School District No. 30 v. Alameda Construction Co.

169 P. 507, 87 Or. 132, 1917 Ore. LEXIS 188
CourtOregon Supreme Court
DecidedDecember 27, 1917
StatusPublished
Cited by18 cases

This text of 169 P. 507 (School District No. 30 v. Alameda Construction Co.) is published on Counsel Stack Legal Research, covering Oregon Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
School District No. 30 v. Alameda Construction Co., 169 P. 507, 87 Or. 132, 1917 Ore. LEXIS 188 (Or. 1917).

Opinion

Mr. Justice Burnett

delivered the opinion of the court.

The bond in question was given under the provisions of Chapter 27 of the Laws of 1913, p. 59, amending Section 6266, L. O. L., so as to read as follows in part:

“Hereafter any person or persons, firm or corporation, entering into a formal contract with the State of Oregon, or any municipality, county, or school district within said state, for the construction of any buildings, or the prosecution and completion of any work, or for repairs upon any building or work, shall be required before commencing such work, to execute the usual penal bond with good and sufficient sureties, with the additional obligations that such contractor or contractors shall promptly make payments to all persons supplying him or them labor or materials for any prosecution of the work provided for in such contracts. ’ ’

1, 2. The same section provides that any person supplying labor or materials shall have a right of action and shall be authorized to bring suit in the name of the State of Oregon or any county, municipality or school [138]*138district within such state for his use and benefit against the contractor and his sureties and to prosecute the same to final judgment and execution. By these excerpts from the pleadings we are taught that the execution of the bond and contract as stated in the fifth allegation of the complaint are admitted. It is true the answer denies that the Surety Company agreed to pay anyone except the School District, but the statute above named must be read as part of the undertaking because the latter instrument was made to fulfill the requirements of that law. By the execution of the bond and its delivery, the Surety Company created a situation in which it would be compelled to pay materialmen for material furnished and not paid for by the contractor. In other words, the effect of this contract is an express agreement of the Surety Company to pay such claims not liquidated by the contractor and not only so, but to make payments directly to the materialmen. In this view of the case, the denial mentioned is sham in effect, so that averment No-. V of the complaint stands uncontroverted, leaving the only contest to be waged over the matter of furnishing the material. It is true that the corporate character of the relator was denied on information and belief, but no notice seems to have been taken of that in the trial and no error is predicated concerning it.

3. The bond has a double obligatory aspect. As to the School District, it is the usual penal undertaking ordinarily required between owners and builders; but it operates equally in favor of those who furnish labor or materials, for the statute imposes upon the surety

“the additional obligations that such contractor or contractors shall promptly make payments to all persons supplying him or them labor or materials for any [139]*139prosecution of the work provided for under such contracts. ’ ’

This latter stipulation of the bond, therefore, is for the benefit of the materialman or laborer and is not affected by breaches of other terms of the contract, committed by other parties. As stated in the syllabus to Kansas City ex rel. v. Schroeder, 196 Mo. 281 (93 S. W. 405):

“The contract between the materialmen and the contractor is independent of the contract between the city and the contractor; therefore, the relief to which the materialmen are entitled does not depend upon the validity of the contract between the city and the contractor.”

Unless, therefore, the relator was a party to the breach of the main contract between the School District and the contractor its rights cannot be prejudiced by any act of either of the other stipulating parties. There is no charge of the kind against the relator. By the terms of the enactment it is entitled to bring an action on the undertaking for its own benefit and to pursue the same even to judgment and execution independent of the School District except the mere use of its name. It is stated in United States v. National Surety Co., 92 Fed. 549 (34 C. C. A. 526), that:

“The two agreements which the bond contains, the one for the benefit of the government and the one for the benefit of third persons, are as distinct as if they were contained in separate instruments, the government’s name being used as obligee in the latter agreement merely as a matter of convenience. In view of these considerations, we are of the-opinion that the sureties in a bond, executed under the act now in question, cannot claim exemption from liability to persons who have supplied labor or material to their principal to enable him to execute his contract with the United States, simply because the government and the [140]*140contractor, without the surety’s knowledge, had made some changes in the contract, subsequent to the execution of the bond given to secure its performance which do not alter the general character of the Avork contemplated by the contract or the general character of the materials which are necessary for its execution ' When the government has executed the contract and taken and approved the bond, it ceases to be the agent of third parties whom the contractor employs in the execution of the work or from whom he obtains materials and the rights of such persons under the bond are unaffected by subsequent transactions between the government and the contractor”: Griffith v. Rundle, 23 Wash. 453 (63 Pac. 199, 55 L. R. A. 381); Conn v. State, 125 Ind. 514 (25 N. E. 443).

All the allegations of the answer, therefore, respecting a change in the contract after its execution and delivery and of other violations not attributed to the relator may well be disregarded as affecting the right of the plaintiff to recover in this action. Indeed, passing the denial on information and belief of the corporate existence of the relator, all that was incumbent upon it in the trial of the case was to prove its allegation about furnishing material and the failure of the contractor to pay for the same.

4. The Surety Company offered to show at the trial substantially this state of facts: The architect who had prepared the plans and specifications for the building and who was acting as the agent of the School District prepared a form of contract in Portland which was signed by the contractor in triplicate and by it taken to the Surety Company to whom it applied for the bond. The company executed the bond and gave it to the contractor to be delivered to the School District. The officers of the contractor then went to Warrenton with the bond and the contract in triplicate signed by [141]*141itself and tendered the papers to the School District. The officers of the district then made some material changes in the contract increasing the obligation of the contractor without the knowledge of the Surety Company and signed the contract thus altered and retained the bond. The Circuit Court denied the Surety Company the right to show this state of facts under the pleadings as framed. This ruling was correct for the reason that the allegation was to the effect that the alterations were made after the execution of the contract, whereas the offer of proof was to show a change before the contract was executed. The allegations and the proof did not correspond.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Railton v. Redmar
304 P.2d 408 (Oregon Supreme Court, 1956)
Farris v. Pendleton
284 P.2d 362 (Oregon Supreme Court, 1955)
Lyon v. Mazeris
132 P.2d 982 (Oregon Supreme Court, 1942)
Glickman v. Solomon
12 P.2d 1017 (Oregon Supreme Court, 1932)
Hooton v. Jarman Chevrolet Co.
296 P. 36 (Oregon Supreme Court, 1931)
Hill v. Hill Et Ux.
270 P. 911 (Oregon Supreme Court, 1928)
Southern Surety Co. v. Chambers
154 N.E. 786 (Ohio Supreme Court, 1926)
State v. Way
251 P. 761 (Oregon Supreme Court, 1926)
Philip Carey Co. v. Maryland Casualty Co.
206 N.W. 808 (Supreme Court of Iowa, 1926)
American Surety Co. v. State ex rel. HUMFELD
299 F. 357 (Ninth Circuit, 1924)
American Central Insurance v. Weller
212 P. 803 (Oregon Supreme Court, 1923)
Leadbetter v. Price
199 P. 633 (Oregon Supreme Court, 1921)
Clatsop County v. Fidelity & Deposit Co.
189 P. 207 (Oregon Supreme Court, 1920)
Ogilvie v. Stackland
179 P. 669 (Oregon Supreme Court, 1919)
Multnomah County v. United States Fidelity & Guaranty Co.
170 P. 525 (Oregon Supreme Court, 1918)

Cite This Page — Counsel Stack

Bluebook (online)
169 P. 507, 87 Or. 132, 1917 Ore. LEXIS 188, Counsel Stack Legal Research, https://law.counselstack.com/opinion/school-district-no-30-v-alameda-construction-co-or-1917.