United States Fidelity & Guaranty Co. v. Zidell-Steinberg Co.

51 P.2d 687, 50 P.2d 584, 151 Or. 538, 1935 Ore. LEXIS 40
CourtOregon Supreme Court
DecidedSeptember 6, 1935
StatusPublished
Cited by8 cases

This text of 51 P.2d 687 (United States Fidelity & Guaranty Co. v. Zidell-Steinberg Co.) is published on Counsel Stack Legal Research, covering Oregon Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Fidelity & Guaranty Co. v. Zidell-Steinberg Co., 51 P.2d 687, 50 P.2d 584, 151 Or. 538, 1935 Ore. LEXIS 40 (Or. 1935).

Opinions

KELLY, J.

This is a suit to determine amount of plaintiff’s liability upon a contractors’ bond and to enjoin the prosecution of actions at law thereon by certain of the contractors’ creditors. From a decree requiring certain defendants to refund payments made by plaintiff to them and ordering the alleged balance due on said bond to be distributed pro rata among the contractors’ creditors, the plaintiff and the defendants, The Texas Company, H. J. Nelson and State of Oregon ex rel. Howard-Cooper Corporation, cross-complainant, appeal.

On December 27, 1932, the State of Oregon, acting by and through the State Highway Commission, entered into a contract with F. C. Feldschau and Art Feldschau *541 doing business as Feldschau & Son, who for brevity will be referred to as the contractors, by the terms of which contract the contractors were to furnish approximately 5,000 yards of crushed rock to surface a portion of the state highway system known as the Jack Horner CreekMohler Section of the Oregon Coast highway in Clatsop and Tillamook counties, said contract being designated as Oregon State Highway Contract No. 1455.

On January 3, 1933, the contractors and the plaintiff, the United States Fidelity and Guaranty Company, a corporation, executed a contractors’ bond to secure the performance of said contract and the payment of laborers and materialmen as provided by statute in the penal sum of $5,475, being the amount estimated to complete the contract.

During the month of June, 1933, the contractors became financially embarrassed and the work on the contract stopped. On or about July 4; 1933, further credit was refused them by certain of their creditors, among whom were The Texas Company and H. J. Nelson. This situation was made known to plaintiff by the contractors and by some of the creditors.

On July 13, 1933, the following letter was transmitted to H. J. Nelson and The Texas Company, to wit:

“July 13th, 1933.
Mr. H. J. Nelson,
The Texas Co.,
Tillamook, Oregon. Re Feldschau & Son account.
Dear Sir:
In connection with the above captioned account for gasoline and oil used on contract No. 1455, known as the Jack Horner Creek-Mohler Job, I wish to advise you that F. C. Feldschau & Son were bonded on this job by .the United States Fidelity & Guaranty Company. *542 The surety Company is responsible with the assured on this Job and all bills incurred under this Contract No. 1455 will be paid by either Feldsehau & Son or by the Surety Company as soon as the job is done.
Very truly yours
United States Fidelity & Guaranty Company
By ........................................
Victor L. White
Attorney-in-Faet.
VLW :IJ
Copy to Mr. Nason.”

As to Mr. White’s authority to write the foregoing letter for plaintiff, Mr. White testified that Mr. Nason, who was then the plaintiff’s superintendent of claims, authorized him to write it, in fact, dictated the letter to Mr. White over the telephone. A carbon copy of the following letter was introduced by plaintiff:

“July 14, 1933
Mr. Henry C. Hones, Supt.,
Surety Claim Department,
Home Office,
58288-12-322-32- F. C. Feldsehau - State of Oregon
Local S-1534

Our principal came in with our agent, Mr. WTiite of Tillamook, and reported himself in trouble.

The contract was for crushing some 5000 cubic yards of road surfacing material and delivering to stock piles. His prices were:

For y2 inch minus - - 85^ per cu. yd.) In Bunkers ” % inch minus -- 80# ” ” ” )
10 per yard - mile for hauling

He has been fiddling along getting out his rock at the rate of some 10 yards an hour. He has out some 3000 yards. His equipment is all rented except 4 old trucks that he owns and with which he is doing the hauling. The rock is hard and breaks out of the quarry in large pieces and so has to be worked over by again blasting or by hand work. The job is an emergency *543 relief job and requires hand labor getting the rock into the crusher.

It is obvious from his small out-put, the smallsizéd material the nature of the rock, and the hand-labor requirement that his price is ridiculously low.

The contract price was $5,475.00
Extras 400.00 $5,875.00
He has had estimates amounting to 2,066.00
Balance to earn $3,809.00

He now has outstanding bills against the job amounting to approximately $5500. He estimates Ms cost to complete at $1500. This makes a charge of $7,000 with $3800 to earn, - a deficit of $3,200. It will run Mgher, first, because we never at this stage have all the bills, and, second, because his estimate for completion is too low. It has cost him some $2.50 a yard so far, and yet he thinks he can get out the remaining 2000 yards for 75‡. He can’t, although it shouldn’t cost as much as the former, because he now has a good part of the rock blasted down.

He had not cashed the last estimate of $1056, so we had him turn it over to Mr. White who will pay labor and keep the job going. (This amount is deducted from the outstanding bills.)

He should be done in 20 to 25 days. Then we will have the íness to clean up.

I suggest a reserve of $4,000.

I have not been able to ascertain anytMng definite on salvaging possibilities. He has another crushing plant, four trucks referred to above, and has listed some real estate, which I understand is in Ms wife’s name.

The present necessity was to get the job started again - - he had shut down the last of June - -, thus get the State off our backs, and get the job completed without having to let the State take it .over or take it oyer ourselves. With only 2000 yards to make it is too small to re-let except at excessive cost. We have accom *544 plished this. He started up yesterday after White had paid some of the men, and assured the gasoline dealer that his bill would ultimately be paid.

I have got to go over on the I. L. Young job (H. O. claim 194633) next week and after I get back I will go over as soon as necessary and cheek this one out.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State ex rel. Beckett v. Stockett
552 P.2d 838 (Court of Appeals of Oregon, 1976)
Crouch v. Pixler
320 P.2d 943 (Arizona Supreme Court, 1958)
Caron v. Andrew
284 P.2d 544 (California Court of Appeal, 1955)
Paulsell v. Peters
115 P.2d 708 (Washington Supreme Court, 1941)
Maryland Casualty Co. v. Alford
111 F.2d 388 (Tenth Circuit, 1940)
Wilson v. State Industrial Accident Commission
94 P.2d 129 (Oregon Supreme Court, 1939)
Rust v. Pratt
72 P.2d 533 (Oregon Supreme Court, 1937)

Cite This Page — Counsel Stack

Bluebook (online)
51 P.2d 687, 50 P.2d 584, 151 Or. 538, 1935 Ore. LEXIS 40, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-fidelity-guaranty-co-v-zidell-steinberg-co-or-1935.