United States, ex rel. Fidelity Nat. Bank v. Rundle

100 F. 400, 40 C.C.A. 450, 1900 U.S. App. LEXIS 4270
Court of Appeals for the Ninth Circuit·Decided February 5, 1900·No. No. 557·Published·Cited by 29 cases

Opinion

BOSS, Circuit Judge.

An act of congress approved August 13, 1894, entitled “An act for the protection of persons furnishing materials and labor for the construction of public works,” provided that thereafter “any person or persons entering into a formal contract with the United States for the construction of any public building, or the prosecution and completion of any public work or for repairs upon any public building or public work, shall be required before commencing such work to execute the usual penal bond, with good and sufficient sureties, with the additional -obligations that such contractor or contractors shall promptly make payments to all persons supplying him or them labor and materials in the prosecution of the work provided for in such contract; and any person or persons making application therefor, and furnishing affidavit to the department under the direction of which said work is being, or has been, prosecuted, that labor or materials for the prosecution of such work has been supplied by him or them, and payment for which has not been made, shall be furnished with a certified copy of said contract [401] and bond, upon which said person or persons supplying such labor and materials shall have a right of action, and'shall be authorized to bring suit in the name of the United States for his or their use and benefit against said contractor and sureties and to prosecute the same to final judgment and execution: provided, that such action and its prosecution shall involve the United States in no expense”; and with the further provision that the court in which such action is brought may require further security for costs in case the judgment goes for the defendant. 28 Stat. 278. On the 1st day of July, 1897, N. B. Bundle entered into a contract with the United States for the erection of certain buildings upon the army post grounds near Spokane, Wash., and, pursuant to the above statute, executed a bond to the United States in the penal sum of $10,000, with D. W. Henley and F. E. Snodgrass as sureties, conditioned that, if the principal “shall and will in all respects duly and fully observe and perform all and singular the covenants, conditions, and agreements in and by said contract agreed and covenanted by said N. B. Bundle to be observed and performed, according to the true intent and meaning of the said contract, and as well during any period of extension of said contract that may be granted on the part of the United States as during the original term of the same, and shall promptly make full payments to all persons supplying him labor or material in the prosecution of the work provided for in said contract,” then the obligation to be void; otherwise, to remain in full force and virtue. The present action was brought in the court below upon this bond by the Fidelity National Bank, in the name of the United States, against Bundle as principal and Henley and Snodgrass as sureties, upon claims for labor and material furnished to said Bundle, of which the bank alleged in its complaint i t had become the owner by purchase and assignment. During the progress of the work by Bundle, and while the buildings were but partially completed, the government, in the exercise of a right reserved in the contract, took the work out of his hands, and upon the same day notified the sureties of its action. With the consent of the government, the sureties at once took up the work so contracted for, and upon its completion by them the government accepted it as full performance of the contract. Bundle made no defense to the action, and the plaintiff took judgment against him by default for the full amount claimed in its complaint. The sureties resisted the plaintiff’s claim on three grounds: First, that the facts alleged in the complaint do not constitute a cause of action in favor of the plaintiff against them; second, that by agreement between Bundle and the bank the latter, as the holder of the claims sued upon, had so extended the time of payment thereof, without the knowledge of the sureties, as to discharge them from their obligation to pay the same; and, third, that in the completion of the contract work from the point where Bundle left it they necessarily expended, not only the full amount received from the government (being the balance of the contract price unpaid when Bundle left off and the sureties assumed the work), but beyond and in excess thereof more than the amount of the penalty of the bond. The two last-mentioned de[402] fenses were pleaded in tbe answer of tbe sureties. Upon tbe com elusion of tbe evidence tbe court below instructed tbe jury, among other things, to tbe effect that the bond sued upon was of a dual character, creating a liability to the government, and also to those who should furnish the principal in the bond with labor or material, but that the full extent of the liability assumed by the sureties was the sum of $10,000; that the obligation to the government was paramount to that to the creditors of Bundle, and that, therefore, if the full amount of the penalty was exhausted in satisfying the demand of th.e government, it would release and absolve the sureties from any obligation to the creditors; that when the contract was taken out of the hands of Bundle the sureties stood obligated to the United States to see the work contracted for completed, or pay $10,000, and that they had the right to complete the contract, which their principal had failed to do; and that, if the evidence satisfied the jury that in completing the contract the sureties necessarily expended all the money which they received from the government, and, in addition to that, a sum exceeding the amount named as the penalty of the bond, their liability thereon was fully exhausted, and the verdict should be for the defendants. To the giving of this instruction the plaintiff duly excepted, which exception was allowed by the court; and the court refused to give, at the request of the plaintiff, instructions to the effect that neither of the affirmative defenses set up in the answer constituted any valid defense to the action, to which the plaintiff'also excepted.

Free access — add to your briefcase to read the full text and ask questions with AI

United States, ex rel. Fidelity Nat. Bank v. Rundle, 100 F. 400, 40 C.C.A. 450, 1900 U.S. App. LEXIS 4270 (9th Cir. 1900).

100 F. 400 (United States, ex rel. Fidelity Nat. Bank v. Rundle) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Dysart Corp. v. Seaboard Surety Co.
688 A.2d 306 (Supreme Court of Connecticut, 1997)
National State Bank of Newark v. Terminal Const. Corp.
217 F. Supp. 341 (D. New Jersey, 1963)
In re the Probate of the Will of Konas
9 Misc. 2d 319 (New York Surrogate's Court, 1957)
United States Ex Rel. Sherman v. Carter Constr. Co.
353 U.S. 210 (Supreme Court, 1957)
United States v. Conn
19 F.R.D. 274 (E.D. South Carolina, 1956)
Feutz v. Massachusetts Bonding & Ins.
85 F. Supp. 418 (E.D. Missouri, 1949)
United States Fidelity & Guaranty Co. v. Yeilding Bros.
143 So. 176 (Supreme Court of Alabama, 1932)
Karsh v. Fidelity Union Casualty Co.
6 P.2d 980 (California Court of Appeal, 1932)
New York Indemnity Co. v. Niven
133 So. 261 (Supreme Court of Alabama, 1931)
Independence Trust Co. v. Porter & Boyd, Inc.
132 S.E. 806 (Supreme Court of North Carolina, 1926)
Commonwealth v. Market Warehouse Co.
146 N.E. 29 (Massachusetts Supreme Judicial Court, 1925)
Columbia County v. Consolidated Contract Co.
163 P. 438 (Oregon Supreme Court, 1917)
United States v. Fabian
8 P.R. Fed. 406 (D. Puerto Rico, 1916)