Neuwirth v. Moydell

174 S.W. 206, 188 Mo. App. 467, 1915 Mo. App. LEXIS 101
CourtMissouri Court of Appeals
DecidedMarch 2, 1915
StatusPublished
Cited by2 cases

This text of 174 S.W. 206 (Neuwirth v. Moydell) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Neuwirth v. Moydell, 174 S.W. 206, 188 Mo. App. 467, 1915 Mo. App. LEXIS 101 (Mo. Ct. App. 1915).

Opinion

NORTÓNI, J.

This is a suit against the sureties alone on a builder’s bond, for damages accrued through a breach of the building contract. Plaintiffs recovered and defendants prosecute the appeal.

Plaintiff Ladislaus Neuwirth is the pastor and his coplaintiffs are trustees of the Roman Catholic Slovak Church of the Holy Trinity in, St. Louis, and defendants,- Moydell and Piskulic, are sureties on the contractor’s bond. It appears that the church, desiring to erect a parish school building on the south side of [473]*473Rutger street, between Eleventh and Thirteenth streets, contracted with Stephen Harik, a builder, to furnish •the materials and construct the building, for the consideration of $6000. The contract was entered into on the first day of June, 1910, and the bond in suit was executed by Harik, as principal, together with the two defendants, as sureties, in the penal sum of $3000, contemporaneously therewith. Harik failed to complete the building and the plaintiffs were required to pay out something more than $1000 in excess of the contract price in discharge of lien claims against it. This suit proceeds against the sureties to compensate the loss entailed through the default of Harik, the builder.

Among other things, the building contract makes the plans and specifications for the building parcel thereof, and the bond is conditioned for the faithful performance of the contract. Defendants, in their answer, set forth numerous changes and alterations in the construction of the building, which were made without regard to the provisions of the contract and at variance from' the specifications, without their knowledge or consent, and assert that they are discharged as sureties because of these. It is entirely clear that,' while all of the matters and things set forth in the answer as changes going to destroy the identity of the contract may not be regarded as such, others do so. All of those changes are detailed in,plaintiff’s evidence and stand conceded in the case, in that the parish priest, Reverend Ladislaus Neuwirth, who, it appears, was the active agent of plaintiffs, frankly testified to each.

The building contemplated is a two-story-and-basement brick school building, and the contract includes, too, the repair of certain sidewalks about it. It appears that, while the building was in course of construction, a city inspector interposed an objection to the sufficiency of one of the walls. Because of this, plaintiff entered into a new and independent contract with Harik, the builder, to erect a fire wall adjacent [474]*474to the old church building for the sum of fifty-six dollars, which was paid. This fire wall was not mentioned in the plans and specifications nor stipulated for in the original building contract.

Then, too, the plans and specifications called for plastered ceilings in the school building, and it appears the contractor put in two of the classrooms downstairs corrugated iron ceilings instead. However, he did this voluntarily and without any agreement or request from plaintiffs to do so.

The plans and specifications required the builder, Harik, to repair the old sidewalk and such was parcel of the contract; but, instead, after the work was in progress, plaintiffs entered into a new agreement with Harik, whereby a concrete sidewalk was substituted, at the agreed price of $125', which was paid. Touching this matter, Father Neuwirth testified: “Instead of having the sidewalk repaired, I had the brick sidewalk torn up and had a granitoid sidewalk made.”

Another change in the terms of the original contract, made by agreement between plaintiffs and the builder, pertains to the lathing of a partition on the first floor of the building. Concerning this the parish priest testifies as follows: “On the north side of that hall between it and the classrooms is a partition. This partition was made fireproof with metal lath and studding. . According tp the specifications that was to be ordinary wooden studding and plastering and wooden laths. Mr. Harik didn’t pay for the change in that partition; I paid for it. The money was received by one of the old-time parishioners who did the work; Harik’s plasterers did the plastering and Harik’s car-' penters put in the partition and lath. The metal lath and metal studding for that partition were furnished by John Nitka, a parishioner. I paid seventy-five dollars for the metal laths and studding.” It appears from this that plaintiffs substituted the metal lath and studding at an expense of seventy-five dollars, with the [475]*475consent of the contractor, whose workmen pnt in the studding and lath so furnished.

On the second floor of the building a partition was changed—that is, moved eastward about three feet— and thus-varied from the specifications, in order to make the room on the second floor at the head of the stairs larger. In this connection, also, a double door called for in the specifications between a large room called a hall and a room at the head of the stairs was changed to a single door of the same shape as the small doors downstairs. These changes plaintiffs says were done by agreement with the builder and at a cost of five dollars.

In the original plans a door was designed on the first floor, opening into the back of the church, but when the fire wall was constructed, a change was made with respect to this. However, no charge was made for this change.

Father Neuwirth also testifies that two doors were put in, one upstairs and one downstairs, different from those mentioned in the specifications, and “ Harik charged eight dollars for changing or constructing each of these doors. I paid him for it. . . . One of these doors is entering from a room to the classroom. The other door opened from the lower classroom to the yard on the east side of the building, so that in case the fire would come, that the children could go out fast enough to save their lives.”

The building contract provided in substance that the superintendent shall be at liberty to make any deviations from or alteration in the plan and construction of the building; but this provision is limited by another in the bond executed by the sureties.

The condition of the bond is as follows:

“The condition of the above obligation is such, that, whereas, the said Stephen Harik has on the day of the date of these presents executed and entered into a certain contract for the erection of certain build[476]*476ings in said contract described, which contract is hereto annexed. Now, if the said Stephen tlarik shall well and trnely perform and fulfill all and every the covenants, conditions, stipulations and agreements in said contract mentioned to be performed and fulfilled, and any alterations and additions in said contract, provided such alterations and additions, if any such be made, shall not exceed in extra costs the sum of eight and 00-100 dollars ($8).
“We, the said sureties, hereby expressly waiving all rights to be notified of, or by any further act to give our assent to, such alterations and additions and acknowledging ourselves to be bound unconditionally for the faithful performance of said contract price and of such alterations and additions within limit of said contract price and of such extra costs aforesaid, and shall keep the said Rev. Ladislaus Neuwirth, pastor, and John Palubiak, Andró Spavor and J. P.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

O'Neil Engineering Co. v. City of Lehigh
1919 OK 151 (Supreme Court of Oklahoma, 1919)
National Surety Co. v. Haley
159 P. 292 (Supreme Court of Oklahoma, 1916)

Cite This Page — Counsel Stack

Bluebook (online)
174 S.W. 206, 188 Mo. App. 467, 1915 Mo. App. LEXIS 101, Counsel Stack Legal Research, https://law.counselstack.com/opinion/neuwirth-v-moydell-moctapp-1915.