Employers Mutual Casualty Co. v. United Fire & Casualty Co.

682 N.W.2d 452, 2004 Iowa App. LEXIS 239, 2004 WL 239909
CourtCourt of Appeals of Iowa
DecidedFebruary 11, 2004
Docket03-0489
StatusPublished
Cited by7 cases

This text of 682 N.W.2d 452 (Employers Mutual Casualty Co. v. United Fire & Casualty Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Employers Mutual Casualty Co. v. United Fire & Casualty Co., 682 N.W.2d 452, 2004 Iowa App. LEXIS 239, 2004 WL 239909 (iowactapp 2004).

Opinion

MAHAN, J.

I. Background Facts & Proceedings

Employers Mutual Casualty Company (EMC) hired Neumann-Kiewit Constructors (Neumann) as the general contractors to construct a high-rise, the EMC Building, in Des Moines, Iowa. Neumann subcontracted with Keith Janning’s Terrazzo & Tile, Inc. (Janning) to install terrazzo on the first two floors, of the building for the price of $147,864. 1 The contract provided Janning was required to furnish a performance and payment bond in the amount of the contract price.

Janning obtained a performance and payment bond from United Fire .& Casualty Company (United Fire) in the amount of $147,864. Janning installed the terrazzo, but it was of substandard quality. Neumann filed suit against Janning and United Fire, as its surety. The parties discussed whether the floor should be entirely replaced or could possibly be repaired.' Janning and United Fire offered the services of DH & Associates (DH) to repair, the terrazzo. DH inspected the floor in August and November 2000, and thought the problem could be fixed.

On February 9, 2001, the parties entered into the “Mutual Releases and Settlement Agreement,” which provided Neu-mann would dismiss its lawsuit. 2 The settlement agreement specified that DH would be retained • under a contract with Janning and United Fire to repair the terrazzo and replace certain panels “to a commercially reasonable finish.” DH was to begin work within 120 days after Neu-mann dismissed its lawsuit. The parties agreed, “Any dispute involving the scope of work or what constitutes a commercially reasonable finish will be resolved by an independent expert to be agreed upon by the parties.” Neumann’s suit was dismissed on March 26, 2001.

Janning and United Fire entered into a contract with DH to repair the terrazzo for $68,389. No provision was made to replace certain panels which had been removed for testing. EMC required an independent expert .to be selected before it would allow DH to begin work. United Fire agreed to the selection of an expert, *454 but pointed out that an expert was not required under the terms of the settlement agreement, because there was at that time no “dispute involving the scope of work or what constitutes a commercially reasonable finish.” The parties agreed upon FEH Associates, Inc. (FEH) to act-as an independent expert.

DH appeared at the EMC Building on July 7, 2001, with the intention of beginning the repair process. EMC employee Donald Klemmé took David Hulee of DH oh a tour or survey of the damage to the terrazzo. . Hulee did not make any repairs because he determined the first floor had deteriorated since he had previously inspected it, and the cost to repair the floor had increased to the point where it would be more effective to replace the floor. DH remained willing to do the work on the second floor. United Fire sought to involve the independent expert, FEH, but EMC would not agree to this procedure.

EMC filed suit against United Fire for breach of contract due to DH’s failure to repair or replace the terrazzo as required by the settlement agreement. United Fire claimed: (1) the parties were mutually mistaken' about DH’s ability to do the work; (2) EMC breached the contract first; (3) if United Fire did breach the contract, this was due to a legal excuse; and (4) its damages should be limited to $147,864, the amount of the bond agreement.

The district court determined that under the settlement agreement United Fire and Janning were jointly liable to provide EMC with a terrazzo floor with a “commercially reasonable finish.” The court found United Fire breached the contract, and it failed to prove any of its defenses. The court determined the total cost of repair and replacement was $847,390, and United Fire should be liable for this amount. United Fire appeals.

II. Standard of Review

Our scope of review in this action is for the correction of errors at law. Iowa R.App. P. 6.4. The findings of fact in a law action are binding upon us if they are supported by substantial evidence. Iowa R.App. P. 6.14(6)(a). Evidence is substantial if a reasonable mind would accept it as adequate to reach the same findings. Frontier Props. Corp. v. Swanberg, 488 N.W.2d 146, 147 (Iowa 1992).

III. Mutual Mistake

United Fire claims the settlement agreement is not enforceable because the parties made a mutual mistake regarding DH’s ability to repair the terrazzo. It asserts that at the time of the settlement agreement the parties believed the terrazzo was “very fixable” and that DH was willing to perform the required repair work.

For a contract to be valid, the parties must express mutual assent to the terms of the contract. Heartland Express, Inc. v. Terry, 631 N.W.2d 260, 268 (Iowa 2001). If there is a misunderstanding as to the object of the agreement, no meeting of the mind occurs, and there is no contract. Schaer v. Webster County, 644 N.W.2d 327, 338 (Iowa 2002). The misunderstanding must be reasonable under the circumstances of the case. Id. A unilateral mistake by one party will not release that party from its obligations under the contract. State v. Unisys Corp., 637 N.W.2d 142, 150 (Iowa 2001).

The language of the settlement agreement shows the parties did not believe the problems with the terrazzo could be completely fixed by repair work alone. The agreement provided DH would engage in “replacement of panels where samples removed ....” In addition:

*455 It is understood that DH may subcontract out certain work; that is, the replacement of the panels where samples were taken out of the first and second floor, and any other panels that are deemed necessary to replace in order to achieve the commercially reasonable finish as provided herein.

We conclude the district court did not err by ruling United Fire had failed to show the contract was unenforceable due to mutual mistake.

TV. Breach of Contract by EMC

United Fire contends EMC is not entitled to relief because it failed to perform under the terms of the contract. A party who seeks recovery on a contract has the burden to plead and prove the contract and its performance. Roland A Wilson & Assocs. v. Forty-O-Grand Corp., 246 N.W.2d 922, 925 (Iowa 1976) (citing Heaberlin v. Heaberlin, 255 Iowa 403, 406-07, 122 N.W.2d 841, 843 (1963)).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bruhn Farms Joint Venture v. Fireman's Fund Insurance
103 F. Supp. 3d 968 (N.D. Iowa, 2015)
Ryko Manufacturing Co. v. NATIONWIDE WASH SYSTEMS, INC.
736 F. Supp. 2d 1226 (S.D. Iowa, 2010)
North Dakota State Hospital v. C.A.H.
2010 ND 131 (North Dakota Supreme Court, 2010)
United States v. Schilling
454 F. Supp. 2d 831 (N.D. Iowa, 2006)
Wells Fargo v. LMT Fette
Eighth Circuit, 2004

Cite This Page — Counsel Stack

Bluebook (online)
682 N.W.2d 452, 2004 Iowa App. LEXIS 239, 2004 WL 239909, Counsel Stack Legal Research, https://law.counselstack.com/opinion/employers-mutual-casualty-co-v-united-fire-casualty-co-iowactapp-2004.