidence, the referee is unable to determine what, if any, extra costs were added to the contract price, by reason of the changes, additions and alterations specified under division first, second, third and fourth, and' hence finds the fact to be that such changes, alterations and additions, were made without adding extra cost to said contract price. The referee finds that the changes, alterations and additions named under divisions fifth and sixth, added to the contract price for the construction of said addition, the sum of $221.61, which said sum was an extra for the material and labor in doing sixty-three and eighteen one hundredths square yards of plastering at thirty-five cents per square yard, made necessary by such changes alterations and additions in and to said new addition, not originally provided for by said plans.”

As a matter of law the referee found that the sureties were discharged because of these changes and alterations. To this conclusion of law the plaintiff excepted and the exception was sustained, and the court gave judgment against all of the defendants for $4,431.

1. The first question is, did the appellants contract as principals, so as to waive' their rights ás sureties. One who is in reality a surety may contract as a principal. He may waive the rights which the law throws around a surety, for such a waiver has nothing in it offensive to the law; and the surety does waive such rights when he in terms contracts and agrees to be bound as principal. Picot v. Signiago, 22 Mo. 587; McMillan v. Parkell, 64 Mo. 286; Brandt on Surety-ship, sec. 28. But in this case the appellants did not waive their rights as sureties. They are in the beginning of the contract described as sureties, and when we come to the agreements concerning the last two payments the distinction between principal and sureties is [184]*184again shown; and there is no statement in the contract to the effect that they contract as principals. As they are described in the contract as sureties, it must appear from other parts thereof that they agreed to be bound as principals before it can be said that they waived any of their rights as sureties. The contract contains no statement to the effect that they bound themselves as principals, and they must have accorded to them all the rights of sureties.

2. It is contended on behalf of the plaintiff that the superintendent had the right to make changes in the plans and specifications without consulting the sureties. Whether he had such right or not must depend upon a proper construction of the contact. As there is a dispute as to the meaning of the contract, it may be stated here, that ,the contract of a surety must be construed like any other contract, that is to say, according to the intent of the parties. There should be no strained construction in order to release or hold the surety. The contract of the, surety is “to be construed according to what is fairly to be presumed to have been the understanding of the parties, without any strict technical nicety.” Lee v. Lick, 10 Pet. 482; Lionberger v. Krieger, 88 Mo. 160; Locke v. McVean, 33 Mich. 473. “The rules for construing the contract of a surety or a guarantor, should by no means be confounded with the rule that sureties and guarantors are favorites of the law, and have a right to stand upon the strict terms of their obligations. * * * In the construction of the contract of a surety or guarantor, as well as of every other contract, the true question is: What was the intention of the parties, as disclosed by the instrument read in the light" of the surrounding circumstances? * * * The meaning of the words is not affected by the fact that the party sought to be [185]*185charged is principal, surety or guarantor.” Brandt on Suretyship [1 Ed.], sec. 80.

Guided by these principles we come to the contract, which contains the following stipulations: “The superintendent shall be at liberty to make any deviation from, or alteration in, the plan, form, construction, detail and execution, described by the drawings and specifications without invalidating or rendering void this contract, and in case of any difference in the expense, an addition to or abatement from the contract price shall be made, and the same shall be determined by the architect.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Employers Mutual Casualty Co. v. United Fire & Casualty Co.
682 N.W.2d 452 (Court of Appeals of Iowa, 2004)
Caron v. Andrew
284 P.2d 544 (California Court of Appeal, 1955)
Finch v. Heeb
107 S.W.2d 962 (Missouri Court of Appeals, 1937)
Maryland Casualty Co. v. City of South Norfolk
54 F.2d 1032 (Fourth Circuit, 1932)
Little v. Fidelity & Deposit Co. of Maryland
3 Tenn. App. 157 (Court of Appeals of Tennessee, 1926)
National Union Fire Insurance v. Nevils
274 S.W. 503 (Missouri Court of Appeals, 1925)
Missouri, Kansas & Texas Railway Co. v. American Surety Co.
236 S.W. 657 (Supreme Court of Missouri, 1921)
Cowles v. J. C. Mardis Co.
192 Iowa 890 (Supreme Court of Iowa, 1921)
First Congregational Church of Christ v. Lowrey
165 P. 440 (California Supreme Court, 1917)
Evans v. United States Fidelity & Guarantee Co.
192 S.W. 112 (Missouri Court of Appeals, 1917)
National Surety Co. v. Haley
159 P. 292 (Supreme Court of Oklahoma, 1916)
Barton v. Title Guaranty & Surety Co.
183 S.W. 694 (Missouri Court of Appeals, 1916)
Myers v. Chesley
177 S.W. 326 (Missouri Court of Appeals, 1915)
Neuwirth v. Moydell
174 S.W. 206 (Missouri Court of Appeals, 1915)
Jackson Exchange Bank v. Russell
164 S.W. 694 (Missouri Court of Appeals, 1914)
P. H. Rea Implement Co. v. Smith
151 S.W. 203 (Missouri Court of Appeals, 1912)
Stephenson v. Joplin State Bank
141 S.W. 691 (Missouri Court of Appeals, 1911)
Utterson v. Elmore
136 S.W. 9 (Missouri Court of Appeals, 1911)

Cite This Page — Counsel Stack

Bluebook (online)
22 S.W. 620, 116 Mo. 179, 1893 Mo. LEXIS 277, Counsel Stack Legal Research, https://law.counselstack.com/opinion/beers-v-wolf-mo-1893.