O'Neil Engineering Co. v. City of Lehigh

1919 OK 151, 182 P. 659, 75 Okla. 227, 1919 Okla. LEXIS 81
CourtSupreme Court of Oklahoma
DecidedMay 13, 1919
Docket6454
StatusPublished
Cited by1 cases

This text of 1919 OK 151 (O'Neil Engineering Co. v. City of Lehigh) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
O'Neil Engineering Co. v. City of Lehigh, 1919 OK 151, 182 P. 659, 75 Okla. 227, 1919 Okla. LEXIS 81 (Okla. 1919).

Opinion

PITCHEORD, J.

This action was commenced in the district court of Atoka county, Okla., on the 23d day of April, 1910, by the city of Lehigh, hereinafter designated as plaintiff, against the O’Neil Engineering Company and the Southern Surety Company, hereinafter designated as defendants. It is claimed by the plaintiff that on the 25th day of July, A. D. 1008, the. defendant'O’Neil Engineering Company entered into a certain contract with the plaintiff for the preparation of plans and specifications and construction of a system of waterworks and an electric light plant for the said town ; that by the terms of said contract the defendant O’Neii Engineering Company obligated itself to prepare and furnish complete plans and specifications for the construction and equipment of a waterworks system and an electric light plant for the town of Lehigh, and to submit an estimate of the cost of said waterworks system and electric light plant, and to make such changes as should be desired by the plaintiff, and to guarantee said estimate by a good and sufficient surety bond. The defendant O’Neil Engineering Company was to employ all laboi, collect all material necessary for the construction of the said waterworks system and electric light plant, and to furnish competent superintendence for the construction of the same. As a consideration for said contract, the town of Lehigh agreed to pay the ‘ defendant O’Neil Engineering Company for its services 10 per cent, of the entire cost of material, labor, machinery, and all other things going into the cost of the construction of said work; that under said contract the defendant O’Neil Enginering Company prepared the plans and specifications for the construction of said waterworks system and electric light plant, and also furnished to the city an estimate of the cost of 'the same; that said estimate estimated the cost of construction of the said waterworks system and electric light plant at the gross sum of $49,000.

On the 25th day of August, 1909, the defendant O’Neil Engineering ••Company and the defendant Southern Surety Company made and executed a certain contract bond for the faithful performance of all the terms of the above-mentoned contract, and further guaranteeing that the total cost of the construction, erection, and completion of said waterworks system and electric light plant should not exceed the sum of $49,000.

It is charged that the defendant O’Neii Engineering Company failed to keep and perform its said contract, and failed to keep and perform the conditions of the bond above mentioned; that it failed to furnish and install certain items therein mentioned of the total value of $238.50, and that it further defaulted in its contract and bond, in that it did not construct, erect, and complete said waterworks system and electric light plant at a cost of not less than $49,000; that, in addition to the failure to furnish the items above mentioned, the plaintiff had been compelled to spend the sum of $53,057.13, making an excess over the guaranteed estimate of the sum of $4,295.71, for which sum the plaintiff asked judgment.

The defendant O’Neil Engineering Company denied the right of the plaintiff to recover, for the reason, as charged by the defendant, that the contract had been changed so that there should be constructed a waterworks system, but not any electric light system ; and charged that the contract had been abandoned as to the electric light system, except as to engine and generator, and that the defendant was released from its obligation to superintend and supervise and furnish labor for the construction of an electric light plant, except as to said engine and generator; and charged that the plaintiff purchased an electric light system already standing and constructed and in existence in lieu of the electric light system designated and contemplated in the original contract, and that in purchasing the same paid therefor the sum of $8.750; and charged that the electric light system was estimated in defendant’s plans, specifications, contracts, and bonds, not including engine and generator,' at $4,479 for construction, and that the purchase of said plant was in lieu of- constructing such a system; that there was not any agreement made between the parties thereafter as to the electric light plant, and that thereby, so far as the .contract for the specifications and construction of the electric light system was concerned, said contract was abrogated, apd claimed that the changes in the contract released the bond sued upon, and demanded judgment against the plaintiff in the sum of $1,020, for commissions remaining unpaid.

The answer filed by the Southern Surety *229 Company was practically tlie same as that filed by its codefendant. On the 12th day of November, 1910, the case was tried and a verdict returned in favor of the city of Lehigh against the O’Neil Engineering Company for the sum of $1,000 and in favor of the Southern Surety Comizany, whereupon it appears a new trial was granted as to the O’Neil Engineering Company ' without protest. On the 17th day of November, 1910, the plaintiff filed a motion for a new trial-as to the Southern Surety Company. On the 23d day of January, 1911, the Southern Surety Company moved to strike the motion for a now trial from the-files, for the reason it was not filed in time. On the 5th day of January. 1912, the motion to strike the motion for a new trial was overruled, and new trial granted as to the Southern Surety Company, to which the surety company duly excepted. On the 7th and 8th days of July, 1913, the cause was again tried before a jury, and a verdict was returned in favor of the plaintiff and against both the defendant in the sum of $4,295.71. The defendants appeal.

The assignments of error are numerous, z-eaching to the number of 46. As we view the questions involved, we deem it unnecessary to consider the assignments of error in the order they are presented, but will content ourselves with three propositions, to which all of the assignments are directed, either directly or indirectly:

“First. Did the court err in granting a new ti-ial as to the defendant Southern Surety Company; the motion for a new trial not being filed in time?
“Second. Was there a material change in the contract?
“Third. Did the court commit error in the instructions given, or refusing to give instructions asked for by the defendants?”

We will consider these points in the order named.

Did the court err in granting a new trial as to the defendant Southern Surety Company? We have seen that the verdict was returned on the 12th day of November, 1910, and that the motion for a new trial was not filed by the plaintiff until the 17th day of November. Under section 5267, Rev. Laws 1910, the district court shall have power to vacate or m!odif.y its own judgments or orders at, or after, the term at which such judgment order was made.

First. By granting a new trial for the cause, within the time, and in the manner prescribed in section 5035. Section 5035 provides that the application for a new trial must be made at the term the verdict, report, or decision is rendered, and, except for the cause of newly discovered evidence, material for the party applying,- which he could not with reasonable diligence have discovered and produced at the trial or impossibility of making a case-made, within three days after the verdict or decision was rendered, unless unavoidably prevented.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Shobe v. Sykes
1934 OK 657 (Supreme Court of Oklahoma, 1934)

Cite This Page — Counsel Stack

Bluebook (online)
1919 OK 151, 182 P. 659, 75 Okla. 227, 1919 Okla. LEXIS 81, Counsel Stack Legal Research, https://law.counselstack.com/opinion/oneil-engineering-co-v-city-of-lehigh-okla-1919.