Snoqualmi Realty Co. v. Moynihan

78 S.W. 1014, 179 Mo. 629, 1904 Mo. LEXIS 39
CourtSupreme Court of Missouri
DecidedFebruary 10, 1904
StatusPublished
Cited by13 cases

This text of 78 S.W. 1014 (Snoqualmi Realty Co. v. Moynihan) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Snoqualmi Realty Co. v. Moynihan, 78 S.W. 1014, 179 Mo. 629, 1904 Mo. LEXIS 39 (Mo. 1904).

Opinion

MARSHALL, J.

— These two cases are cross-appeals from the judgment of the circuit court of St. Louis, in the case of Snoqualmi Realty Company, plaintiff, against Patrick J. Moynihan and the American Surety Company, defendants. The case is a suit upon a builder’s bond for ten thousand dollars, Moynihan being the principal and the American Surety Company the surety in the bond, and the plaintiff the obligee in the bond. The plaintiff claimed $9,154.16 damages for the breaches of the bond. The defendants denied any breaches and all liability, and the surety pleaded release by virtue of various acts of the parties. On motion of the plaintiff, and without objection or exception by the defendants, the cause was referred to E. T. Farish, Esquire, as referee. After a long and thorough trial, the referee made an exhaustive, learned and detailed report, covering seventy-three printed pages, in which he recommended a judgment for the plaintiff for $1,518.09, with interest at the rate of six per cent from the commencement of the suit, on September 28, 1898. Both parties filed extensive exceptions -to the report. The trial court heard the exceptions, and in a forceful and very convincing opinion covering fifteen printed pages,overruled the defendants’ exceptions, and sustained the plaintiff’s exceptions, so far as to increase the plaintiff’s recovery from $1,518.09, as recommended by the referee, to $1,847.69, and allowed interest thereon [634]*634from the' institution of the suit, and entered judgment Tor the plaintiff for $2,099.59.

' After proper steps, both parties appealed. Because the plaintiff’s claim brought the case within the jurisdiction of this court, its appeal was allowed to this court. The defendant’s appeal was allowed to' the St. Louis Court of Appeals, and that court properly certified the case to this court, under the rulings of this court in Ellis v. Harrison, 104 Mo. 280, and Douglas v. Kansas City, 147 Mo. 428. Manifestly the same case can not be pending in two appellate courts at the same time, although upon cross-appeals, for incongruous results might ensue for inconsistent judgments rendered by the two courts. This case illustrates the rule. The defendant, contractor, claims that he owes the plaintiff nothing, and the defendant, surety, claims it was released from liability on the bond. The judgment against them was for $2,099.59. On the other hand the plaintiff got a judgment for $2,099.59, upon a claim for $9,154.16, and appealed because it was not allowed the difference. If the Court of Appeals on the defendant’s appeal should reverse the judgment and hold that the plaintiff was entitled to nothing against the principal in the bond or that the surety was released, and if this court should affirm the judgment on the plaintiff’s appeal or should hold that the plaintiff was entitled to even more than the amount for which it recovered judgment, a manifest incongruity and inconsistency would be the result. Hence the wisdom of holding that in such cases the case can not be split up, but that the whole case must go to the appellate court that has jurisdiction of the appeal by either party.

The controversy is this:

The plaintiff contracted with the defendant Moynihan to build for it a certain house, upon lot numbered 66 in Bell Place, in St. Louis, according to plans and specifications drawn therefor by architect J. B. Legg, at an agreed price of $18,800. The contract was executed on [635]*635November 7,1896, and tbe work was to be completed by August 1, 1897. Tbe work was not completed on October 1,1897, and on that day tbe plaintiff took possession ■over tbe objection of tbe contractor. During tbe progress of tbe work tbe plaintiff paid tbe contractor tbe sum of- $13,000. After differences arose and after tbe plaintiff took possession, and to avoid tbe expense of mechanic's liens, tbe plaintiff, under a tripartite agreement between tbe plaintiff, tbe contractor and tbe .surety, paid to tbe sub-contractors and materialmen tbe further sum of $6,590.69. The plaintiff concedes that tbe defendant, contractor, was entitled to $235 for extra wainscoting, and to $15 for extra partition wall in third story, in addition to tbe contract price of $18,800, thus increasing tbe plaintiff’s credit to $19,050. And thus tbe plaintiff shows that it overpaid tbe contractor in tbe sum of $540.69, for which it asks judgment.

Tbe plaintiff further claims that tbe contractor did not complete tbe work at tbe time agreed and that by tbe terms of tbe contract it is entitled to recover five dollars a day as liquidated damages from August 1, 1897, to November 1,1897, aggregating $540 for tbe delay.

Tbe plaintiff further claims that tbe contractor failed to put into tbe bouse tbe kind and quality of tbe mahogany, cherry, bird’s eye maple and oak wood requided by tbe specifications, and instead thereof tbe plaintiff was forced to have tbe work done over, at a cost to tbe plaintiff of $5,822, for which it also asks judgment.

Tbe plaintiff also claims $783.25 on account of improper stone work put in by tbe contractor, and further claims $429.77 on account of defective granitoid walks and driveways put in by tbe contractor; and further .claims $91.50 for cost of repairs to tbe woodwork made necessary by tbe reconstruction of tbe hardwood work aforesaid; and further claims $408.81 on account of certain minor items of cost in completing tbe work contracted for; and also claims $595 for cost of watchmen [636]*636and of coal for heating the house while the work of completing and correcting the work contracted for was being done after the plaintiff got possession. Thus making an aggregate claim of $9,450.02, from which the plaintiff allows a deduction of $100.60 on account of the sum realized by the plaintiff for the sale of the materials that were put in by the contractor and rejected by the plaintiff.

On the other hand the contractor denies any liability to the plaintiff, and says the work was done according to the contract and specifications and to the directions of the architect, and pleads that the delays were caused by the acts and interferences of the plaintiff.

The surety denies that there is anything owing to the plaintiff, and pleads that it was released, by force of various acts of the plaintiff, which are fully set out and which will be stated and considered in the course of the opinion.

The referee allowed the plaintiff $440.09 for overpayment, and $1,078 for reconstructing the woodwork in the parlor, the library, the bedroom over the parlor, and the painting in the room over the dining room, aggregating $1,518.09, and found against the plaintiff on all of the other claims, and found against the defendants on their other claims and defenses. The circuit court approved all the findings of the referee, except as to the painting in the bedroom over the dining room, for which the referee had allowed one hundred dollars, and in lieu thereof found that the plaintiff was entitled to $329 for refinishing that room, and except as to '$100 realized by the plaintiff from the sale of the rejected materials, which the court disallowed, and entered judgment for the plaintiff for $1,847.69 with interest.

The facts necessary to be considered in the determination of the case will be stated in the opinion. For the sake of convenience the plaintiff’s contentions will be considered first, and those of the defendant afterwards.

[637]*637I.

Overpayment.

The trial court properly held that the plaintiff was entitled to recover. $540.69 for overpayments.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Heiden v. General Motors Corp.
567 S.W.2d 401 (Missouri Court of Appeals, 1978)
Walsh v. Southwestern Bell Telephone Co.
52 S.W.2d 839 (Supreme Court of Missouri, 1932)
Jacobs v. Danciger
41 S.W.2d 389 (Supreme Court of Missouri, 1931)
Walker v. Gateway Milling Co.
92 S.E. 826 (Court of Appeals of Virginia, 1917)
Coyle v. United States Gypsum Co.
1917 OK 191 (Supreme Court of Oklahoma, 1917)
Sandusky v. Sandusky
177 S.W. 390 (Supreme Court of Missouri, 1915)
Neuwirth v. Moydell
174 S.W. 206 (Missouri Court of Appeals, 1915)
Pulaski Hall Ass'n v. American Surety Co.
143 N.W. 715 (Supreme Court of Minnesota, 1913)
Fellows v. Dorsey
157 S.W. 995 (Missouri Court of Appeals, 1913)
Sonnenfeld v. Rosenthal
152 S.W. 321 (Supreme Court of Missouri, 1912)
Connelly v. Illinois Central Railroad
153 S.W. 79 (Missouri Court of Appeals, 1912)
Citizens Coal Mining Co. v. McDermott
84 S.W. 459 (Missouri Court of Appeals, 1904)

Cite This Page — Counsel Stack

Bluebook (online)
78 S.W. 1014, 179 Mo. 629, 1904 Mo. LEXIS 39, Counsel Stack Legal Research, https://law.counselstack.com/opinion/snoqualmi-realty-co-v-moynihan-mo-1904.